Earned Value Management (EVM): How Much is Enough?

I took the scenic route to selecting the theme of this blog. First, it was suggested that I write a blog on the benefits and costs of the earned value process as it applies to program management. Next it was suggested that I describe the harm of not using any of the elements of the earned value process.

This blog summarizes my observations of how companies have chosen “how much EVM is enough” for them and share my observations of the results of these decisions. Each company has selected an EVM implementation strategy and each company’s strategy falls along a bounded continuum.

Two Goal Posts and a Cross Bar

There are as many strategies for implementing earned value management as there are companies using EVM to manage their programs and projects.

I will describe this continuum of company EVM strategies as a left goal post and a right goal post with the space between as a cross bar. The “left goal post” represents companies that elect to be very poor at EVM or to not use EVM at all. The “right goal post” represents companies that have committed to being “best-in-class” practitioners of the EVM process and are the polar opposite of the companies at the left goal post. There are few companies at either the left or right goal posts. The “cross bar” represents the vast majority of companies that have selected an EVM strategy somewhere between the left and right goal posts.

Left Goal Post: The Unwilling

I have firsthand experience with a company that at the time I initially joined them, had decided to ignore earned value management even though it was a requirement in several of its contracts. After many painful years of attempting to maintain this EVM resistant strategy, this company decided that a better strategy would be to become an “efficiently expert” at EVM.

Cross Bar: Merely Compliant at EVM

It has been my experience that most companies desire to become “EVM compliant,” which generally means being compliant with the EIA-748 Standard for EVMS 32 guidelines and to avoid failing to comply with those guidelines that could result in losing their approved or certified EVMS status. This is the vast middle ground between the two goal posts. I have five observations regarding companies in the “cross bar” majority.

Observation #1: Compliance as a Goal

Compliance should be a given or a pre-condition, not a goal. Remaining merely compliant implies a status quo or static posture.

I will use the game of golf as an analogy. Golf is a game of honor and compliance to well established rules. All PGA professional tour golfers “comply” with the rules that govern golf. Although all PGA tour pro golfers comply with these rules, their performance on tour differs dramatically.

Ninety percent of all PGA golf pros, past and present, have no tour wins. That means only 10% of all PGA tour golf pros have won at least a single PGA tour. There are seven players in the history of the PGA that have fifty or more tour wins. If the bar is lowered to forty or more wins, only three players are added to the list. If the bar is lowered yet again to thirty or more tour wins, only eight more players are added to the list. Only 18 golfers have won 30 or more PGA tournaments.

Professional golfers do not confuse compliance with performance, nor do these professionals assume that “being compliant” will improve their performance.

Observation #2: The Tyranny of the Status Quo

With apologies to Milton Friedman and his book of the same name, companies that attempt to maintain mere guideline compliance will do no better than the status quo, and often regress toward non-compliance. Maintaining status quo is a myth – you either improve or regress.

All professionals, companies included, must compete in their markets and selected fields. To succeed in this competition requires constant improvement in areas critical to success. A company, organization, or individual without the means or the desire to improve will eventually fail and perhaps perish.

Observation #3: Blaming the Scoreboard

As a program manager, I considered EVM as my scoreboard. I reacted to the EVM data – the scoreboard – and made decisions based on that data (Guideline 26: Implement managerial actions taken as the result of earned value information).

I recall the 2024 Super Bowl’s final score: Chiefs 25, 49ers 22. Did the scoreboard cause the 49ers to lose the game or did a poor decision by their coach cause the loss?  Imagine a coach that cannot see the scoreboard. That coach does not know the score or how much time remains. That coach cannot react to the realities of the game.

Observation #4: EVM Causes Poor Program Performance

I have witnessed several company leaders assert that the use of EVM on a poorly performing program is the cause of that program’s poor cost and schedule performance. A correlation between two variables, or a sequence of two variables (use of EVM and poor performance), does not imply that one caused the other. This is the logical fallacy known as “X happened, then Y happened, therefore X caused Y.”  Night follows day, but day does not cause night. Use of EVM does not cause poor program performance. Not reacting to EVM data and promptly taking corrective action with your program’s cost and schedule performance often leads to poor outcomes.

Observation #5: It Takes More Energy to be Poor at EVM than to be an Expert

Returning to the earlier golf analogy, professional golfers make very difficult shots appear easy. I played in a pro/am tournament years ago. The pro I was teamed with took me to the range hours before our tee time. He asked me how many balls I hit before each round. I told him sometimes none and sometimes 50. He hit 1,000 balls before our round. When we finished our round, he was ready for another 18 holes. I was not. Both of us “complied” with the rules of golf. His score was significantly lower than mine. His game was effortless and produced a below par score. My game was labored and produced a poor result.

It is the same with EVM or any other process. The better you are at a skill, the easier it becomes. Experts consume far fewer calories at their craft than ambivalent amateurs.

Right Goal Post: Efficiently Expert at EVM

The polar opposite of a resistant EVM strategy is a strategy to become “efficiently expert.”  As I mentioned earlier, I joined a company that attempted to sustain an EVM resistant strategy. Their EVM strategy led to de-certification, large dollar withholdings, and significant damage to their corporate reputation.

After the most ardent EVM opponents in this company sought employment elsewhere, a new strategy was adopted. This company embraced a strategy to become “best-in-class” as expert practitioners of EVM. This company’s goal was EVM perfection. EVM perfection is an impossible ambition, but wiser than “mere compliance.”  And as with the PGA tour golf pro, EVM became nearly effortless.

Which EVM strategy will your company choose?

—

Mr. Kenney is a senior business executive with over 35 years of experience in the aerospace industry as well as over 10 years as a consultant to industry. He is an experienced practitioner of program management best practices as an Executive Vice President of Government Programs, Vice President of Naval Programs, and Program Manager at various aerospace and defense contractors. He is also a retired U.S. Marine Corps Colonel with 27 years of active and reserve duty.