EVMS Guidelines

EVMS Guidelines 2 – Five Sections of Organizational Guidelines

, , ,

Video Contents

The EVMS Guidelines are Grouped in five major categories which address these five sections:

0:12 – Organization
0:32 – Planning, Scheduling, and Budgeting
0:46 – Accounting Considerations
0:56 – Analysis and Management Reports
1:15 – Revisions and Data Maintenance


More EVMS Training

If you liked this video you can purchase the entire course below. This video is an excerpt from the Department of Defense (DOD) version of this eLearning module. We also offer the same course customized for the Department of Energy’s (DOE) specific Earned Value Management (EVM) implementation/requirements, as well as a version of the course customized for NASA’s EVM implementation/requirements.  

— Purchase This Course —
EVMS DOD Virtual Learning Lab

— Purchase the DOE Version of this Course —
EVMS DOE Virtual Learning Lab

— Purchase the NASA Version of this Course —
EVMS NASA Virtual Learning Lab


EVMS Document Matrix

EVMS Document Matrix

Not sure what the different requirements are between the DOE and NASA? Can’t remember if Cost and Software Data Reporting (CSDR) is required for an NSA contract? Check out our easy to read Earned Value Management Systems Document Matrix


All Online Courses

All Online Courses Available from Humphreys & Associates

Earned Value Training

EVMS Guidelines 2 – Five Sections of Organizational Guidelines Read Post »

EVMS Guidelines and Required Elements

, , , , ,

Video Contents

This video reviews the data points that an Earned Value Management System provides and how variances can be calculated from those data points.  Timely analysis of performance data and variances assists contractors to proactively resolve issues and effectively manage the remaining work on a project.

You can use the links below to jump to a specific part of the video.

Earned Value Contractors’ Internal Systems must be able to provide the following:
00:06Budgeted Cost for Work Scheduled (BCWS)
00:26Budgeted Cost for Work Performed (BCWP)
00:38Actual Cost of Work Performed (ACWP)
00:47Buget At Completion (BAC)
00:52Estimate At Completion (EAC)

Variances can be calculated using the BCWS, BCWP, ACWP, BAC and EAC.
00:58Variances Explanations
01:03Schedule Variance (SV)
01:19Cost Variance (CV)
01:31Variance at Completion (VAC)
01:45Why do we calculate Variances?


01:54EAC and BAC Comparison
2:06What does Variance at Completion (VAC) indicate?
2:18Structure your Earned Value Management System so that Variances can be traced to their source.
2:32Use your existing project management systems.

We also have additional free resources for learning about

You can also find Earned Value Definitions as well as additional free resources for learning more about EVMS concepts like Budgeted Cost for Work Performed (BCWP), Actual Cost of Work Performed (ACWP), Buget At Completion (BAC), and Estimate At Completion (EAC) in our EVMS Education Center and in other posts on this blog.


More EVMS Training

If you liked this video you can purchase the entire course below. This video is an excerpt from the Department of Defense (DOD) version of this eLearning module. We also offer the same course customized for the Department of Energy’s (DOE) specific Earned Value Management (EVM) implementation/requirements, as well as a version of the course customized for NASA’s EVM implementation/requirements.  

— Purchase This Course —
EVMS DOD Virtual Learning Lab

— Purchase the DOE Version of this Course —
EVMS DOE Virtual Learning Lab

— Purchase the NASA Version of this Course —
EVMS NASA Virtual Learning Lab


EVMS Document Matrix

EVMS Document Matrix

Not sure what the different requirements are between the DOE and NASA? Can’t remember if Cost and Software Data Reporting (CSDR) is required for an NSA contract? Check out our easy to read Earned Value Management Systems Document Matrix


All Online Courses

All Online Courses Available from Humphreys & Associates

Earned Value Training

EVMS Guidelines and Required Elements Read Post »

EVMS Guidelines and Objectives

,

An overview of Earned Value Guidelines and Objectives. These are the key building blocks for a successful Earned Value Management System.

Video Contents

You can use the links below to jump to a specific part of the video.
0:05 – Helpful Earned Value Management System Elements
0:35 – EIA-748-C EVMS Guidelines
1:22 – EVMS Objectives
2:10 – Policy and Procedures
3:00 – Integrated Baseline Review (IBR)

More EVMS Training

If you liked this video you can purchase the entire course below. This video is an excerpt from the Department of Defense (DOD) version of this eLearning module. We also offer the same course customized for the Department of Energy’s (DOE) specific Earned Value Management (EVM) implementation/requirements, as well as a version of the course customized for NASA’s EVM implementation/requirements.  

— Purchase This Course —
EVMS DOD Virtual Learning Lab

— Purchase the DOE Version of this Course —
EVMS DOE Virtual Learning Lab

— Purchase the NASA Version —
EVMS NASA Virtual Learning Lab


EVMS Document Matrix

Not sure what the different requirements are between the DOE and NASA? Can’t remember if Cost and Software Data Reporting (CSDR) is required for an NSA contract? Check out our easy to read Earned Value Management Systems Document Matrix


All Online Courses

All Online Courses Available from Humphreys & Associates


Other Posts in this Series

EVMS Guidelines and Objectives Read Post »

EIA 748-D Released – Change Notes

,

EIA 748 D Released

Portions extracted from the EIA-748-D © SAE International (with permission).

Are you aware that a revision to the Society of Automotive Engineers (SAE) / Electronics Industry Alliance (EIA)  Standard 748 Earned Value Management Systems, has been released? The new revision is SAE / EIA 748-D. Officials have been discussing the changes at recent industry conferences.

Sections 2.1-2.5 – No Changes to EVMS Guidelines

No changes have been made to the 32 EVMS Guidelines in Sections 2.1-2.5 of the standard. The changes are primarily clarifications of the existing text:

Section 1 – Additional 4th Note

Section 1 “Scope of EVMS” previously “Introduction” in 748-C now has an additional 4th Note:

“Note 4: There are occasions where it is beneficial for complementary systems or methodologies (e.g., Enterprise/ Manufacturing Resource Planning, Agile Software Development, Theory of Constraints) to interface with the EVM System. These complementary systems or methodologies can be used to deliver functionality and value to the customer while EVM provides a standardized method for measuring progress and reporting across the contract. The EVMS documentation should describe the interface content as well as the recurring control process to maintain data conformance and system compliance.” © SAE

Section 2.6 –  Six Additional Terms

Section 2.6 “Common Terminology” includes six additional terms:

ACTIVITY OR TASK: An element of work with an expected duration in the network schedule that is performed during the course of a project. Activities generally have expected resource requirements used to determine the budget for the work effort. One or more activities may relate to a work package.

AUTHORIZED UNPRICED WORK (AUW): A contract scope change which has been directed by the customer’s contracting officer but has not yet been fully negotiated/definitized. It includes a value, excluding fee or profit, typically associated with the authorized, unpriced change order.

ELEMENT OF COST (EOC): The categories of cost such as labor, material, subcontractor, and other direct costs as defined by company accounting practices.

OVER TARGET SCHEDULE (OTS): A replanned schedule baseline that extends beyond contract milestone dates, delivery dates, or completion date. An OTS is usually accompanied by an increase in budgets resulting in a corresponding Over Target Baseline (OTB). It typically requires customer approval to implement.

RISK AND OPPORTUNITY (R&O): An uncertain future event or situation that could impact the ability to achieve overall project requirements within defined cost, schedule, and technical objectives. Risk has two components: (1) the probability (or likelihood) of a particular outcome and (2) the consequences (or impact) of that outcome. The consequences of risks are typically thought of as negative that may need to be mitigated to minimize the impact to the project. A risk event with positive consequences is referred to as an opportunity that may be captured as a benefit to the project.

SUMMARY LEVEL PLANNING PACKAGE (SLPP): An aggregation of far-term work efforts (scope, schedule, and budget) that are not able to be identified at the control account level but can be distributed to reporting level WBS elements.

Section 2.6 – Term Changes

Section 2.6 “Common Terminology” includes changes/clarifications to existing terms:

ESTIMATE AT COMPLETION (EAC): The current estimated total cost for authorized project work. It equals the cumulative to date Actual Cost of Work Performed (ACWP) plus the estimated costs to complete (Estimate to Complete or ETC) the authorized work remaining.

LEVEL OF EFFORT (LOE): Support type activities that lack measurable output or product that cannot be discretely planned or objectively measured in a practical manner. LOE automatically earns performance with the passage of time, an earned value technique.

MANAGEMENT RESERVE (MR): An amount of the total budget set aside for unplanned, in scope effort that may arise during the course of the project which cannot be identified in advance and is used to handle execution risks. Management reserve budget should be commensurate with the level of project risk. It is not part of the Performance Measurement Baseline (PMB).

OVER-TARGET BASELINE (OTB): A Performance Measurement Baseline (PMB) that exceeds the Contract Budget Base (CBB). It is implemented to produce a realistic schedule and budget plan for the project’s remaining work. It typically requires customer approval to implement.

Section 2.7 – 3 Additional References

Section 2.7 “List of Suggested References” has been updated to include 3 additional references. The complete list is below:

– NDIA IPMD EVMS Intent Guide
– NDIA IPMD IBR Guide
– NDIA IPMD Surveillance Guide
– NDIA IPMD EVMS Acceptance Guide
– NDIA IPMD EVMS Application Guide
– NDIA IPMD Planning and Scheduling Excellence Guide (PASEG)
– NDIA IPMD Industry Practice Guide for Agile on Earned Value Management Programs (New)
– NDIA IPMD Master Definitions List for IPMD Guides (New)
– NDIA IPMD Earned Value Management System Guideline Scalability Guide (New)

Sections 3 thru 5

In Section 3.2.1 WBS Dictionary, discussion regarding segregation by WBS element for direct costs has been removed.

In Section 3.3.1 Control Accounts, discussion regarding guidance that a Control Account shall not span multiple WBS elements has been removed.

In Section 3.3.1, a new figure, Figure 1 – Establishing Control Accounts was added.

In Section 3.4.3 Subcontract/Procurement Schedules, the phrase “high risk” has been removed.

In Section 3.8.2 Cost Performance, The Labor Rate and Efficiency variance calculations were corrected. The corrected equations are below.

• Labor Rate Variance Calculation = Actual Hours x (Earned Rate – Actual Rate)
• Efficiency Variance Calculation = Earned Rate x (Earned Hours – Actual hours)

In Section 3.8.2 Cost Performance, the acronym “EAC” has been replaced with “ETC”.

In Section 3.10.2 Authorized Changes, discussion regarding allowable changes for optimum utility has been removed.

In Section 4 System Documentation, the term “GEIA” has been replaced with “SAE”.

In Section 5.1, Evaluation Process, the term “officer” has been replaced with “authority”.

In summary, EIA 748-D has added/modified a few items for clarification but does not change any of the implementation, reporting, surveillance, or enforcement aspects of Earned Value Management Systems.

Purchase a copy of the standard here: https://www.sae.org/standards/content/eia748d/

EIA 748-D Released – Change Notes Read Post »