DFARS

Clarification on the New Department of Defense Earned Value Management System EVMS Thresholds | DOD & DPAP

, , , , , , , , , , , , , , , ,

New Department of Defense Earned Value Management System (EVMS) ThresholdsOn September 28, 2015, the Defense Procurement and Acquisition Policy Directorate (<abbr=”Defense Procurement and Acquisition Policy Directorate”>DPAP) released a memorandum entitled “Class Deviation – Earned Value Management System Threshold”. In this memo the DoD changed the threshold for <abbr=”Earned Value Management System”>EVMS application to $100 million for compliance with EIA-748 for cost or incentive contracts and subcontracts. That same memorandum stated that no EVMS surveillance activities will be routinely conducted by the Defense Contract Management Agency (<abbr=”Defense Contract Management Agency”>DCMA) on contracts or subcontracts between $20 million to $100 million. As attachments to this memorandum, there was a reissuance of the Notice of Earned Value Management System <abbr=”Department of Defense Federal Acquisition Regulations”>DFARs clause (252.234-7001) and the Earned Value Management Systems DFARs clause (252.234-7002), with both reflecting the new $100 million threshold.In response to this guidance, a series of questions from both contractors and other government personnel were submitted to Shane Olsen of the DCMA EVM Implementation Division (<abbr=”EVM Implementation Division”>EVMID). Below are the salient points from this communication:

  • There will be no EVMS surveillance of DFARs contracts under $100 million. Contracts without the DFARs clause, such as those under other agencies using the FAR EVM clause, will continue surveillance under their current thresholds.
  • The $100 million threshold is determined on the larger of the contract’s Ceiling Price or Target Price; as reported on the Integrated Program Management Report (IPMR) or Contract Performance Report (CPR) Format 1.
  • The threshold is based on the Contract Value including fee (at Price) as noted above. If there is an approved Over Target Baseline (OTB) which increases the Total Allocated Budget (TAB), this cannot push a contract over the threshold.
  • The new thresholds not only apply to subcontracts, but also Inter-organizational work orders with an EVMS flow-down.
  • Regardless of the circumstances, the DCMA will not conduct surveillance on contracts less than $100 million. However, if there are Earned Value issues that the buying command or other parties believe need to be reviewed, then the DCMA may conduct a Review for Cause (RFC) of the system against potentially affected guidelines.
  • The DCMA Operations EVM Implementation Division (EVMID) will not be conducting Compliance Reviews in FY-2016 unless there is an “emergent need”.
  • If a site is selected for a Compliance Review, only contracts greater than $100 million would be in the initial scope of the Implementation Review (IR). However, if an issue is discovered that requires the team to “open the aperture”, other contracts are not precluded.

The DCMA is still working on a response to the following questions:

  • How do I handle a contract that is currently below $100 million but has options that, in aggregate, would exceed $100 million?
  • How is the contract value determined on:
    • Indefinite Delivery/Indefinite Quantity (ID/IQ) Contracts
    • Non-ID/IQ with Multiple CLIN-Level or Task Order reports?

This blog will be updated and reposted as answers to these questions are given.

Clarification on the New Department of Defense Earned Value Management System EVMS Thresholds | DOD & DPAP Read Post »

Earned Value Management Implementation Guide (EVMIG) Rescinded

, , , , , , , ,

Earned Value Management Implementation Guide (EVMIG) Rescinded | DFARSThe DoD EVM Implementation Guide (EVMIG, Oct 2006) was rescinded on September 15, 2015 by the Office of Performance Assessments and Root Cause Analysis (PARCA). The EVMIG had provided guidance for understanding Earned Value Management System (EVMS) concepts; detailed procedures for implementing the EIA-748 EVMS Standard, Earned Value Management Systems (EVMS), on government contracts; tailoring guidance for EVMS application and reporting; and post award procedures. Most of the details contained in the EVMIG are also available in other, more recent, publications and the EVMIG is replaced with these other references. EVM System information can be found in the DoD EVM System Interpretation Guide (EVMSIG) which provides overarching DoD interpretation of the 32 EIA-748 EVMS guidelines. Additional information can be found in multiple Defense Contract Management Agency (DCMA) compliance instruction documents.

PARCA identified the following references to replace the contents and guidance found in the EVMIG:

EVM Concepts and Guidelines
EVM Concepts TBD EVM Analysis Guide
Defense Acquisition University (DAU) EVM Community of Practice
PARCA EVM Website
EVM System (EVMS) Concepts EVMSIG
DCMA Surveillance Guide

 

Procedures For Government Use of EVM
Organizational Roles and Responsibilities TBD EVM Application Guide
PARCA EVM Website
Defense Acquisition Guide (DAG)
WBS Development and Use MIL-STD-881C
TBD EVM Application Guide
EVM/EVMS Policy and Application TBD EVM Application Guide
PARCA EVM Website
Cost and Schedule Reporting Integrated Program Management Report (IPMR) Data Item Description (DID) and IPMR Guide
TBD EVM Application Guide
EVMS System Compliance EVMSIG
DCMA Surveillance Guide
Integrated Baseline Review (IBR) Program Manager’s Guide to the Integrated Baseline Review (IBR)
TBD EVM Application Guide
Reprogramming Formal Reprogramming Over Target Baseline (OTB)/Over Target Schedule (OTS) Guide
EVMSIG
Training Defense Acquisition University Website
PARCA EVM Website

Earned Value Management Implementation Guide (EVMIG) Rescinded Read Post »

DoD Earned Value Management System Interpretation Guide | EVMSIG

, , , , ,

The updated DoD Earned Value Management System Interpretation Guide (EVMSIG), dated February 18, 2015 was released in March, 2015.

This DoD update, per the GAO, focuses on “(1) problems facing the cost/schedule control system (CS2) process; (2) progress DOD has made with reforms; and (3) challenges DOD faces in fostering and managing potentially significant changes”.

The update commences with:

EVMSIG INTRODUCTION

1.1 Purpose of Guide

Earned Value Management (EVM) is a widely accepted industry best practice for program management that is used across the Department of Defense (DoD), the Federal government, and the commercial sector. Government and industry program managers use EVM as a program management tool to provide joint situational awareness of program status and to assess the cost, schedule, and technical performance of programs for proactive course correction. An EVM System (EVMS) is the management control system that integrates a program’s work scope, schedule, and cost parameters for optimum program planning and control. To be useful as a program management tool, program managers must incorporate EVM into their acquisition decision-making processes; the EVM performance data generated by the EVMS must be timely, accurate, reliable, and auditable; and the EVMS must be implemented in a disciplined manner consistent with the 32 EVMS Guidelines prescribed in Section 2 of the Electronic Industries Alliance Standard-748 EVMS (EIA-748) (Reference (a)), hereafter referred to as “the 32 Guidelines.”

The DoD EVMS Interpretation Guide (EVMSIG), hereafter referred to as “the Guide”, provides the overarching DoD interpretation of the 32 Guidelines where an EVMS requirement is applied. It serves as the authoritative source for EVMS interpretive guidance and is used as the basis for the DoD to assess EVMS compliance to the 32 Guidelines in accordance with Defense Federal Acquisition Regulation Supplement (DFARS) Subpart 234.2 and 234.201 (References (b) and (c)). The Guide provides the DoD Strategic Intent behind each guideline as well as the specific attributes required in a compliant EVMS. Those attributes are the general qualities of effective implementation that are tested in support of determining EVMS compliance as it relates to the 32 Guidelines. As applicable, the DoD Strategic Intent section may clarify where differences in guideline interpretation exist for development and production type work. DoD agencies and organizations charged with conducting initial and continuing EVMS compliance activities will establish amplifying agency procedures and/or guidance to clarify how they are implementing this Guide to include the development of evaluation methods for the attributes associated with each of the 32 Guidelines.

1.2 EVM Policy

The Office of Management and Budget Circular No. A-11 (Reference (d)), the Federal Acquisition Regulation (FAR) Subpart 34.2 and Part 52 (References (e) through (h)) require federal government agency contractors to establish, maintain, and use an EVMS that is compliant with the 32 Guidelines on all major capital asset acquisitions. Based on these federal regulations and the DoD Instruction 5000.02 (DoDI 5000.02) (Reference (i)), the DoD established the Defense Federal Acquisition Regulation Supplement (DFARS) 234.201 (Reference (c)), which prescribes application of an EVMS, via the DFARS 252.234-7002 EVMS clause (Reference (j)). When EVM reporting is contractually required, the contractor must submit to the government an Integrated Program Management Report (IPMR) (DI-MGMT-81861) (Reference (k)) to report program cost and schedule performance data. The IPMR is being phased in to replace the Contract Performance Report (CPR) (DI-MGMT-81466) and the Integrated Master Schedule (IMS) (DI-MGMT-81650). Hereafter, for simplicity purposes, the term “IPMR” is used to reference legacy or current CPR/IMS DIDs. There are times in this Guide when the IMS reference is to an output of the contractor’s internal management system, i.e., a work product, which may not be referred to in the same context as the IPMR. [The full EVMSIG update is found here.]

Furthermore, also in March, 2015 the GAO released its “Report to the Committee on Armed Services, House of Representatives: Defense Acquisition | Better Approach Needed to Account for Number, Cost, and Performance of Non-Major Programs”.

An overview:

The Department of Defense (DOD) could not provide sufficiently reliable data for GAO to determine the number, total cost, or performance of DOD’s current acquisition category (ACAT) II and III programs (GAO-15-188Better Approach Needed to Account for Number, Cost, and Performance of Non-Major Programsoverview). These non-major programs range from a multibillion dollar aircraft radar modernization program to soldier clothing and protective equipment programs in the tens of millions of dollars. GAO found that the accuracy, completeness, and consistency of DOD’s data on these programs were undermined by widespread data entry issues, missing data, and inconsistent identification of current ACAT II and III programs. See the figure below for selected data reliability issues GAO identified. [The full GAO-15-188 document is found here.]

DoD Earned Value Management System Interpretation Guide | EVMSIG Read Post »

Earned Value Management for Biotech and Pharma – Part 2 Accounting

By Ric Brock – Engagement Director, Humphreys & Associates

As a follow up to our article on the Earned Value Management for Biotech and Pharma Industries, this is a quick look at how Biotech and Pharma companies collect and manage costs compared to accounting requirements on federal acquisitions.

The Operating Model for the Biotech and Pharma Industry

The basis of the Biotech and Pharmaceutical operating model is to discover/invent a compound or device to meet a need, validate its safety and efficacy, ensure proper patent protection, market it as quickly as possible, and maximize commercialization while there is still patent protection.  In short, it is about speed to market and maximizing the commercial life cycle.

Operating costs are collected and managed from a process costing basis.  Internal costs are usually not collected by a cost objective, as they are not managed to that level of detail.  Most internal labor is collected by department total headcount and labor dollars.  Project or activity based timekeeping is not practiced; i.e. time cards are not used.  External costs (materials, contract services, subcontractors, etc.) are collected within the purchasing system and can be tied to specific activities and traced to the originating departments.  Most companies do have the ability to set up and track job costs within their capital management system.

Federal Acquisition Regulations (FAR), Cost Accounting Standards (CAS), and Timekeeping

The ability to plan and collect actual costs in a consistent and systematic manner by contract/project is a key to the Earned Value Management System requirement.  The costing of items and services purchased by the US Government on a non-firm fixed price basis are covered in the Federal Acquisition Regulations (FAR) and the Cost Accounting Standards (CAS).  The ability to collect costs in a consistent and timely manner is an EVMS prerequisite.

Federal Acquisition Regulations

Federal Acquisition Regulations (FAR) are a set of regulations governing the US Government processes of purchasing goods and services.  Among the guiding principles are to have an acquisition system that satisfies the customer’s needs in terms of cost, quality, and timeliness; to conduct business with integrity, fairness, and openness; and to fulfill other public policy objectives.

Part 52 of the FAR contains standard contract clauses and solicitation provisions. Many clauses incorporate parts of the FAR into government contracts by reference, thereby imposing FAR rules on contractors.

Part 30 of the FAR describes policies and procedures for applying the Cost Accounting Standards Board (CASB) rules and regulations [48 CFR Chapter 99 (FAR Appendix)] to negotiated contracts and subcontracts. This part does not apply to sealed bid contracts or to any contract with a small business concern [see 48 CFR 9903.201-1(b) (FAR Appendix) for these and other exemptions].  Part 30 also identifies the standard contract clauses and solicitation provisions contained in FAR Part 52 that are to be incorporated when applying the CASB rules and regulations to a contract or subcontract.

When a government agency issues a contract or request for proposal, it will specify a list of FAR clauses that will apply.  In order to be awarded the contract, a bidder must either comply with the clauses, demonstrate that it will be able to comply at time of award, and/or claim an exemption from them.  A bidder must also ensure that it understands the contractual commitments, as complying with some FAR clauses may require changes to operating processes.

Cost Accounting Standards

Cost Accounting Standards (CAS) are a set of 19 standards and rules (CAS 401 – 420) that the US Government uses in determining the costs on negotiated procurements.

A company may be subject to full CAS coverage (required to follow all 19 standards), modified CAS coverage (required to follow only Standards 401, 402, 405, and 406), or be exempt from coverage.

Full coverage applies only when a company receives either one CAS-covered contract of $50 million or more, or a number of smaller CAS covered contracts totaling $50 million. In addition to complying with the standards, the company must also file a CAS Disclosure Statement (CASB DS-1) which clearly describes the company’s accounting practices (such as what costs are treated as direct contract charges and what costs are treated as part of an overhead expense). There are two versions of the CAS Disclosure Statement: DS-1 applies to commercial companies while DS-2 applies to educational institutions.

Modified coverage applies when a company receives a single contract of $7.5 million or more. 

Timekeeping

Despite the significant role timekeeping plays in government contracting, the FAR provides little direction on timekeeping.  This lack of guidance has been left to government audit agencies (such as the Defense Contract Audit Agency (DCAA) to establish audit standards.  The DCAA uses its Contract Audit Manual (CAM) to provide audit guidance to its auditors.  The CAM provides guidance on auditing timekeeping procedures in section 5-909.  The audit manual states that timekeeping procedures should be able to “assure that labor hours are accurately recorded and that any corrections to timekeeping records are documented…”.

This timekeeping system should feed a labor distribution system that maintains labor hours and dollars by employee, by project/contract, and type of effort account.  This labor distribution should be reconciled to the general ledger labor accounts at least monthly.

Timekeeping is critical.  Unlike other contract costs, labor charges are not supported by external documentation.  The move by a Biotech/Pharma company to a formal timekeeping system may require extensive cultural change.

Summary

As Biotech and Pharmaceutical companies move to FAR contracting, it will require a transition to a project/job costing basis from a process costing basis.  This change may appear straight forward, but any process change requires sound change management.

All aspects of EVMS are critical to ensure the utility of an effective program management tool.  In this blog we provided a summary level look at cost accounting data.  The ability to collect valid, timely, and auditable cost is the foundation for the Actual Cost of Work Performed (ACWP).  Without knowing what we accomplished and what we spent to get to where we are, it is very hard to predict where we are going: the Estimate to Complete (ETC).   As a company designs and develops its EVMS, it must make sure actual cost collection and management is also addressed within the FAR and CAS requirements.

For questions or inquires on how to implement Earn Value project management in the biotechnology or pharmaceutical industries, contact one of the experts at Humphreys & Associates.

Ric Brock - Engagement Director, Humphreys & AssociatesMr. Brock has over 30 years of experience in program and project management, operations, and quality assurance in government and commercial environments.  He has extensive experience working with all levels of an organization, from top management to performing personnel. Ric has extensive experience supporting Pharmaceutical companies in life cycle management, filing new drug applications, and launching new drugs.  He has a wealth of experience with EVM systems across a variety of industries from defense to commercial including biotech/pharma. You can find Ric on LinkedIn

 

Earned Value Management for Biotech and Pharma – Part 2 Accounting Read Post »

DFARS 252.234-7001 – “Thou Shalt Do Earned Value”

Overview

Earned Value Management (EVM) have become increasingly relevant for industries like Biotech and Pharma.

Hypothetically, your organization has received a Request for Proposal (RFP) and wishes to bid for the work.  The RFP includes the clause DFARS 252.234-7001 if the cost to the government is anticipated to be in excess of $20M.  What choices does a company have?  First, the clause could be ignored and the bid made as Firm Fixed Price (FFP). However, this places the entire cost risk on the company and unless the scope is well known and routinely achievable, this risk may be unacceptable.

Otherwise, with any other kind of contract, be it incentive or cost plus, it will require the company to comply with the Earned Value Management Systems (EVMS) clause.  Assume that the proposal is anticipated to be in excess of $50M (as this is the most stringent requirement), your company does not have an EVMS, and it is decided to bid and include a plan to reach compliance.

The subject DFARS Clause requires that a contract be managed with a fully compliant Earned Value Management System as defined in EIA-748 (the latest revision is “C” dated March 2013).  If a system has not been validated, meaning accepted by the Government, the company must include in its proposal how validation will be achieved.

This includes a description of the system proposed to be used including an annotated checklist which addresses each of the 162 management system characteristics, proposed changes to the current system, resumes of the personnel who will design and implement a compliant system, how the Guideline requirements will be met, subcontractor compliance, and a time-phased plan to achieve EVMS compliance.

What is the Extent of the Requirement?

The answer to this question is the object of the first steps towards full Earned Value Management (EVM) system design, implementation, operation, and acceptance.

Step 1: Familiarize company management with the EIA-748 Guideline requirements.  This is usually done with a two to four hour presentation to management conducted by experienced EVMS personnel.  The single most important outcome from this presentation, leading to a successful EVMS implementation and acceptance by the customer, is senior management’s commitment in fully supporting the steps that follow.

Step 2: Review the current management control systems including existing software and identify which of these fully support the earned value requirements.  This information is then used to develop an implementation plan of the necessary tasks, their associated schedule as well as the costs of needed changes.

Step 3:  This significant step helps senior management to:

    1. Review the cost benefit of the EVMS and either change the proposal strategy to a Firm Fixed Price (FFP) bid and stopping the EVMS process without significant investment
    2. Decide to implement the system a step at a time and proceed with the design and subsequent implementation and maintenance of the EVMS; or
    3. Simply not bid

The Choice – Proceed to Implement

Assuming the answer is to proceed, the question becomes what are the next steps?

First, the management system is divided into the required subsystems such as:  work definition and assignment, planning and scheduling, budgeting, work authorization, accounting, material and subcontract management, data analysis and reporting, and change control.  Next, pertinent existing information and materials (forms, documents, reports, etc.) are gathered that support these same subsystems. Interviews are also conducted to determine the “real” needs.  After collecting the existing system documentation and understanding the processes from interviews conducted, the  system documents  are placed in sequence on wall flow charts, commonly called storyboards, which allow the identification of system/subsystem “holes” and/or “gaps and overlaps” versus the EVMS requirements.  New forms, procedures, software modifications and other additions can then be identified and developed to fill these holes.

At this point in the process, the final management system design should be developed and a revised implementation plan/schedule presented to senior management for approval.  Upon approval, the first step is now accomplished.

Second, is to develop an EVMS compliant System Description, procedures and associated desk top instructions.  The System Description is a document that defines the management system much like the operator’s manual to your automobile.  It is a “what to do” document and includes definition of the processes, depicts forms and reports used in and produced by the system, and describes how the system meets the requirements of the EIA-748 Guideline requirements. This is typically organized by the Nine Process Groups of organizing, scheduling, etc.  The procedures and desk top instructions define how to do it and support the requirements outlined in the System Description.  Procedures and desk top instructions define the detailed steps necessary for all requirements and what organizations are responsible for those steps.   With the system documentation in place, and upon its presentation and acceptance by management, the second step is now complete. You could say that you have now designed and built a new automobile and it is time to train people how to drive.

The third step is to train all levels of management in the operation and use of the EVM System.  This can be accomplished in groups (functional management, control account managers (CAM), IPT Leads, senior management, etc.), and/or by one-on-one training.

Fourth, once all of the above has been accomplished, the company is ready to apply and operate the EVM system on a project.  Ideally the project that was proposed has now been won, and it is the one with which the system will be implemented—and used.  It is much easier to put the system in place and begin to operate it on a new project/contract than it is to try and retrofit it onto an existing project.  This entails following the definition, planning, and authorization subsystem steps defined in the approved Management System Description, procedures and associated desk top instructions, and then producing the required data for analysis and reporting to management and the customer.  Generally speaking, three months of system data and reports are required by the customer before the next step can be undertaken.

Fifth, the next major step is the customer’s review of the EVM system and its subsequent acceptance and validation.  Once system operation has begun, at least one visit will be conducted by the customer’s EVMS representative (in the case of DOD contracts it is the Defense Contract Management Agency (DCMA)).  The visit(s) is conducted to assess the progress against the plan that was submitted in the original proposal.  The visit(s) is usually two to three days in length and conducted by three or four well qualified government representatives.

Once an organization conducts a self assessment and informs the reviewing agency that it is ready for their review, that agency reviews the documentation provided by the organization to determine readiness for a Validation Review.  This review will then be scheduled with the company.  It may be quite some time in the future, as there are very few DCMA representatives available and there are many companies requiring reviews of one kind or another.  A “data call” will occur which is a request for information such as 12 months of Contract Performance Reports (CPRs) or Integrated Program Management Reports (IPMR), the baseline logs from the beginning of the program, etc. When the review does occur, the program team should plan on 15 to 20 reviewers for at least two weeks. The company will need to provide all of the support the review team requires. This will include work rooms, computers, printers, and other elements that will be specified in the review notification.  Other preparations will include development of in-briefings, construction/updates of storyboards, and conduct of mock interviews with project and management personnel to prepare them for their government interviews.

The company cannot expect to complete the Validation Review without action items being assigned.  The DCMA will create Discrepancy Report(s) which will lead to Corrective Action Reports (CARs) that are rated by the degree of severity from 1 to 4. These system discrepancies will each require a Corrective Action Plan (CAP) to be developed and accepted by the DCMA, monitored, and progress reported to the DCMA.  Once the DCMA has accepted all of the responses, the company can expect to receive a formal “System Acceptance Letter,” but it should not heave a sigh of relief – there is still one more step to be accomplished.

The On-Going Process

This last step is Surveillance, the development and execution of a plan that ensures continued system operation in accordance with the EIA-748 Guidelines.  History has proven over the past 46 years that EVM Systems’ operation tends to degrade over time.  This occurs because of taking short cuts, lack of continued management commitment and emphasis, degrading system use, a “we are too big to be failed” attitude, and an occasional laissez-faire attitude.

While all of the steps except this last one can usually be accomplished in nine months to a year, the last one, Surveillance, will need continued operational discipline as long as a validated EVM system is required.

If you have questions on the DFARS clause 252.234-7001 or would like to explore EVM training options, please feel free to contact Humphreys & Associates.

DFARS 252.234-7001 – “Thou Shalt Do Earned Value” Read Post »

Scroll to Top