IMS

Understanding the As Late As Possible (ALAP) Scheduling Option in Practical Terms

, , , , , , , , , ,
Understanding the As Late As Possible Scheduling Option in Practical Terms

Many project professionals have spent entire careers without ever using the As Late As Possible (ALAP) scheduling option, although the underlying idea feels familiar. Why? Because it’s very similar to the “just-in-time” concept widely used in manufacturing and logistics.

In materials management, just-in-time means having what you need arrive exactly when you need it, minimizing storage costs and reducing inventory. The same principle can apply to project labor, but with some important cautions.

The “Right Time” for Project Work

On development or design projects, doing work too early can be counterproductive. If designs change, early work may become obsolete, forcing costly rework. The “right time” to perform a task is often determined by schedule logic. In some cases, however, it can also be guided by the ALAP constraint.

Before we explore when ALAP makes sense, let’s quickly review the two primary constraint options in Microsoft Project (and most other scheduling tools).

ASAP – As Soon As Possible

As soon as possible:

  • Is the default setting for forward-scheduled projects (when you set a project start date).
  • Means tasks are pushed as early as possible, immediately after their predecessors finish.
  • Is ideal when you want the earliest possible completion and clear visibility into float/slack.

In an ASAP chain, every task begins at the earliest opportunity, pushing resources as far to the left as possible on the Gantt chart as illustrated in Figure 1.

Figure 1: As Soon As Possible Scheduling Option
Figure 1: As Soon As Possible Scheduling Option

ALAP – As Late As Possible

As late as possible:

  • Means tasks are scheduled as late as possible without delaying the successor or project finish date.
  • Is used in backward-scheduled projects (those planned from a fixed finish date) or when you want to defer work until the last responsible moment.
  • Microsoft Project automatically places each task at the latest feasible start date that still satisfies all constraints.

Switching a chain of tasks to 100% ALAP dramatically shifts all work to the right on the timeline as illustrated in Figure 2. The impact on management is significant: Every task now has zero total slack, which means any delay, even one day, directly delays the project finish. Multiple paths can appear “critical,” making control and reporting more complex.

Figure 2: As Late As Possible Scheduling Option
Figure 2: As Late As Possible Scheduling Option

When ALAP Makes Sense

There are legitimate reasons to use ALAP selectively. For example:

  • When a task consumes resources you don’t want engaged early (e.g., expensive equipment rental or specialized consultants).
  • For just-in-time deliveries or procurements where early completion has no benefit.
  • When modeling backward scheduling. For instance, working from a fixed delivery date toward today.
  • A mixed schedule. Mostly ASAP but with a few ALAP tasks can balance flexibility, cost control, and realism as illustrated in Figure 3.
Figure 3: A Schedule Using ALAP and ASAP
Figure 3: A Schedule Using ALAP and ASAP

A Real-World Example

One of H&A’s senior scheduling consultants once faced this exact dilemma while helping to prepare a multi-year, multi-billion-dollar defense proposal for a project with strict annual funding limits. 

With less than two weeks before the submission deadline, the Proposal Director was exasperated: “I keep asking the engineers what can be delayed! Why does everything have to happen up front? The front-loaded schedule is blowing our funding cap!”

A quick inspection revealed the problem: every task was set to ASAP. The entire effort was jammed toward the beginning of the timeline, creating a massive early demand for resources. After several failed attempts to persuade the engineers to move work later, the consultant proposed something unconventional: “Let’s flip the question. Instead of asking what can we delay, let’s ask what must be done now.”

The H&A scheduling consultant converted the entire schedule to ALAP, instantly shifting all work to the far right of the timeline. The resulting view inverted the problem, from overspending early to under-spending, and gave the team a new way to discuss priorities.

In meetings, engineers were asked to move tasks from ALAP to ASAP one at a time, stopping when the annual funding limit was reached. The discussion changed from “Why can’t we do this now?” to “What can we afford to do this year?”

The result wasn’t elegant, but it solved the immediate problem: the funding limits were clearly observed, the resource profile became manageable, and the trade-offs were visible to everyone.

How ALAP Affects Critical Path and Risk

Because ALAP tasks consume all available float, they appear critical even when they may not truly drive the project finish. This can obscure the actual critical path, making it difficult for project managers to distinguish between genuine schedule risks and artificial ones. In Earned Value Management (EVM) environments, this matters. Earned value metrics depend on knowing which tasks drive completion. Excessive use of ALAP can lead to misleading forecasts and distort DCMA data quality metrics such as the Total Float test and the Critical Path test. For this reason, auditors often recommend using ALAP sparingly and documenting the rationale wherever it’s applied. 

Note: in a sophisticated scheduling environment, it is possible to make a copy of the integrated master schedule (IMS) and revert to ASAP to look for critical paths in the normal sense.  

Combining ALAP with Other Constraints

In practice, project managers often use a blend of constraint types. For example, you can combine ALAP with “Must Finish On” or “Start No Earlier Than” dates to simulate external dependencies such as contract milestones, funding release dates, or material delivery windows. This hybrid approach allows the schedule to model reality while maintaining logical control. However, it’s important to track these constraints carefully. Too many “hard” constraints of any type can reduce the schedule’s dynamic nature and make automated forecasting less accurate.

Guidance from Industry and Agencies

Industry and government scheduling guides consistently advise restraint when using ALAP. The DCMA data quality tests consider the presence of ALAP tasks as a potential red flag because they can mask schedule float and obscure the true drivers of program completion. Similarly, the GAO’s Schedule Assessment Guide recommends minimizing artificial constraints and using logic-driven sequencing whenever possible. ALAP may be appropriate for modeling constrained resources or fixed delivery milestones, but it should always be justified and documented. Within DoD and NASA programs, reviewers often require clear evidence that ALAP usage is intentional, controlled, and limited to well-understood modeling cases. It should never be used as a workaround for poor sequencing.

Key Takeaways

  • ASAP emphasizes early starts, clear float visibility, and traditional forward scheduling.
  • ALAP emphasizes delayed starts, tighter resource control, and is useful in backward or funding-constrained planning.
  • Use ALAP sparingly and intentionally as it can obscure float and create multiple critical paths.
  • In creative problem-solving, toggling between ASAP and ALAP can reveal insights about timing, funding, and necessity that might otherwise remain hidden.

Final Thoughts

The ALAP constraint is a powerful but double-edged tool. It can simplify discussions about funding limits, resource phasing, and timing priorities, but it also carries risk if used indiscriminately. Like most features in commercial off the shelf (COTS) scheduling tools, its value depends on the user’s intent and discipline. The best project schedules blend logic, transparency, and flexibility. Understanding when to use ALAP (and when not to) can make the difference between a reactive plan and a truly managed one.

Interested in Learning How to Use More Advanced Scheduling Techniques?

Master schedulers skilled at asking the right questions to solve project management challenges hone their craft based on years of experience and working with other scheduling experts. There are always opportunities to learn more. H&A routinely offers basic, advanced, and tailored scheduling workshops taught by senior master schedulers with decades of experience in all types of project environments using common scheduling tools such as Microsoft Project and Oracle Primavera P6. Give us a call today to get started. 

Humphreys and Associates also offers basic and advanced EVMS training as well as tailored EVMS training that aligns with a client’s EVM System Description. 

Understanding the As Late As Possible (ALAP) Scheduling Option in Practical Terms Read Post »

How to Get the Most from Your IMS: What Makes an IMS Useful?

, , , ,
How to Get the Most from Your IMS: What Makes an IMS Useful?

A major challenge with an Integrated Master Scheule (IMS) is making the most out of this powerful project management tool. Large and even not-so-large projects are required to have an IMS which adheres to the requirements of the Integrated Program Management Report (IPMR) or Integrated Program Management Data and Analysis Report (IPMDAR) Data Item Description (DID) and meets the schedule data quality checks available. But having met the DID requirements and passing the quality checks does not mean the IMS is being used to get the most information into the hands of decision makers on the project. 

The IPMR or IPMDAR DID, even though detailed and thorough, is generic. The same DID is used on a contract whether it is for an important new hardware-based system, a new software system, or some other goal. The DID misses the point that the type of product on the contract means that unique topics may be the most important. There is no focus in the DID; it is high level and comprehensive. What’s missing are the special interest or special focus schedules that can be drawn from the IMS with good coding, grouping, filtering, and sorting techniques.

Remember that the statement of work (SOW) for the project is really comprised of promises made in the various plans submitted in the proposal and updated after contract award. The System Engineering Management Plan (SEMP), the Software Development Plan (SDP), Make/Buy Plan, Procurement Plan, Test and Evaluation Management Plan (TEMP), and others all contain commitments that should be translated into actions in the IMS. There should be access to the portions of the IMS that show how these commitments will be accomplished.

Examples of Special Interest Schedules

On a new hardware-based project, key pieces of information revolve around getting designs done and into a form to plan for the procurement of the various things needed to build the end items. This information often resides in the IMS but must be pulled out into a “drawing release” schedule. That is a schedule showing the transition from design to 3-D models or drawings. Pinpointing the times and links in the IMS where design becomes actionable for procurement enables the project team and their suppliers to be prepared to execute the procurements. The teams or engineers (designers) and procurement people should be focused on the drawing release schedule with frequent, at least weekly meetings to coordinate.  

One of the serious issues I witnessed on a project was the lack of preparedness in having trained and qualified drawing checkers who could sign-off and release drawings. Because of the need for flight safety considerations, the drawing checker position could only be filled by qualified people. Instead of preparing months ahead for the wave of drawings, the waves were allowed to crash into the far-too-few checkers. What was supposed to be a short cycle became weeks long as drawings sat waiting for release.

As the transition is made from design to production, then the procurement schedule becomes another focused schedule which should show the information about what is being procured, from whom, and when it will be delivered. This information is used by the engineers, procurement, and inventory control people including receiving to understand the timing and volume of inbound items. Frequent coordination with suppliers and internal team members using this focused schedule helps to ensure a smooth process. Will the factory be ready to receive, inspect, process, and store all the inbound items?

What about software development as a special topic focus schedule? This is often needed. The project personnel must be able to quickly understand where in the cycle the software is and when releases will be made as well as what the release is needed for in the overall project. 

Think about all the other important focus areas that could exist on a project. For example, the training effort should be in a focused schedule showing the development of the training material (courseware), training aids, facilities, instructor preparation and anything else needed to execute the statement of work related to training.

Testing is possibly more complicated than training. This includes development of test plans and procedures, as well as the creation of test fixtures and tools. The preparation of test personnel capable of performing complicated tests should be in the focused schedule.

By now you get the idea. The IMS is the combination of all these schedules, the thing that coordinates between and among them. But the focused schedules are the real bread-and-butter of the schedule discipline. It is shocking to see a project where these do not exist. Maybe the managers don’t know they are needed or possibly that they are available. Maybe the schedule team did not prepare for these extractions from the IMS.

If your project does not have focused schedules and does not use them, the project is in jeopardy. These schedules should be generated and used frequently; weekly at least.  Even if the IMS itself is only undergoing a monthly update, the detailed schedules should be much more alive and part of the weekly communication between work teams on the project.

Tips and Suggestions

  • How to get started. Begin with the source documents and their authors, the SEMP, the TEMP, and so on. Make a list of the likely focused schedules that need to be drawn from the IMS. Read them and extract the information you need to build your IMS. If you are just starting the IMS, you could build individual schedules with the authors and then integrate them into the IMS. If you already have built the IMS, you can find the tasks you need and code them so they will appear on the focused schedule. Once coded, extract the focused schedule from the IMS using the applicable coding filters and verify it matches the commitments that were made in the source documents from the various authors. 
  • Hold “report court.” Rather than reading and sorting through all the various plans, schedule a project meeting with the key team members and ask them what reports and what schedules they need to do their jobs. Remind them of the commitments they made in the plans. They can bring or provide a list and description to you, and you can decide “in court” which items you can or cannot incorporate into the IMS. That can help to streamline what is included in the IMS and who is responsible for what. 
  • Create a schedule data dictionary if you haven’t already done so. This is essential to identify standard as well as project unique activity, milestone, or resource coding and how the coding is used so there is a common understanding of the content. The customer will need this information as well as when the IMS is provided as a monthly performance reporting data deliverable (see the IPMDAR Section 2.4.2.20, Data Dictionary for Native Schedule File). It is a prerequisite to ensure consistency in use as well as to establish a level of discipline throughout the IMS development and maintenance process. Ensure tasks always include the necessary coding. Ideally, you did your homework on the likely special topic schedules you need to draw from the IMS before starting to build the IMS. Otherwise you may need to determine various sorting and filter techniques to identify the tasks that require additional coding details. As noted above, once the tasks are coded, you or other project personnel will be able to extract the various special interest schedules from the IMS as needed. 

Need help?

Building a useful IMS for complex projects is not easy. Up front planning for the development of the IMS can help to identify the necessary outline codes and other coding to be able to group, filter, or sort the activities to extract the special topic or special focus details from the IMS. The IMS is an essential communication tool for everyone on the project. How the schedule is constructed and coded makes a difference. H&A scheduling subject matter experts (SMEs) have decades of experience in a variety of complex project environments and can help you avoid common pitfalls. Contact us today.

How to Get the Most from Your IMS: What Makes an IMS Useful? Read Post »

Establishing Milestones in the Integrated Master Schedule (IMS) Appropriately

, , , ,

The purpose of the Integrated Master Schedule (IMS) is to model and communicate the plan to accomplish a project’s objectives. A key part of that model is the identification of key events that are represented as milestones. The selection of these milestones should be done with consideration for its purpose – what does the milestone represent and communicate? You should be aware of the intent of each milestone that is entered into the IMS. The IMS is a critical communication tool to ensure everyone on the project has a common understanding of the project’s work flow. Too many times I have witnessed a scheduler slam a milestone into the IMS without regard to how it impacts the schedule logic. This could be due to haste but, in my experience, it is often due to a lack of understanding of the purpose of the milestone.

Figure 1 illustrates a common diagram for a milestone. 

Gate Review Milestone.  C may not proceed until the Gate Review has been completed.
Figure 1 Example of a Gate Milestone

As illustrated in Figure 1, the milestone is a gate and will hold up work in task C until the milestone is claimed as finished.

If the intent is to have the milestone act as an indicator instead of a gate, then the diagram in Figure 2 could satisfy that intent. If a successor is needed for the indicator milestone, something like the “End of Project” milestone could be added.

Indicator Milestone - C may proceed as soon as A is completed. Until the Milestone is claimed finished, it will move along with the data date leaving its baseline behind and indicating it has not been claimed.
Figure 2 Example of an Indicator Milestone

An accomplished scheduler knows the dangers of a Merge in the IMS. The Merge introduces schedule risk. Imagine the damage to the schedule risk assessment (SRA) if a Merge were entered as illustrated in Figure 3.

MERGE in the IMS - Neither C no D may proceed until the Gate Review has been completed. Does C really depend on B or does D really depend on A?
Figure 3 Example of Merge Risk in the IMS

In addition to adding risk, as the question indicates in Figure 3, the situation portrayed may not be true.

Is the purpose of a milestone clear to everyone?

What is the real purpose of the milestone? That must be defined first so the diagram can be entered properly into the schedule, and the IMS can model the correct steps for the project. Along with the definition of the purpose, the completion criteria should be defined and documented.

Unfortunately, this problem often extends to others on the project and even to those most responsible for the project – the Program/Project Managers (PMs). A case in point. Some years ago, a high-level customer PM challenged me, in my role as the contractor IMS architect, after the PM’s schedule subject matter expert (SME) expressed their concern that milestones in the IMS were being input incorrectly.

The milestone in dispute was the Preliminary Design Review (PDR). The PM and the PM’s schedule SME said the review was a gate and therefore should be modeled as illustrated in Figure 4. Note: In the real schedule, there were many more predecessors and successors to the milestone. Figure 4 simplifies the schedule content for clarity.

MERGE in the IMS - Neither C nor D may proceed until the Gate Review has been completed. Does C really depend on B or does D really depend on A?
Figure 4 Impact of a Gate Review Milestone

They both agreed that Tasks A and B were tasks to be done during the review itself and that the Milestone was to represent the satisfactory completion of the review. According to the definition of the PDR in the Integrated Master Plan (IMP) entrance/exit criteria, the review would lead to a letter of acceptance. The letter of acceptance was the definition of done in this case. When asked how long it would take from the time the review in A and B (and all predecessors) would be held until the letter was received, the answer was something in the order of weeks.

A literal reading of the IMS would go like this: “Hold the review in tasks A and B (and all predecessors) then wait for the approval letter before starting any other work.”

When asked if it was the PM’s intent for the several hundred engineers and others working on the project to put down their pencils after the review and wait for the letter while doing nothing as shown in PM’s desired version of the milestone in the IMS, the immediate reaction of the PM was shocked silence. Of course not. The project could not go on hold for even one week waiting for a letter. The teams would disband, and the workforce would be gone. Work would stop.

I then told the PM it was not the contractor’s intention to go parade rest and wait for the letter even if he had thought that was what was supposed to happen. If the review in A and B was deemed successful with some reasonable set of action items, then the teams would proceed. It might be that they would proceed on risk, but they would proceed anyway. I then showed the PM and the PM’s schedule SME how we would model the review in the IMS to show proceeding on risk. It would look like the example in Figure 5 if we implemented the milestone as an indicator milestone.

Review as Indicator
Milestone - C and D may proceed when their respective predecessor is completed. The milestone is not a gate.
Figure 5 Review as an Indicator Milestone

The PM thought that could work but was concerned there was no gate review aspect to this diagram and PM control of the project would be weakened or lost. I then showed him how we could put the review into the IMS as an indicator with a delayed gate effect. In other words, work would proceed while the letter was being prepared but would stop at some point if the letter was not received. That diagram looked like the example in Figure 6. 

Review as Indicator
Milestone but also a Gate - C and D may proceed on risk when their respective predecessor is completed. E and F however may not proceed until their immediate predecessor (C or D)
and the Gate Milestone are finished.
Figure 6 Review as Indicator and as a Gate

The letter could be prepared while the teams worked on tasks C and D. If issues arose then the teams would be compelled to stop after tasks C and D individually. In this case an issue with task C might not hold up task D and conversely, an issue with task D might not hold up task C. This was a measure of control the PM thought would be adequate when the need for the approval letter in the milestone was also added.

Talking Through the IMS to Verify the Intent of Milestones

The point is that the IMS is a model of the project that should define exactly what is supposed to happen. What exactly is the IMS telling us to do? Is the review a gate? Is it just an indicator? What do the documents and agreements say about the milestone? This is definitely not the time to quickly slam a milestone into the schedule logic without taking the time to think about its purpose or what you want to communicate to someone else on the project.

This story also highlights the importance of ‘reading’ or ‘talking through’ the IMS. When it was explicitly stated that the project would be put on hold if the schedule depicted in Figure 4 were followed, the team quickly realized the need for a better approach, leading to the development of a more effective plan.

Interested in Learning More?

There is an art and skill that is honed over time for creating integrated master schedules that accurately reflect the work to be performed and clearly communicates that plan to everyone on the project. There is always more to learn. H&A offers basic and advanced scheduling workshops taught by senior master schedulers with decades of experiences in all types of scheduling environments that can be tailored for the scheduling tools you are using. Give us a call today to get started.

Establishing Milestones in the Integrated Master Schedule (IMS) Appropriately Read Post »

Including Level of Effort (LOE) in the Integrated Master Schedule (IMS)

, , ,

A recent H&A blog titled “Level of Effort (LOE) Best Practice Tips” discussed different approaches for handling LOE to avoid generating false variances. That discussion did not elaborate on including the LOE tasks in the integrated master schedule (IMS). This blog is a follow on to that earlier discussion with a focus on options for including LOE in the IMS along with notes on best practices, tips, and customer expectations.

In the general sense of an earned value management system (EVMS), the LOE scope of work is contained in summary level planning packages (SLPPs) or control accounts as subordinate planning packages or work packages. The budget values for those elements will most likely come from a resource loaded IMS or a resource loading mechanism aligned with the IMS. Not all organizations resource load the IMS activities but instead extract time buckets from the IMS for resource loading using other mechanisms. Resource loading the IMS activities is the recommended practice because it assures cost/schedule integration, but it can be difficult.

LOE work might not appear in the IMS since it is considered optional by some customers such as the Department of Defense (DoD). The Department of Energy (DOE) requires LOE tasks to be included so you can expect it to be in the IMS when DOE is the customer.

Before we talk about LOE in the IMS we must think about the type of work the LOE tasks represent. LOE might be a general task such as “Control Account Management” that is not directly related to other work except perhaps in the time frame in which they happen. But some LOE tasks such as support tasks are related to other discrete work. Modeling the LOE in the IMS starts by understanding what type of effort is involved and can help to determine the approach for linking activities. 

LOE Best Practice Tips Related to the IMS

The Level of Effort (LOE) Best Practice Tips blog included these points related to the IMS:

  • “When LOE activities are included in the schedule, they should not drive the date calculations of discrete activities in the integrated master schedule (IMS). They should also not appear on the critical path.”
  • “LOE must be segregated from discrete work effort. In practice, this means a work package can only be assigned a single earned value method.”
  • “Consider shorter durations for the LOE when that LOE is supporting discrete effort. Should the first occurrence of the LOE trigger a data anomaly test metric, it can be proactively handled along with any future replanning. The remaining LOE would already be in one or more separate work packages so there won’t be any criticism for changing open work packages.”

Government Agency and Industry Guidance on LOE on the IMS

Is there any guidance that can help clarify how best to handle LOE tasks in the IMS? Let’s take a look at three of the guidance documents that may be useful for your environment.

  1. The Integrated Program Management Data and Analysis Report (IPMDAR) Data Item Description (DID), DI-MGMT-81861C (August 2021). This DID is typically placed on contracts with the DoD or NASA that exceed the contract value threshold for EVM reporting or EVMS compliance. Relevant mentions of the data requirements for the IMS in the DID are as follows.

“2.4.1.1 Content. The Schedule consists of horizontally and vertically integrated discrete tasks/activities, consistent with all authorized work, and relationships necessary for successful contract completion.”

Note: This is where the option to exclude LOE from the IMS appears since this requires only discrete tasks/activities. The following sections provide additional guidance when LOE is included in the IMS.

“2.4.2.7 Level of Effort (LOE) Identification. If tasks/activities within an LOE work package are included in the Schedule, clearly identify them.”

“2.4.2.9 Earned Value Technique (EVT). Identify the EVT (e.g., apportioned effort, level of effort, milestone).”

  1. National Defense Industrial Association (NDIA) Integrated Program Management Division (IPMD) Planning and Scheduling Excellence Guide (PASEG) (Version 5.0). The PASEG is a widely recognized industry guide on scheduling best practices in government contracting environments. Section 5.8, Level of Effort (LOE) provides a discussion on the topic including things to promote and things to avoid. Excerpts from the PAGEG follow.

“There are pros and cons around including or excluding LOE tasks in the IMS. Including LOE tasks in the IMS allows for a more inclusive total program look at resource distribution, which aids in the maintenance and analysis of program resource distribution. However, if modeled incorrectly, including LOE tasking in the IMS can cause inaccurate total float and critical path calculations.”

“Tasks planned as LOE in the IMS should be easily and accurately identifiable. This includes populating the appropriate Earned Value Technique field (as applicable) and possibly even identifying the task as LOE in the task description.”

“Consider adding an LOE Completion Milestone to tie all LOE tasking to the end of the program.”

“LOE tasks should not be networked so that they impact discrete tasks. Incorrect logic application on LOE can lead to invalid impacts to the program critical path.”

“Level of Effort tasks should have no discrete successors and should therefore never appear on critical/driving paths.”

  1. DOE Guide 413.3-24 Planning and Scheduling (April 2022). This document provides guidance for acceptable practices in a DOE contractual environment. The discussion on LOE can be found in Section 7 Planning and Scheduling Special Topics, 7.2 Level of Effort, and 7.3 Inclusion of Level of Effort in the Integrated Master Schedule. Excerpts and image from the Guide follow. 

“Overview: Activity-based methods either cannot, or impracticably can measure the performance of LOE WPs and activities. Include all activities, both discrete and LOE, in the IMS.”

“LOE is planned in the IMS so that it does not impact discrete work. Figure 6 shows the recommended linkages in the IMS for planning level of effort.”

Interpreting this DOE Guide diagram for the recommended modeling of LOE in the IMS, notice the inclusion of a “LOE Complete” milestone following the Critical Decision (CD) 4 milestone with no constraint. CD4 in this diagram represents the end of contract effort. The purpose of this LOE-complete milestone, with no constraint, is to provide a successor for all LOE tasks where one is needed. That will prevent generating issues where tasks have no successors.

This recommended modeling is done so that the LOE tasks are not linked to the end of the contract work and thus will not push it. The LOE tasks will also not appear on the critical path since they are not in the path that established the end date.

Also note that the LOE tasks in green are linked as successors to discrete work which is a logic linking approach intended to keep the LOE work aligned with the discrete work but off the critical path. Study the logic and you see that a movement to the right of a discrete task will drag along its related LOE task.

DOE requires the use of Primavera schedule tools so the relationships shown here can be accomplished in that tool. That may not be true of all tools. Know how your tools work before you generate any guidance.

Additional Relevant Guidance Search

H&A earned value consultants recently conducted a survey of the various government and non-government documents regarding the IMS and collected relevant guidance related to LOE among other things. The table below lists the results from a search for “LOE” wording. Note: this is a representative sample of typical government agency and industry IMS references. You should verify current references before you generate your own internal IMS guidance.

Source DocumentGuidance for Capturing all Activities, LOE in IMS
DCMA EVMS Compliance Metrics (DECM) Checks (version 6.0)
  • 06A210a: Do LOE tasks/activities have discrete successors? (0% threshold)
  • 12A101a: Are the contractor’s Level of Effort (LOE) WPs supportive in nature and/or do not produce technical content leading to an end item or product? (≤ 15% threshold)
  • 12A301a: Does the time-phasing of LOE WP budgets properly reflect when the work will be accomplished? (≤ 10% threshold)
IPMDAR DID DI-MGMT 81816CIf tasks/activities within an LOE work package are included in the Schedule, clearly identify them.
DOE Guide 413.3-24 Planning and Scheduling, Appendix A Schedule Assessment PrinciplesPrinciple 20. No LOE on critical path.
GAO Schedule Assessment Guide: Best Practices for Project Schedules (December 2015)Selected excerpts:
  • LOE activities should be clearly marked in the schedule and should never appear on a critical path.
  • LOE activities … derive their durations from other discrete work.
  • Best Practices for confirming the critical path is valid: Does not include LOE activities, summary activities, or other unusually long activities, except for future planning packages.
NDIA IPMD PASEG (version 5.0) (as noted above)
  • Tasks planned as LOE in the IMS should be easily and accurately identifiable.
  • LOE tasks should not be networked so that they impact discrete tasks.
  • Level of effort tasks should have no discrete successors and should therefore never appear on critical/driving paths.
PMI Practice Standard for Scheduling (Second Edition)Since an LOE activity is not itself a work item directly associated with accomplishing the final project product, service, or results, but rather one that supports such work, its duration is based on the duration of the discrete work activities that it is supporting.

Conclusion

Based on the various sources of guidance, it is possible to structure the IMS to include LOE in a way that provides cost/schedule integration and keeps all work correctly aligned yet does not cause issues with the critical path and the driving paths. From this guidance, it should be a straightforward effort to generate your own internal scheduling procedure defining how to handle LOE in the IMS if you choose to include it or if you are required to include it.

Need help producing a clear and concise scheduling procedure or tool specific work instructions? H&A earned value consultants and scheduling subject matter experts have worked with numerous clients to create easy to follow guides that help to ensure schedulers are following your company’s best practices using the scheduling tools of choice. Call us today at (714) 685-1730 to get started. 

Including Level of Effort (LOE) in the Integrated Master Schedule (IMS) Read Post »

Video Series – Common Problems Found in EVMS and Recommended Corrective Actions – 3 of 5

, ,

If you have been following Humphreys & Associates YouTube channel you know we have been releasing new a video library reviewing some of our most successful blog series.

This month we released video 3 of 5  for the blog series “Common Problems Found in EVMS and Recommended Corrective Actions”.

The following links will let you skip to the specific part of the video related to the following issues.  (opens in a new tab)

0:15 – IMS Health Problems

3:30 –Data Item Noncompliance

5:17 –Planning Package Mismanagement

You can also read the whole blog post here:

https://blog.humphreys-assoc.com/common-problems-found-evms-recommended-ca-part-3/ 

Video Series – Common Problems Found in EVMS and Recommended Corrective Actions – 3 of 5 Read Post »

EVM Consulting | Corrective Action Response

, , , , , , ,

Corrective Action Response

How do I respond to a Corrective Action Request?

In EVM Consulting, we deal with Corrective Action Requests (CARs) on a regular basis, so we have plenty of real-world experience. We created an outline of valuable information about DRs / CARs based on our collective experience. Part 1 of the guide is designed to inform you of why CARs are received and who issues them, so you can work to prevent them. Part 2 will prepare you to respond to a CAR in an effective and efficient way.

Corrective Action Response: Sources – Part 1 of 2

In Part 1 of the series we illuminated the varied sources of Corrective Action Requests:
1) Standard Surveillance Instruction (SSI)
2) Agencies that do not use the DCMA for surveillance, such as the Department of Energy.
3) Integrated Baseline Review (IBR)
4) Procedures that are compliant with the EIA-748 Guidelines
5) Contract Performance Report (CPR)
6) Integrated Project Management Report (IPMR)
7) Integrated Master Schedule (IMS)
8) Discrepancy Reports (Levels I-IV)

 

Corrective Action Response: Planning and Closure – Part 2 of 2

In part 2 of the series, we addressed responding to a Corrective Action Request (CAR):
1) Review the DRs/CARs with the customer
2) Organize for successful CAP management
3) Begin a thorough Root Cause Analysis
4) Develop and evaluate Corrective Action Plans
5) Develop verification closure steps
6) Develop a detailed Integrated Master Schedule for CAP implementation
7) Submit CAP and CAP IMS to the customer for approval prior to implementing the Corrective Actions
8) Implement Corrective Action Plans and track progress to successful completion
9) CAR closure and follow-up

EVM Consulting | Corrective Action Response Read Post »

Scroll to Top