EVMS Variance Analysis — EVMS Analysis and Management Reports

, , , ,

A Variance Analysis Report (VAR) that includes specific information about the cause, impact, and corrective action “provides management with early insight into the extent of problems and allows corrective actions to be implemented in time to affect the future course of the program” [reference: NDIA, IPMD EIA-748 (Revision D) EVMS Intent Guide]. Unfortunately, variance analysis is an easy target for criticism during EVMS reviews. There are many examples of inadequate variance analysis to choose from, but what they all have in common is the lack of specific information on the “why, what, how, when, and who” of any variance. The variance analysis reporting requirements are found in the EIA-748 (Revision D) Guidelines in Section IV., Analysis and Management Reports, Guidelines 22-27.

EIA-748 Guidelines
Section IV. Analysis and Management Reports
22 2-4a Control Account Monthly Summary, Identification of CV and SV
23* 2-4b Explain Significant Variances | Earned Value Management
24 2-4c Identify and Explain Indirect Cost Variances
25 2-4d Summarize Data Elements and Variances thru WBS/OBS for Management
26* 2-4e Implement Management Actions as Result of EVM Analysis
27* 2-4f Revise EAC Based on Performance Data; Calculate VAC


A VAR that includes specific information and data about a problem will allow management to make informed decisions and mitigate project risk. Getting specific about variance analysis reporting includes the following elements.

Overall:

  • Emphasis on the quantitative, not qualitative
  • Emphasis on the specific, not the general
  • Emphasis on significant problems, not all problems
  • Define abbreviations and acronyms at first use
  • The Control Account Manager (CAM) is the most knowledgeable person to write the variance analysis report but will need information from the business support team

Cause:

  • Isolate significant variances
  • Discuss cost and schedule variances separately
  • Clearly identify the reason (root cause) for the variance (ties to the corrective action plan)
  • Clear, concise explanation of the technical reason for the variance
  • Provide cost element analysis
    • Labor – hours, direct rates, skill mix, overtime (rate & volume)
    • Material – unplanned requirements, excess quantities, unfavorable prices (price & usage)
    • Subcontracts – changing requirements, additional in-scope work, schedule changes
    • Other Direct Costs – unanticipated usage, in-house vendor
    • Overhead (indirect) – direct base, rate changes
  • Identify what tasks are behind schedule and why

Impact:

  • Describe specific cost, schedule, and technical impact on the project
  • Project future control account performance (continuing problem)
  • Address effect on immediate tasks, intermediate schedules, critical path, driving paths, risk mitigation tasks
  • Describe erosion of schedule margin, impacts to contractual milestones or delivery dates, and when the schedule variance will become zero (this may only mean the work getting completed late (BCWPcum =BCWScum); and does not necessarily mean getting “back on schedule”
  • Describe any impact to other control accounts
  • Assess the need to revise and provide rationale for the Estimate at Completion (justify ETC realism – CPI to TCPI comparison, impacts of corrective action plan, risk mitigation, open commitments, staffing changes, etc.)
  • Note: If there is a root cause, there will be an impact. It could be related to cost, schedule, lessons learned to be applied to future activity, an update required to a process to support the corrective action or a re-prioritization of resources to meet a schedule.

Corrective Action Planning:

  • Describe specific actions being taken, or to be taken, to alleviate or minimize the impact of the problem
  • Include the individual or organization responsible for the required action
  • Include schedules for the actions and estimated completion dates (ECD)
  • If no corrective action is possible, explain why
  • Include results of corrective action plans in previous VARs.

Ask yourself, is the analyses presented in a manner that is understandable? Does the data support the narrative? Does the variance explanation provide specifics of:

“why” the problem occurred,
“what” is impacted now or in the future,
“how” the corrective action is being taken,
“when” the corrective actions will occur,
“when” the schedule variance will become zero, and/ or the work gets “back on schedule”
“who” is responsible for implementing the corrections?

Remember, a well-developed Variance Analysis Report can reduce the risk of a Corrective Action Request (CAR) during an EVMS review.

EVMS Variance Analysis — EVMS Analysis and Management Reports Read Post »

Using the Same Rate for BCWS and BCWP

, , , , , ,
Using the Same Rate for Budgeted Cost for Work Scheduled (BCWS) and Budgeted Cost for Work Performed (BCWP)
There is often an EVMS project managers debate regarding which rates to use for common budget costing EVMS data elements. For Actual Cost of Work Performed (ACWP), it is fairly obvious as the most recently approved actual rates are applied. A planning rate is generally used for BCWS and BCWP, but many in the EVM project management industry use incorrect rate application for the BCWP calculation. In some cases EVM contractors use a weighted average rate; the percent complete in hours multiplied by the dollarized BAC to derive the BCWP in dollars. This method is noncompliant with the EIA-748 Guideline 22 which states that if work is planned on a measured basis, then the BCWP must be calculated on a measured basis using the same rates and values. In other words, the rate and methods used to calculate BCWS and BCWP must be the same. As shown in Example #1, it can be seen that work planned in hours (BCWS) was performed as scheduled (BCWP) each month. Each hour was planned at a rate of $100/hour until the end of the calendar year when the rate increased to $105/hour. In this example, the rates used to calculate BCWS and BCWP are the same.
EVMS: BCWS & BCWP rate calculation example table #1
EVMS: BCWS & BCWP rate calculation example table #1

Example #2 below illustrates a very common scenario. In this example work that was planned in November and December was not completed until the next year. In January, the rate increased from $100 to $105. What should the BCWP in dollars be for both January and February?

EVMS: BCWS & BCWP rate calculation example table #2
EVMS: BCWS & BCWP rate calculation example table #2

For both January and February, the original 10 hours planned was earned at $105/hour equaling $1,050. The work that was planned in November and December, but completed late in January and February, was earned at its planned rate of $100/hour resulting in $1,000 of BCWP.  The sum ($1,050 + $1,000) equals the BCWP of $2,050 in each month. See the Example #3 graphic below:

EVMS: BCWS & BCWP rate calculation example table #3
EVMS: BCWS & BCWP rate calculation example table #3

Even though the rate was escalated in the new year, the BCWP that should have been earned in the prior year is calculated using the rate that was originally planned. The same approach would be logical if the work planned at $105 per hour were performed ahead of schedule in let us say, December of the prior year. It would be earned at $105 per hour even though it was performed in a time frame where the planning rate is $100 per hour. In some instances, business systems are programmed to earn as a percent of the entire Budget at Completion (BAC). This could result in an inaccurate BCWP dollar value. As an example, let us assume 10 hours are earned in September. If those 10 hours were 1/8 of the total BAC, then the BCWP dollars associated with this 10 hours would be $102.50 per hour and the contractor would be earning too much for those 10 hours. They must earn at the planned $100 per hour! Thus the rate used for BCWP is the same as for BCWS and is compliant with Guideline 22; one earns in the same manner as they plan to earn.

In summary, EVM concepts require that in order for the work to be complete, cumulative values of BCWS and BCWP must equal the BAC.  So, from a common-sense standpoint, if BCWP is earned at a different rate than that used for planning the BCWS, the Control Account (or even the Contract) cannot be closed properly.  Examples:

  • If BCWP earns at a lower rate, the BCWP would be, say, 98% of the BAC when the actual work is done.
  • Likewise, if BCWP earns at a higher rate, the BCWP would be, say, 105% of the BAC when the actual work is concluded.

Both of these scenarios violate the EVM concepts.

Using the Same Rate for BCWS and BCWP Read Post »

EVM for Biotech and Pharma – Part I Implementation and Training

, , , , , , , , , , , , ,

Updated December 13, 2017

 

EVM for Biotech and PharmaAs you know, the Earned Value Management System (EVMS) is a management process with characteristics that are absolutely logical to manage projects whether there is an external customer or not. The EVMS is also required by the Federal Government on DOD, DOE, FAA, NSA, DOT, DOJ, NASA, etc. contracts over $20M.

With the phasing in of the Affordable Health Care Act and recent funding for research and preparation in the event of bio-terrorism, other branches of the Government, such as Health and Human Services (HHS) and Biomedical Advanced Research and Development Authority (BARDA), are becoming more involved in the healthcare sector. Implementing and using EVMS is a baseline requirement for biotech and pharmaceutical firms awarded large contracts by the Federal Government.

This will require companies and universities that receive funding to understand and implement Earned Value Management and that key project personnel, including management and executives, will require high quality Earned Value Training.

Why EVM and Government Contracts

Earned Value Management has been used since the 1960’s and has become the standard by which the Government measures and evaluates the management and reporting processes on projects awarded to contractors. Initially, it was implemented on projects; such as the development of satellites, long-range missiles, fighter aircraft, etc., but has become the US Government’s gold standard to manage the technical, schedule and cost progress of projects and to identify and manage risk and opportunities.

In order for defense contractors to be eligible for large contracts, they are required to follow the 32 Guidelines of the EIA-748-C which can entail system design and development and a substantial learning curve. Earned Value Management company-wide training and proper implementation becomes critical for project efficiency, future funding and to meet Government requirements.

Integral to EVM are the uses of the Integrated Master Plan (IMP)/Integrated Master Schedule (IMS) and risk and opportunity management.  The Integrated Master Schedule is the basis for developing the Performance Measurement Baseline (PMB) which in turn, is the basis for measuring performance on a project.   Measurement of progress against the baseline provides early identification of problems and helps to identify and mitigate costs and risks, while also identifying opportunities, by implementation of appropriate corrective actions.

Earned Value Management Systems for Project Management

The basic concept of the Earned Value Management System is more than a unique project management technique.  The EIA-748-C contains 32 Guidelines that define a set of requirements that a contractor’s management system must meet. The objectives of an EVMS are:

  •  Relate time phased budgets to specific contract tasks and/or statements of work
  • Relate technical, schedule and cost performance information
  • Furnish valid, timely and auditable data/information for proactive management action and decision making
  • Provide the basis to capture work progress assessments against the baseline plan to facilitate realistic project costs and completion dates
  • Supply managers with a practical level of summarization for effective decision making

Once a contractor’s EVM System is designed and implemented, there are significant benefits to the contractor and to the customer:

  • Contractor benefits include increased visibility and control to quickly and proactively respond to issues which makes it easier to meet project technical, schedule, and cost objectives
  • Customer benefits include confidence in the contractor’s ability to manage the project, early problem identification, and objective rather than subjective contract cost and schedule status

Earned Value Management Training

Experienced project managers will tell you that understanding the scope, schedule and costs of a project is essential to its success. The primary objective of the EVMS is to ensure that all elements of a project are planned, authorized, managed, and controlled in a consistent and cost-effective manner.  There is an increasing demand for training for organizations beyond the traditional aerospace and defense related construction, software, research and development, and production environment to now include non-defense companies to implement and use the Earned Value Management System.

EVM for Biotech and Pharma

Biotech and Pharma companies are not strangers to dealing with government regulations and requirements. Most have gone through rigorous Food and Drug Administration (FDA) processes to receive approval of compounds and/or devices. Nonetheless, learning how to design and use an EVM system can take a considerable investment of time and money, but is an essential requirement for initial and ongoing funding.

In addition to the EIA-748-C, there are numerous documents that give direction regarding the implementation and use of an EVM system.  Some of these are the National Defense Industrial Association (NDIA) Integrated Program Management Division (IPMD) EIA-748 Intent Guide, Cost Accounting Standards (CAS), Data Item Descriptions (DID), Military Standards (MIL-STD) such as MIL-STD-881, the Earned Value Management System Interpretation Guide (EVMSIG), and many others.  We have helped many organizations to ensure that they do not overkill or underkill based on their desired management system characteristics.  H&A personnel understand the requirements and are able to “size” those requirements to meet company and customer requirements.

Although Biotech and Pharma are relatively recent industries to use EVM, Humphreys & Associates (H&A) has been providing Earned Value Management training and implementation services for over 35 years. H&A provides self-paced online, classroom and private training courses, and can assist in all aspects of Earned Value Management Implementation.

For more information about EVM training or support, or with questions about your company’s requirements, please contact the Humphreys & Associates corporate office.

EVM for Biotech and Pharma – Part I Implementation and Training Read Post »

Level Of Effort Decision Tree – Clarifying Source Articles

, , , , ,
Level Of Effort Decision Tree – Clarifying Source Articles

Updated January 20, 2021

 

Level of Effort Decision Tree – Introduction

If you have not read the LOE source articles, Level of Effort (LOE) Replanning and How to Avoid Corrective Action Requests Related to Level of Effort, it is necessary to read prior to these articles in order to have the context for the following subject matter.

Humphreys & Associates, Inc. prepared an EVM consulting article a couple of months ago in order to increase the awareness of Earned Value Management Systems (EVMS) reviews related to Level of Effort (LOE) replanning. This resulted in considerable attention because we did not adequately explain our intention.

We had hoped readers would recognize that there are many strong and diametrically opposed opinions on acceptable approaches to LOE replanning. An important point to remember is that the principal purpose of an EVMS is to provide adequate information from which to make logical, well-informed decisions based on the best data available.

Our article resulted in a request for the National Defense Industrial Association (NDIA) Integrated Program Management Division (IPMD) to address this topic in its EVMS Clearinghouse Working Group. The company that submitted the issue used one of the approaches that we listed, which led to a DCMA Discrepancy Report. Consequently, they were clearly concerned. To address that one issue would not have provided an intelligent approach – it would have resulted in even more concerns for other organizations. For that reason, we chose to provide an update to our article in the form of a “white paper.” We do not address the many approaches being employed, as some display thinking that is “way out of the box;” such as earning whatever the actual costs are – as opposed to the budget.

We chose to leave some of those approaches out of the options addressed below. One could almost conclude that we are observing the classic consultant response to some issues – “It depends.”

BACKGROUND

The distinctive feature of the Level of Effort (LOE) earned value technique is that it earns value through the passage of time with no consideration of any work being performed. Therefore, it can earn value with no incurrence of actual costs and incur actual costs without earning value. Both of these conditions are currently considered by some DCMA review teams as noncompliant to the EVMS Guidelines (#16 and/or #22) that could result in a DCMA issued Corrective Action Request (CAR).

This is usually not an issue for the typical LOE that is support to the entire project (e.g., project management, contract management, financial management, systems engineering, security, safety, etc.) because these efforts almost always start on time and only face a problem if the support extends past the contract baseline. However, it is frequently an issue for LOE that provides support to discrete efforts that could slip or be moved up for various reasons (e.g., test site availability, equipment failures, successes that eliminate future planned effort, etc.) if the LOE work is not allowed to be replanned to the time period where the discrete work is actually being performed.

The LOE baseline period of performance should match the discrete effort’s period of performance. While the discrete effort can occur early or late and have earned value and actual costs coincide, that is not necessarily true for the supporting LOE, because it earns its value as planned in the baseline regardless of when the work actually starts or when the actual costs are incurred. The examples below show the possible LOE conditions when discrete effort starts early, finishes early, starts late, and finishes late. Each condition trips a significant item of concern when the DCMA runs its diagnostics of a contractor’s EVMS data:

If the discrete effort starts early, and LOE is not allowed to replan, LOE incurs ACWP with no BCWP.

H&A 1 - LOE Decision Tree

If the discrete effort finishes early, the remaining months of LOE support earn BCWP with zero ACWP.

H&A 2 - LOE Decision Tree

If the discrete effort starts late, LOE earns value (BCWP) with no actual costs (ACWP).

H&A 3 - LOE Decision Tree

If the discrete effort finishes late, LOE incurs ACWP without accompanying BCWP because the BCWP now equals the BAC. However, when the support effort’s manager reports an EAC that includes the to-go LOE to report an accurate EAC, it creates the situation of EAC>ACWP with BCWP=BAC, again tripping a DCMA significant item of concern.

H&A 4 - LOE Decision Tree

These conditions have resulted in Corrective Action Requests (CARs) from some local DCMA representatives because they are identified as significant items of concern by the DCMA diagnostics. Unfortunately, the diagnostics applied to discrete work packages are also applied to LOE tasks. There is no consideration of the special circumstances associated with LOE in the diagnostic software being used by review teams.

It is important to note that LOE is often (erroneously) called a work package just like discrete effort is called a work package and, therefore, work package rules are automatically applied to LOE. But not all work package attributes apply to LOE. For example, LOE does not consist of discrete tasks, is not required to be of short duration, and does not measure performance. The special circumstances of LOE were recognized in 1991 by the Department of Defense issuance of the Performance Measurement Joint Executive Group (PMJEG)’s Supplemental Guidance to the Joint Implementation Guide (JIG) involving the Cost/Schedule Control Systems Criteria (C/SCSC). Section 3-6, Revisions, subsection b (Internal Replanning) specified special handling of LOE for the circumstances cited above. However, the JIG Supplemental Guidance has not been incorporated into current implementation guidance. Please note that some DCMA EVMS Center of Excellence personnel have stated that the 1991 JIG Supplemental Guidance is applicable to current guidance. This is the way it used to be and was understood by all. But that position has not been documented and distributed to DCMA field office personnel, resulting in different determinations as to which actions are allowable and which are not. Many DCMA field office EVMS personnel have never been exposed to the JIG Supplemental Guidance. Those that are aware of the 1991 JIG Supplemental Guidance or who would agree with the JIG Supplemental Guidance approach as being compliant tend not to create CARs for the same conditions, while, unfortunately, those who are not aware of the Guidance write CARs.

INTRODUCTION TO THE DECISION TREE

The following decision tree relies heavily on the JIG Supplemental Guidance for recommending actions to avoid CARs. It is organized in outline format with major sections being the four discrete effort status possibilities that can cause LOE to result in a CAR as shown above. The first sub-topic in each section is the supporting LOE condition that results in tripping a significant item of concern in the diagnostic software DCMA employs from the Data Call before arriving on-site. The second sub-topic provides a quotation from the PMJEG Supplemental Guidance to the C/SCSC JIG, Section 3-6 Revisions, Subsection b. Internal Replanning that applies to the identified condition. The third sub-topic provides suggestions on how to implement the guidance to avoid the condition. The following sub-topics provide the advantages, disadvantages, and reporting requirements for each avoidance action.

In presenting these actions we need to make the point that depending on the interpreter none of these or only some of these would be acceptable to a DCMA reviewer. We are merely attempting to bring forth the options observed so that many can consider which approach is best for them and then use simple examples to present their desires to their customers.

Note that JIG references to “cost account” apply to control accounts.

LEVEL OF EFFORT (LOE) DECISION TREE

OUTLINE

Discrete Effort Starts Early

  1. Condition that may result in a DCMA CAR
    1. The LOE BCWS does not start until a later period (cannot earn value in the current period).
    2. LOE has ACWP without BCWP, a significant item of concern condition.
    3. Applicable JIG Supplemental Guidance, Internal Replanning
      1. Paragraph (3)(c).
      2. “Replan future LOE to correlate to the changes in work. LOE, whether planned in separate cost accounts or as part of predominantly discrete cost accounts, has additional flexibility and may be adjusted within the current accounting period without government approval, provided no actual costs (ACWP) have been charged to the LOE.”
      3. How to implement the Supplemental Guidance
        1. In the current accounting period, replan the LOE to begin in the current period.
        2. Determine whether the discrete effort’s early start will result in an early finish (length of the period of performance remains the same).
          1. If so, no BAC change should occur – only the shift in the BCWS.
          2. If not, either provide additional BAC from MR or re-spread the BAC over the revised future period of performance (often called the “peanut butter” approach).
  2. Advantage
    • Avoids the ACWP without BCWP condition.
  3. Disadvantage
    • Changes the baseline in the current period. If the local DCMA office is not aware of the Supplemental Guidance or knows about its existence but disagrees with it, a CAR may be issued. Also, some DCMA teams consider the stretching out of current budget over a longer period of time as creating “token budgets” – for which they have written CARs.
  4. Reporting requirement
    • Must be reported in Integrated Program Management Data and Analysis Report (IPMDAR) database for Format 5.

Discrete Effort Finishes Early

  1. Condition that may result in a DCMA CAR
    1. The discrete effort has finished early and if the LOE had not previously been replanned in anticipation of the early finish, no LOE support effort would be required for the remaining period(s) of the LOE BCWS that must still earn value.
    2. The LOE has BCWP without ACWP, a significant item of concern condition.
    3. Applicable JIG Supplemental Guidance, Internal Replanning
      1. Paragraph (3)(b).
      2. “Replan incomplete future work and adjust the work package budget at completion (BAC) to reflect the change in accordance with normal replanning guidance…”
      3. How to implement the Supplemental Guidance
        1. Because the “incomplete future work” has been eliminated, close the LOE package. The BCWS will already be equal to the BCWP earned to date.
        2. Subtract the BCWP from the BAC and return the BCWR initially to the UB Log and subsequently to the MR Log.
        3. If this can be achieved in the period in which the discrete effort was completed, this is a change to the next accounting period, thus avoiding a change to the current period baseline.

        NOTE: There is another point to be made here. The LOE task was to support the discrete work scope no matter how long it took. If the discrete task finished early because its work scope was reduced, the LOE task requirement was also reduced and the above action is justified. If the discrete task simply finished early, this would be a cost variance in that it cost less to support the unchanged work scope. The above action would be done solely to avoid the BCWP without ACWP condition.

  2. Advantage
    • Avoids the BCWP without ACWP condition.
  3. Disadvantage
    1. If the change is made in the same period in which the discrete effort was completed (or a prior period), there is no disadvantage although some would argue that this approach would be “changing budgets based on performance” which is akin to using MR to hide true cost variances.
    2. If the change is made in the period subsequent to the completion of the discrete effort, the current period baseline will change. If this is a repetitive occurrence, it probably means that a contractor is constantly changing the baseline to avoid true cost variances; therefore, it may result in a DCMA CAR.
  4. Reporting requirement
    • Must be reported in IPMDAR database for Format 5 (MR was increased).

Discrete Effort Starts Late

  1. Condition that may result in a DCMA CAR
    1. The discrete effort has not started (no ACWP or BCWP), hence no LOE was required. This results in zero ACWP for the LOE, but it does report BCWP because of the passage of time.
    2. The LOE has BCWP without ACWP, a significant item of concern condition.
    3. Applicable JIG Supplemental Guidance, Internal Replanning
      1. Paragraph (3)(c).
      2. “Replan future LOE to correlate to the changes in work. LOE, whether planned in separate cost accounts or as part of predominantly discrete cost accounts, has additional flexibility and may be adjusted within the current accounting period without government approval, provided no actual costs (ACWP) have been charged to the LOE.”
      3. How to implement the Supplemental Guidance
        • In the current month replan the LOE to begin in the month that the discrete effort is currently scheduled to begin.
  2. Advantage
    • Avoids the BCWP without ACWP condition.
  3. Disadvantages
    1. Changes the baseline in the current period. If the local DCMA office is not aware of the Supplemental Guidance or disagrees with the Supplemental Guidance, a CAR may be issued.
    2. If the discrete effort recovers its schedule variance, the LOE will be put in the position of having BCWP yet to be earned with no LOE required (equivalent to the early finish condition presented below).
  4. Reporting requirement
    • Must be reported in IPMDAR database for Format 5.

Discrete Effort Finishes Late

  1. Conditions that may result in a DCMA CAR
    1. The LOE incurs ACWP with no accompanying BCWP.
    2. The LOE incurs ACWP with no accompanying ETC, usually indicated by ACWP>EAC.
    3. Both of these are significant items of concern conditions.
    4. Applicable JIG Supplemental Guidance, Internal Replanning
      1. Paragraph (3)(b).
      2. “Replan incomplete future work and adjust the work package budget at completion (BAC) to reflect the change in accordance with normal replanning guidance…”
      3. How to implement the Supplemental Guidance
        1. In or before the last period of performance of the LOE, replan the LOE to cover the extended discrete effort.
        2. Use one of two methods to provide budget for the additional effort:
          1. If ACWP is less than BCWP, recover budget from the previously earned LOE BCWP by using the single point adjustment technique of setting BCWS and BCWP equal to ACWP and replan the recovered budget (BAC minus BCWP) into the future.
          2. If ACWP is equal to or greater than BCWP, but less than BAC, replan the unearned budget (BAC minus BCWP) into the future.

        NOTE: Alternative to 3) implementing the Supplemental Guidance

        1. Allow the LOE package to complete without replanning, which results in accepting the ACWP without BCWP condition.
        2. To mitigate the severity of this approach, be certain to provide an ETC for the periods beyond the LOE baseline period of performance. This action would avoid an ACWP>EAC condition.
  2. Advantages
    1. Avoids the ACWP without BCWP condition.
    2. Avoids the ACWP>EAC condition.
  3. Disadvantage
    • There will be a baseline change in the current period. Because ACWP has occurred, the LOE exception to be able to make a change in the current period if no ACWP has been recorded does not apply. Therefore, a DCMA CAR may be issued.
  4. Reporting requirement
    • Must be reported in IPMDAR database for Format 5.

Observations/RECOMMENDATIONS based on the foregoing:

  1. First and foremost, because many DCMA personnel are not familiar with the JIG Supplemental Guidance or may not agree with it (remember that the DCMA Center of Excellence has not formally confirmed that the JIG Supplemental Guidance remains in effect), contractors must determine the desired approach of the cognizant DCMA personnel for handling the LOE conditions noted above. Early discussions to determine acceptable approaches to the LOE special conditions will avoid many of the CARs/DRs being issued.
  2. Eternal vigilance is required. If a potential change in the performance period of the discrete effort becomes apparent sufficiently early, the change can be accomplished with little chance of incurring a DCMA CAR. This assumes that people recognize the right to change LOE in an “open LOE task”.
  3. The DCMA Center of Excellence must officially transmit additional guidance to the DCMA field offices to ensure consistent application of EVMS Guideline requirements to LOE.
  4. Some may suggest using the Apportioned Effort technique in lieu of LOE, but that would require that the supporting budget be estimated as a percentage of the discrete effort and its time-phasing be established at the same percentage as the time-phasing of the base. Usually, LOE budget is based on an average level of support that is inconsistent with or has a “loose” relation to the discrete package’s time-phasing.
  5. One alternative approach is to consider short duration (3-4 months) LOE for supporting discrete effort. An advantage to this approach is that while the first LOE in the series might incur a significant item of concern condition, the following efforts could be adjusted without penalty.
  6. Another alternative approach is to make the entire support effort a percent complete EVT work package with the Quantifiable Backup Data (QBD) being the milestones in the supported discrete effort.
  7. If the LOE has been reported as complete in the prior month, it has been suggested by some in the DCMA EVMS Center of Excellence that the LOE BCWP that has already been earned can be “harvested” to budget a continuation of the LOE past its original period of performance. This was not a consideration of the JIG Supplemental Guidance and most would argue that this approach is in direct conflict with Guideline 30. Contractors should not use this method unless it is formally approved by the DCMA EVMS Center of Excellence.

To contact Humphreys & Associates click here.

Level Of Effort Decision Tree – Clarifying Source Articles Read Post »

NDIA and Earned Value Management – Humphreys & Associates Marks 35+ Years of Participation

, , , , ,

NDIA and Earned Value ManagementThe National Defense Industrial Association (NDIA), Integrated Program Management Division (IPMD) plays a central role in defining earned value management within the defense contracting community. Earned value management, or EVM, is a project management methodology that measures the technical, cost and scheduling performance of projects and/or programs. EVM systems (EVMS) are widely used and in some cases required by federal government agencies on large and complex contracts. The NDIA IPMD is industry’s opportunity to work closely with the federal government to set policy and provide guidance to its members.

NDIA and Eared Value Management Standards – Their Leadership Role

The NDIA has long taken the lead in setting EVM standards. In the 1990s, it recommended modifications to the 35 Department of Defense Cost Schedule Control Systems Criteria (C/SCSC) and proposed 32 guidelines that included the needs of industry as well as meeting the government requirements. The Defense Contracting Management Agency (DCMA) concurred with the use of the 32 guidelines which became the 748A standard. The NDIA IPMD has since maintained the role of managing the standard.

The NDIA Integrated Program Management Division (IPMD) also provides guidance in the implementation and use of EVM systems (EVMS) to achieve integrated program management. While IPMD membership is limited to industry representatives, government personnel from the various agencies implementing EVMS are regular participants in the IPMD’s quarterly working group meetings. The various IPMD working groups focus on strengthening the understanding and implementation of compliant EVM systems.

NDIA EVM System Guides

The IPMD has published a series of widely used EVMS guides. The Earned Value Management Systems Intent Guide provides an interpretation of the EIA 32 guidelines for  companies seeking to implement a compliant EVM system. The committee revised the Earned Value Management System Intent Guide in 2014 and continues working on further improvements. The Planning and Scheduling Excellence Guide (PASEG) Version 3 was released in 2016 and is used in the development of Integrated Master Plans (IMP) and Integrated Master Schedules (IMS) EVMS compliant processes and artifacts.    Other IPMD documents address specific aspects of the EVM process, such as the Earned Value Management System Acceptance Guide, the Integrated Baseline Review (IBR) Guide and the Surveillance Guide. Other recent additions include a Guide to Managing Programs Using Predictive Measures and an Industry Practice Guide for Agile on EVM Programs.

At set contract value thresholds, the Office of Management and Budget (OMB), Federal Acquisition Regulations (FAR), and Defense Acquisition Regulations (DFAR) requires the government program offices to ensure their supplier’s program management system meets the intent of the Earned Value Management Systems (EVMS) of the EIA 748 standard. In some cases these systems must be validated by the Defense Contract Management Agency (DCMA) as being compliant with the EIA standard.  The NDIA continues to work with government and industry to drive the evolution of standards for Earned Value Management Systems implementation and acceptance in the United States and internationally.

Humphreys & Associates has been an active participant in the NDIA IPMD for more than 35 years. Three of our consultants, including the founder of the company, were part of the eight person committee that developed the EIA 748 Standard for EVMS. We also have three past chairs of the National Defense Industrial Association (NDIA) Integrated Program Management Systems Committee (IPMD) on our staff. Our consultants continue to be active participates in the working groups responsible for the system guides and the continuing improvement of the EVMS guidelines.

Humphreys & Associates is the industry leader in Earned Value Management Systems design, implementation and EVMS training.  You can learn more on the Humphreys & Associates website.

NDIA and Earned Value Management – Humphreys & Associates Marks 35+ Years of Participation Read Post »