EVMS

Using the Same Rate for BCWS and BCWP

, , , , , ,
Using the Same Rate for Budgeted Cost for Work Scheduled (BCWS) and Budgeted Cost for Work Performed (BCWP)
There is often an EVMS project managers debate regarding which rates to use for common budget costing EVMS data elements. For Actual Cost of Work Performed (ACWP), it is fairly obvious as the most recently approved actual rates are applied. A planning rate is generally used for BCWS and BCWP, but many in the EVM project management industry use incorrect rate application for the BCWP calculation. In some cases EVM contractors use a weighted average rate; the percent complete in hours multiplied by the dollarized BAC to derive the BCWP in dollars. This method is noncompliant with the EIA-748 Guideline 22 which states that if work is planned on a measured basis, then the BCWP must be calculated on a measured basis using the same rates and values. In other words, the rate and methods used to calculate BCWS and BCWP must be the same. As shown in Example #1, it can be seen that work planned in hours (BCWS) was performed as scheduled (BCWP) each month. Each hour was planned at a rate of $100/hour until the end of the calendar year when the rate increased to $105/hour. In this example, the rates used to calculate BCWS and BCWP are the same.
EVMS: BCWS & BCWP rate calculation example table #1
EVMS: BCWS & BCWP rate calculation example table #1

Example #2 below illustrates a very common scenario. In this example work that was planned in November and December was not completed until the next year. In January, the rate increased from $100 to $105. What should the BCWP in dollars be for both January and February?

EVMS: BCWS & BCWP rate calculation example table #2
EVMS: BCWS & BCWP rate calculation example table #2

For both January and February, the original 10 hours planned was earned at $105/hour equaling $1,050. The work that was planned in November and December, but completed late in January and February, was earned at its planned rate of $100/hour resulting in $1,000 of BCWP.  The sum ($1,050 + $1,000) equals the BCWP of $2,050 in each month. See the Example #3 graphic below:

EVMS: BCWS & BCWP rate calculation example table #3
EVMS: BCWS & BCWP rate calculation example table #3

Even though the rate was escalated in the new year, the BCWP that should have been earned in the prior year is calculated using the rate that was originally planned. The same approach would be logical if the work planned at $105 per hour were performed ahead of schedule in let us say, December of the prior year. It would be earned at $105 per hour even though it was performed in a time frame where the planning rate is $100 per hour. In some instances, business systems are programmed to earn as a percent of the entire Budget at Completion (BAC). This could result in an inaccurate BCWP dollar value. As an example, let us assume 10 hours are earned in September. If those 10 hours were 1/8 of the total BAC, then the BCWP dollars associated with this 10 hours would be $102.50 per hour and the contractor would be earning too much for those 10 hours. They must earn at the planned $100 per hour! Thus the rate used for BCWP is the same as for BCWS and is compliant with Guideline 22; one earns in the same manner as they plan to earn.

In summary, EVM concepts require that in order for the work to be complete, cumulative values of BCWS and BCWP must equal the BAC.  So, from a common-sense standpoint, if BCWP is earned at a different rate than that used for planning the BCWS, the Control Account (or even the Contract) cannot be closed properly.  Examples:

  • If BCWP earns at a lower rate, the BCWP would be, say, 98% of the BAC when the actual work is done.
  • Likewise, if BCWP earns at a higher rate, the BCWP would be, say, 105% of the BAC when the actual work is concluded.

Both of these scenarios violate the EVM concepts.

Using the Same Rate for BCWS and BCWP Read Post »

Keeping the EVM Love Alive In Your Organization

,

Keeping the EVM loveAdmittedly, operating an Earned Value Management System (EVMS) in an organization can sometimes be like getting your kids to the dentist.  They know they have to do it, and they will even concede that it may be good for them, but it does not mean they have to like it.

Earned Value provides a framework for integrating the cost, schedule, and technical scope of your project, and is an exceptionally valuable tool for management and project status.  There are, however, a few strategies that can be employed in order to maintain a healthy system by motivating those who operate within the system to do so with a sense of ownership.

Keeping the EVM love alive can follow the simple formula of Push, Pull and Inform.

1)   Push:  Senior Management Must Use the Data and Demand Quality

Having those up the food chain demanding accurate and timely information can be a powerful “push” that maintains interest and focuses efforts on system health and quality.  Organizations where EVM is nothing more than a reporting requirement and is not used for decision making or conveyance of project status, will have a difficult time maintaining a healthy system.  Sometimes negative attitudes towards Earned Value can even start with the customer and flow down to the contractor.

The alternative is in companies in which it is apparent that EVM is deeply embedded in the projects’ culture.  In a multitude of forums, the language of Earned Value is used to describe the status and issues of the project.  In these companies you probably will not see only the obligatory EVM charts in project reviews, but instead see the concepts and outputs of the system used throughout project management.  If poor variance analyses, inaccurate Estimates at Completions (EAC), incomplete baselines, or lack of corrective actions are challenged by the entire chain of management, then chances are those problems will stop being problems and the organizations can begin relying on the information to manage effectively.

2)    Pull:  Keep the System Useful to the Users

A great deal of resources may be invested in an EVMS, and in organizations with a healthy and useful system the return on this investment can be substantial.   Organizations that employ toolsets with timely and accessible reporting of project information help combat the belief that EVM is just a one-way reporting process.  A common interface for data is an “EVM Cockpit”, or some other tool set or reports that make the information easy to access for day-to-day management purposes.  The flip side of this are systems that make data accessibility difficult, or the problems of the system cause the data to be unreliable for prompt decision making purposes.  For example, one of the more important processes in an EVMS is variance analysis; however, when a great deal of time and effort is spent explaining variances that are not related to project performance, it becomes a significant drain on the attitude towards the system.

It is also important that the critical processes of the system are easy to use and understand.  These processes include project baselining, updates to the Estimate to Complete (ETC), statusing the Integrated Master Schedule (IMS), incorporation of changes, preparing variance analyses, and tracking of corrective actions.  Decisions regarding the architecture of the toolsets supporting these processes can significantly impact the attitudes of system users.  In addition, developing tool sets that eliminate the redundancy of data inputs between the cost and scheduling systems can dramatically improve the quality of the Earned Value data.

3)   Inform:  Regular Communication and Continuous Education to the Project Teams are Critical

Like any important management system in an organization, it is important to continually inform and support those who operate within the EVM system.  There is an endless source of special topics and project notifications that can provide useful information to project teams, which will help maintain EVM knowledge and a healthy system.  Some topics, such as preparing quality variance analysis, thorough corrective actions, and valid ETCs, need routine refreshment.

Below are a few suggestions on ways to communicate within the organization:

  • Monthly Internal Newsletter: An excellent mechanism to convey important updates to EV processes or changes that pertain to the business and the industry. This gives employees a chance to keep up with the latest news and developments.
  • EV Blog:  By blogging regularly, an organization can develop themes that are specific to business issues the organization is experiencing. If there are many of the same questions repeated again and again, the blog can be used to answer those questions. This way, people can just refer to the blog if they have questions that are common.
  • Lunch & Learn Sessions: These sessions are an excellent way for all participants to gain further knowledge on a specific topic and ask questions in real time.  This becomes more advantageous as all participants benefit from the group discussion.
  • Quarterly Webinar: This is particularly beneficial for organizations that may have multiple facilities located throughout the country. Specific subjects would be applicable to all sites. All participants, regardless of location, can attend and benefit.
  • Annual Quiz: This is a great way to gauge how well employees are grasping and using EVM. Questions would be centered on topics relating to events that occurred during the year. The quiz could be recurring and mandatory in the same manner as ethics and sexual harassment training.

For more information about keeping the EVM love alive in your organization give us a call at Humphreys & Associates, Inc. We are happy to answer questions.

Keeping the EVM Love Alive In Your Organization Read Post »

EVM for Biotech and Pharma – Part I Implementation and Training

, , , , , , , , , , , , ,

Updated December 13, 2017

 

EVM for Biotech and PharmaAs you know, the Earned Value Management System (EVMS) is a management process with characteristics that are absolutely logical to manage projects whether there is an external customer or not. The EVMS is also required by the Federal Government on DOD, DOE, FAA, NSA, DOT, DOJ, NASA, etc. contracts over $20M.

With the phasing in of the Affordable Health Care Act and recent funding for research and preparation in the event of bio-terrorism, other branches of the Government, such as Health and Human Services (HHS) and Biomedical Advanced Research and Development Authority (BARDA), are becoming more involved in the healthcare sector. Implementing and using EVMS is a baseline requirement for biotech and pharmaceutical firms awarded large contracts by the Federal Government.

This will require companies and universities that receive funding to understand and implement Earned Value Management and that key project personnel, including management and executives, will require high quality Earned Value Training.

Why EVM and Government Contracts

Earned Value Management has been used since the 1960’s and has become the standard by which the Government measures and evaluates the management and reporting processes on projects awarded to contractors. Initially, it was implemented on projects; such as the development of satellites, long-range missiles, fighter aircraft, etc., but has become the US Government’s gold standard to manage the technical, schedule and cost progress of projects and to identify and manage risk and opportunities.

In order for defense contractors to be eligible for large contracts, they are required to follow the 32 Guidelines of the EIA-748-C which can entail system design and development and a substantial learning curve. Earned Value Management company-wide training and proper implementation becomes critical for project efficiency, future funding and to meet Government requirements.

Integral to EVM are the uses of the Integrated Master Plan (IMP)/Integrated Master Schedule (IMS) and risk and opportunity management.  The Integrated Master Schedule is the basis for developing the Performance Measurement Baseline (PMB) which in turn, is the basis for measuring performance on a project.   Measurement of progress against the baseline provides early identification of problems and helps to identify and mitigate costs and risks, while also identifying opportunities, by implementation of appropriate corrective actions.

Earned Value Management Systems for Project Management

The basic concept of the Earned Value Management System is more than a unique project management technique.  The EIA-748-C contains 32 Guidelines that define a set of requirements that a contractor’s management system must meet. The objectives of an EVMS are:

  •  Relate time phased budgets to specific contract tasks and/or statements of work
  • Relate technical, schedule and cost performance information
  • Furnish valid, timely and auditable data/information for proactive management action and decision making
  • Provide the basis to capture work progress assessments against the baseline plan to facilitate realistic project costs and completion dates
  • Supply managers with a practical level of summarization for effective decision making

Once a contractor’s EVM System is designed and implemented, there are significant benefits to the contractor and to the customer:

  • Contractor benefits include increased visibility and control to quickly and proactively respond to issues which makes it easier to meet project technical, schedule, and cost objectives
  • Customer benefits include confidence in the contractor’s ability to manage the project, early problem identification, and objective rather than subjective contract cost and schedule status

Earned Value Management Training

Experienced project managers will tell you that understanding the scope, schedule and costs of a project is essential to its success. The primary objective of the EVMS is to ensure that all elements of a project are planned, authorized, managed, and controlled in a consistent and cost-effective manner.  There is an increasing demand for training for organizations beyond the traditional aerospace and defense related construction, software, research and development, and production environment to now include non-defense companies to implement and use the Earned Value Management System.

EVM for Biotech and Pharma

Biotech and Pharma companies are not strangers to dealing with government regulations and requirements. Most have gone through rigorous Food and Drug Administration (FDA) processes to receive approval of compounds and/or devices. Nonetheless, learning how to design and use an EVM system can take a considerable investment of time and money, but is an essential requirement for initial and ongoing funding.

In addition to the EIA-748-C, there are numerous documents that give direction regarding the implementation and use of an EVM system.  Some of these are the National Defense Industrial Association (NDIA) Integrated Program Management Division (IPMD) EIA-748 Intent Guide, Cost Accounting Standards (CAS), Data Item Descriptions (DID), Military Standards (MIL-STD) such as MIL-STD-881, the Earned Value Management System Interpretation Guide (EVMSIG), and many others.  We have helped many organizations to ensure that they do not overkill or underkill based on their desired management system characteristics.  H&A personnel understand the requirements and are able to “size” those requirements to meet company and customer requirements.

Although Biotech and Pharma are relatively recent industries to use EVM, Humphreys & Associates (H&A) has been providing Earned Value Management training and implementation services for over 35 years. H&A provides self-paced online, classroom and private training courses, and can assist in all aspects of Earned Value Management Implementation.

For more information about EVM training or support, or with questions about your company’s requirements, please contact the Humphreys & Associates corporate office.

EVM for Biotech and Pharma – Part I Implementation and Training Read Post »

Aligning ACWP with BCWP for Proper EVM | Earned Value Management

, , , ,

Last Updated May 22, 2025

ACWP and BCWP by DAU

What is estimated Actual Cost of Work Performed (ACWP)?

Estimated ACWP is an adjustment to the actual cost data imported into the EVM cost tool as the Actual Cost of Work Performed (ACWP) to align ACWP with Budgeted Cost for Work Performed (BCWP).  Estimated ACWP is synonymous with “estimated actuals.”

Why is Estimated ACWP necessary?

Without Estimated ACWP, timing mismatches between ACWP and (BCWP) cause false cost variances to be calculated in the EVM cost tool as well as from the data in the Integrated Program Management Data Analysis Report (IPMDAR) Contract Performance Dataset (CPD).  Typically these variances are favorable and can mask other unfavorable variances.  Additionally, if these variances exceed reporting thresholds, the explanations clutter the IPMDAR Narrative Report with variance explanations that discuss timing problems of the accounting system rather than actual performance issues.

When should Estimated ACWP be used?

Estimated ACWP is most typically required for material costs.  For example, when BCWP is claimed upon receipt of the material, the payment for accrued costs in the accounting system typically occurs one or more months following material receipt, which creates the timing mismatch between BCWP and ACWP in the EVM cost tool.  Other cost element types that may require Estimated ACWP include subcontracts and Other Direct Costs (ODC).  Examples of ODCs that may require Estimated ACWP include staff augmentation, purchased labor, and travel.

How does Estimated ACWP function?

Receipt-type material:

  1. First, a determination must be made whether Estimated ACWP is necessary.  For some categories of material, when a material item is received, the BCWP is claimed in the EVM cost tool.  If actual costs for the materials do not enter the accounting system in the same period that the BCWP was claimed, Estimated ACWP is necessary to ensure ACWP occurs when BCWP occurs.
  2. Second, the Estimated ACWP adjustment is entered into the EVM cost tool as a current period transaction.  The amount of the Estimated ACWP is based on the best information available for the material item (often accrued costs in the accounting system) using the invoice, purchase order, or receiving report.
  3. Third, the Estimated ACWP adjustment transaction is reversed in the EVM cost tool when the actual costs are recorded in the accounting system; this could be the following reporting period or later.  If actual costs were to come in that month and the transactions were not reversed, the ACWP would be double-counted when the actual cost data from the accounting system is imported into the EVM cost tool. Also, the Estimated ACWP transaction should be recorded in a log to maintain traceability. 

Production-type (inventory) material:

For production type materials, or materials that are common to many control accounts or even contracts, that go into inventory, earned value is claimed upon issuance from inventory, sometimes several months after receipt of the material and after the incurrence of actual costs in the accounting system.  In this case, the opposite condition would exist.  The accounting actuals occur before earned value is claimed for material. The EVM rules in the EIA-748 Standard for EVMS Revision D Guideline 21 or Revision E Guideline 14 (and common sense) state that ACWP is not to occur until BCWP takes place.  Therefore, the accounting actual costs have to be “suppressed” from entering the EVM cost tool until material earned value is claimed. Since some companies say they cannot suppress actual costs, they let the actual costs enter the system, but make an off-setting “Negative Estimated ACWP” entry in the EVM cost tool until the material is issued and BCWP can be claimed for the material.

Do you need to implement an Estimated ACWP process in your Earned Value Management System?  Humphreys & Associates has the earned value experts to assess your material management processes and to help you implement the appropriate procedures. Contact us today.

Aligning ACWP with BCWP for Proper EVM | Earned Value Management Read Post »

Scroll to Top