Government Agencies

Introduction to the Cost and Software Data Reporting (CSDR) Reporting Requirements

, , , ,

A common client request is to assist them with sorting through the various DoD contractual reporting requirements and contract value reporting thresholds that apply. We frequently run into situations where a contractor needs clarification on why they have a Cost and Software Data Reporting (CSDR) requirement and whether they should seek to waive the requirement. Subcontractors to a prime often question the requirement to provide actual cost data directly to the DoD, especially for Firm Fixed Price (FFP) contracts.

Background

CSDRs are the primary means the DoD uses to collect data on the development, production, and sustainment costs incurred by contractors performing DoD acquisition contracts. It is a DoD system for collecting actual costs, software data, and related business data. The resulting data repository serves as the primary source for contract cost and software data for most DoD resource analysis efforts including cost database development, applied cost estimating, cost research, program reviews, analysis of alternatives (AoAs), and life cycle cost estimates.

CSDR reporting requirements are determined by the contract value regardless of the acquisition phase and contract type. In general, CSDR reporting is required for Acquisition Category I-II programs and Information System (IS) programs valued at more than $50M. They can also be required for Middle Tier Acquisition programs (greater than $20M) and other programs (greater than $100M). Risk can also be a determining factor regardless of the contract value.

DoD Instruction (DoDI) 5000.73, Cost Analysis Guidance and Procedures (March 2020), provides additional details about the cost data reporting. Table 1 in the 5000.73 lists the cost reporting requirements contract value thresholds. The DoD Manual 5000.04 Cost and Software Data Reporting (May 2021) is the primary requirements document for the development, implementation, and operation of the DoD CSDR system to ensure data reported is accurate and consistent.

About CADE

The Office of the Secretary of Defense Cost Assessment and Program Evaluation (OSD CAPE) established the Cost Assessment Data Enterprise (CADE), a secure web-based information system that hosts the controlled unclassified CSDR repository, the Defense Acquisition Cost Information Management System, and the forward pricing rate library. CADE also contains a selected acquisition report database, a contracts database, data analytics capabilities, and a library containing cost estimating content such as cost analysis requirement descriptions and cost estimates. CADE is access-controlled, and available through the public-facing CADE Portal website.

Similar to the cost estimating and proposal pricing functions within contractor’s organizations that rely on historical actual costs to assess the validity of a proposed cost estimate, independent and sound cost estimates are vital for effective DoD acquisition decision making and oversight. CADE plays a critical role in capturing the expenditure, technical, and programmatic data after contract execution in a consistent manner to enable independent cost estimating and analysis. This cost estimate data is essential to support efficient and effective resource allocation decisions throughout the planning, programming, budgeting, and execution process for the DoD.

CSDR Reporting Requirements

There are a series of Data Item Descriptions (DIDs) for this reporting requirement.  Some forms are submitted electronically using DoD defined XML schemas, Excel, or JSON encoded data in accordance with a File Format Specification (FFS) and Data Exchange Instruction (DEI). The list of DIDs are as follows. These DIDs can be downloaded from the CADE website.

  • Contract Work Breakdown Structure, DI-MGMT-81334D (May 2011).
  • Cost Data Summary Report, DI-FNCL-81565C (May 2011), DD Form 1921, XML Schema.
  • Functional Cost-Hour Report, DI-FNCL-81566C (September 2015), DD Form 1921-1, XML Schema.
  • Progress Curve Report, DI-FNCL-81567C (May 2011), DD Form 1921-2, XML Schema. 
  • Sustainment Functional Cost-Hour Report, DI-FNCL-81992 (May 2011), DD Form 1921-5, XML Schema.
  • Contractor Business Data Report, DI-FNCL-81765C (March 2021), DD Form 1921-3, Excel. 
  • Software Development Report, DI–MGMT-82035A (October 2022), DD Form 3026-1, XML Schema. 
  • Software Maintenance Report, DI–MGMT-82035A (October 2022), DD Form 3026-2, XML Schema.
  • Enterprise Resource Planning (ERP) Software Development Report, DI-MGMT-82035A (October 2022), DD Form 3026-3, XML Schema.
  • Cost and Hour Report (FlexFile), DI-FNCL-82162 (November 2017), JSON encoded data file following FFS and DEI.
  • Quantity Data Report, DI-MGMT-82164 (November 2017), JSON encoded data file following FFS and DEI.
  • Maintenance and Repair Parts Data Report, DI-MGMT-82163 (November 2017), Excel.
  • Technical Data Report, DI-MGMT-82165 (November 2017), Excel.

The Cost and Hour Report (FlexFile) and Quantity Data Report play a critical role in collecting cost data from contractors for the DoD data repository because they use JSON data encoding to organize the content. They are intended to replace the legacy 1921 series of paper-based formats including the DD 1921, 1921-1, 1921-2, and 1921-5. It also requires contractors to provide significantly more historical cost data than the 1921 formats. As a result, the DoD cost estimating community has additional insight into historical costs. The goal is to establish a common framework and standard nomenclature to collect data from different contractors, all of them with unique cost accounting structures, that are mapped to the DID, FFS, and DEI requirements for use in the data repository.

Establishing a Consistent, Repeatable Process to Produce the CSDR Data Deliverables

For contractors new to the CSDR reporting requirements and in particular, the FlexFile JSON data encoding, can appear to be daunting. That’s where software tools such as those from Midnite Dynamics can help. Midnite Dynamics specializes in assisting contractors with producing the CSDR data deliverables. 

Their software tool, C*CERT+, streamlines, automates, validates, and produces the legacy 1921 family of Excel and XML reports as well as the FlexFile and Quantity Data Report JSON submittals. C*CERT+ eliminates what otherwise is a manually intensive, resource draining, tedious and costly effort subject to recurring rejections. It is one thing to create the required legacy reports or FlexFile JSON files for submittal, it is another to pass the submittal validation process. C*CERT+ provides numerous data validations and analysis reports to ensure the data is 100% compliant before it is submitted. For example, the software includes over 90 FlexFile validations to ensure data compliance as illustrated in Figure 1.

Figure 1: Example of FlexFile data validation results.
Figure 1: Example of FlexFile data validation results.

The software includes a Validation and Remarks utility to analyze the source data details that could result in a Validation Trip. Remarks can be entered directly into the validation module for anything that requires an explanation. This is illustrated in Figure 2. This narrative is included with the data submittal.

Figure 2: Example of providing remarks about the FlexFile data content.

C*CERT+ also interfaces with existing EVM cost tools and accounting systems to produce the existing legacy 1921 reports, the FlexFile, and other data submittals as well as to consolidate separate projects/CLINs/task orders into a single contract report.

Once the C*CERT+ Standard Category Mapping Rules are set up, they can be shared throughout the corporation or business unit to establish a standard and repeatable process for producing the data deliverables. This mapping process translates the contractor’s source data into an output that matches the CSDR data submittal format rules. This saves a tremendous amount of time and makes it much easier to consistently produce the CSDR data deliverables. An example of the Mapping Rules is illustrated in Figure 3.

Figure 3: Mapping Rules translate contractor unique cost data into a format that matches the CSDR data submittal requirements.

Do your process and procedures or training materials need an update to include specific guidance for project control teams to produce required DoD contractual reports or data submittals using your tool sets of choice? Give us a call today at (714) 685-1730 to get started. 

Introduction to the Cost and Software Data Reporting (CSDR) Reporting Requirements Read Post »

Humphreys and Assoc Reviews 7 Principles of Earned Value Management Tier 2 System Implementation Intent Guide

, , , , , , ,

In this video we review the 7 Principles of Earned Value Management Tier 2 System Implementation Intent Guide published by the Assistant Secretary for Preparedness and Response, or ASPR.

This Guide is primarily used by the Biomedical Advanced Research and Development Authority, or BARDA, on countermeasure R&D contracts that have a total acquisition cost greater than $25 million and a Technical Readiness Level of less than 7.

7 Principles of Earned Value Management Tier 2 System Implementation Intent Guide -- EVM Cross Reference Guide

Humphreys and Assoc Reviews 7 Principles of Earned Value Management Tier 2 System Implementation Intent Guide Read Post »

EVM (Earned Value Management) vs. Agile Project Management

, , , , , , , , , , , , ,

This article provides an introduction to the differences between an Earned Value Management System (EVMS) and Agile approaches on projects, and isolates the challenges of implementing an EVMS on a project where the project management has chosen to follow an Agile approach to the development work. The article explores the principles of EVMS and of Agile, and contrasts them to show where there are inherent conflicts. The article then discusses how the conflicts can be mitigated so that the benefits of both the EVMS and Agile can be obtained from a joint implementation.

Controlled Planning with EVMS

Controlled Planning with EVMS

Earned Value Management (EVM) Background

Earned Value Management is a 50 +/- year old methodology based on widely accepted principles that applies documented, systematized practices to support the processes of organizing, planning, directing, and controlling large complex projects, of any nature, which contain a high degree of uncertainty.

An EVMS is structured compliant to 32 guidelines that define what a project management information system should be capable of doing to support the program management team. Within the 32 guidelines there is a subset of generally recognized core principles. The core principles are:

  1. Organize the entire scope of the project using a Work Breakdown Structure (WBS).
  2. Organize the project team using an Organization Breakdown Structure (OBS).
  3. Integrate the project work with the project team to create management control points (Control Accounts).
  4. Schedule the project work in the Control Accounts across the entire project duration at the appropriate level of detail.
  5. Establish time-phased budgets for the scheduled work in the Control Accounts.
  6. Establish the scope/schedule/budget baseline as the Performance Measurement Baseline (PMB).
  7. Authorize the scope/schedule/budget and control the start/stop of work.
  8. Periodically measure the schedule and the value of completed work and determine the Earned Value.
  9. Record direct costs (actual costs) and summarize into the Control Accounts.
  10. Compare planned, accomplished, and spent to analyze the performance and associated variances.
  11. Develop realistic time and cost estimates for the remaining effort in the Control Accounts.
  12. Rigorously control changes to the Performance Measurement Baseline.

The EVM concept presented in these guidelines is a sound management approach, that once incorporated on any type of program, whether research and development, construction, production, etc. provides all levels of management with early visibility into cost and schedule problems.  Earned Value Management now appears as a contractual requirement on programs world-wide.  Primary EVM users include the United States, Europe, England, Canada, Australia, China, and Japan. It is a requirement of many U.S. Government agencies, including the Department of Defense (DoD), the National Aeronautics and Space Administration (NASA), the Department of Energy (DOE), the Intelligence Community, the Department of Homeland Security (DHS), the Federal Aviation Administration (FAA), the Department of Transportation (DOT), Health and Human Services (HHS), and others.

EVMS has been adopted by companies in situations where it is not a contractual requirement so that they can gain the discipline and benefits of the structural management approach discussed in the guidelines.

 

evms 2

Flexible Planning with Agile

Agile Background

Agile is a 20 +/- year old approach to applying a mindset that values the use of small, empowered, self-organizing, multi-functional teams, mainly in software development, to establish a test driven product development effort. This uses a series of short, rapid incremental builds within projects with a high degree of uncertainty to achieve shorter development times, lower costs, and products more closely aligned with customer requirements.

Agile does not usually appear as a contractual requirement. The concept is adopted by companies and organizations with the belief that a better product will be produced faster, and with less expense, using this approach than if traditional approaches were followed.

There are a core set of principles for Agile that were initially established in the copyrighted Agile Manifesto. These delineated core principles are:

  1. Early and continuous product delivery.
  2. Deliver working software (product) frequently.
  3. Expect change and respond positively to change.
  4. Developers and project business organization (PMO) work together.
  5. Product-focused build teams are at the core.
  6. Support self-organizing teams – trust among peers.
  7. Encourage face-to-face discussions (involve the user/customer).
  8. Working software is the measure of progress.
  9. Maintain a constant sustainable pace of development.
  10. Simplify the process and the product.
  11. Put the highest value on technical excellence.
  12. Improve team effectivity.

So How Does Agile Work?

The Agile mindset or approach is implemented through a process of defining the product backlog into smaller and smaller subsets of work that are structured in a top down fashion. At the lowest level of product backlog, the work elements or requirements can be prioritized and assigned to teams. The self-organizing teams pull work from the backlog and work the tasks to completion in a series of short, time-fixed Sprints or iterations. Sprints are often from 2 to 4 weeks long.

Because the teams are self-organizing, there is no team manager or team lead. The teams work as a group and only pull from the backlog at the last possible minute, and do minimal planning for each Sprint. If the product backlog is properly deconstructed and defined into user stories, then the planning meeting for an entire 4 week Sprint can be accomplished in a few hours.

The teams design, code, test, integrate, and deliver functionality in every Sprint. Since tested product is output every few weeks, all on the project can see the product being created and can contribute along the timeline, as needed, to provide a complete finished product.

The product owner embodies the customer’s perspective and either accepts or rejects the team’s work.  At the latter point of each Sprint, the tested product is demonstrated to the product owner.

High Level Side-by-Side

The two approaches are contrasted in the chart shown below. The EVMS is a methodology that is highly documented and highly systematized, while Agile is just the opposite. It is more of a mindset than a methodology with the preference not to have significant process documentation.

The EVMS is applied to entire projects and contracts, while generally Agile is applied to software portions of projects.  However, it could also be used on other development work.

The EVMS is usually a contractual requirement with significant implementation and operation constraints while Agile has none of these. As a contractual requirement, the EVMS carries with it the option for customer reviews and the threat of non-compliance, which entails penalties.

EVM Agile
Methodology Mindset
Documented Self-defined
Systematized Self-defined
Any type of project Software development (mainly)
High degree of uncertainty High degree of uncertainty
Applied to the entire project Applied to portions of the project
Often a contractual requirement Adopted not required

Lower Level Side-by-Side

In addition to the high level side-by-side, there are significant differences within the details of the two approaches. These are shown in the side-by-side table below.

Agile EVMS
Minimal documentation More documentation
Plan at last moment Plan ahead to end of project
Scope is flexible Scope is baselined and controlled
Expect and embrace change Avoid and/or control change
Schedule (Sprint) is fixed.  Timebox ends the Sprint. End the package when the work is done.
Budget is secondary Budget is baselined and controlled
Cost collection is not mentioned. Cost collection at the right level is critical

Accommodate and Capitalize on Differences

It is possible to implement Agile along with an EVMS if the EVMS application is set up to accommodate the differences and capitalize on them.

For example, the main reason that Agile’s embrace of change is a potential problem within an EVMS is because often the EVMS is used to plan too far in advance, and then reacting to change is difficult and expensive. If short term planning in the EVMS can be coordinated with the Agile planning, then the two can coexist.

The Agile free acceptance of scope changes within the backlog runs counter to the EVMS imposition of baseline change control. But if the EVMS baseline can be carefully set at a work level above the busy lowest level ups and downs, the impact to baseline change control is manageable.

A surprising chance to capitalize on Agile, within the EVMS, is found in the Scrum team approach in Agile where the team breaks work down into tasks far below what would normally be done in an EVMS, and then meets daily to update progress and provide corrective action. This low level constant attention means that the EVMS benefits from a better look at real progress as assessed by the real performers.

Not all the compromise needs be on the EVMS side of the equation. The Scrum team operations will often be defined to have the least possible recording of what happens during the Sprint. Since the product is king, then only the product really matters. But that misses the opportunities to capture the actions of the team for analysis, and use in upgrading their skills later. Necessary compromises would include some additional recording of the daily actions of the team and capturing the progress and problems. These would then be used in the EVMS functions of performance measurement, variance analysis, and corrective action planning.

One other compromise in the Agile realm that would be needed is the adoption of some minimum documentation of processes so that team operations can be repeatable and stable. Even a self-organizing team cannot change the way they work every time it wishes. That would raise the risk of a chaotic work environment.

These topics are recapped in the table below.

Agile EVMS Accommodation
Scope is flexible Select a higher level package for the baseline
Change is expected and embraced Have the shortest possible planning horizon
Plan at the last possible minute Have the shortest possible planning horizon
Daily Scrum Stand-up Meeting Collect the data and use it for performance measurement
Sprint Review Meeting Use for periodic measurement and analysis
Sprint Retrospective Meeting Use in Corrective Action Plans
Lack of documentation Add minimum documentation to stabilize team operations

Bottom Line

Implementing an EVMS is a challenge itself. Implementing Agile is a challenge too; perhaps a more difficult challenge. Implementing the two approaches side-by-side can seem impossible. But it is possible and even beneficial if done in a way the makes needed accommodations in both arenas for the project’s benefit.

EVM (Earned Value Management) vs. Agile Project Management Read Post »

Clarification on the New Department of Defense Earned Value Management System EVMS Thresholds | DOD & DPAP

, , , , , , , , , , , , , , , ,

New Department of Defense Earned Value Management System (EVMS) ThresholdsOn September 28, 2015, the Defense Procurement and Acquisition Policy Directorate (<abbr=”Defense Procurement and Acquisition Policy Directorate”>DPAP) released a memorandum entitled “Class Deviation – Earned Value Management System Threshold”. In this memo the DoD changed the threshold for <abbr=”Earned Value Management System”>EVMS application to $100 million for compliance with EIA-748 for cost or incentive contracts and subcontracts. That same memorandum stated that no EVMS surveillance activities will be routinely conducted by the Defense Contract Management Agency (<abbr=”Defense Contract Management Agency”>DCMA) on contracts or subcontracts between $20 million to $100 million. As attachments to this memorandum, there was a reissuance of the Notice of Earned Value Management System <abbr=”Department of Defense Federal Acquisition Regulations”>DFARs clause (252.234-7001) and the Earned Value Management Systems DFARs clause (252.234-7002), with both reflecting the new $100 million threshold.In response to this guidance, a series of questions from both contractors and other government personnel were submitted to Shane Olsen of the DCMA EVM Implementation Division (<abbr=”EVM Implementation Division”>EVMID). Below are the salient points from this communication:

  • There will be no EVMS surveillance of DFARs contracts under $100 million. Contracts without the DFARs clause, such as those under other agencies using the FAR EVM clause, will continue surveillance under their current thresholds.
  • The $100 million threshold is determined on the larger of the contract’s Ceiling Price or Target Price; as reported on the Integrated Program Management Report (IPMR) or Contract Performance Report (CPR) Format 1.
  • The threshold is based on the Contract Value including fee (at Price) as noted above. If there is an approved Over Target Baseline (OTB) which increases the Total Allocated Budget (TAB), this cannot push a contract over the threshold.
  • The new thresholds not only apply to subcontracts, but also Inter-organizational work orders with an EVMS flow-down.
  • Regardless of the circumstances, the DCMA will not conduct surveillance on contracts less than $100 million. However, if there are Earned Value issues that the buying command or other parties believe need to be reviewed, then the DCMA may conduct a Review for Cause (RFC) of the system against potentially affected guidelines.
  • The DCMA Operations EVM Implementation Division (EVMID) will not be conducting Compliance Reviews in FY-2016 unless there is an “emergent need”.
  • If a site is selected for a Compliance Review, only contracts greater than $100 million would be in the initial scope of the Implementation Review (IR). However, if an issue is discovered that requires the team to “open the aperture”, other contracts are not precluded.

The DCMA is still working on a response to the following questions:

  • How do I handle a contract that is currently below $100 million but has options that, in aggregate, would exceed $100 million?
  • How is the contract value determined on:
    • Indefinite Delivery/Indefinite Quantity (ID/IQ) Contracts
    • Non-ID/IQ with Multiple CLIN-Level or Task Order reports?

This blog will be updated and reposted as answers to these questions are given.

Clarification on the New Department of Defense Earned Value Management System EVMS Thresholds | DOD & DPAP Read Post »

Earned Value Management Implementation Guide (EVMIG) Rescinded

, , , , , , , ,

Earned Value Management Implementation Guide (EVMIG) Rescinded | DFARSThe DoD EVM Implementation Guide (EVMIG, Oct 2006) was rescinded on September 15, 2015 by the Office of Performance Assessments and Root Cause Analysis (PARCA). The EVMIG had provided guidance for understanding Earned Value Management System (EVMS) concepts; detailed procedures for implementing the EIA-748 EVMS Standard, Earned Value Management Systems (EVMS), on government contracts; tailoring guidance for EVMS application and reporting; and post award procedures. Most of the details contained in the EVMIG are also available in other, more recent, publications and the EVMIG is replaced with these other references. EVM System information can be found in the DoD EVM System Interpretation Guide (EVMSIG) which provides overarching DoD interpretation of the 32 EIA-748 EVMS guidelines. Additional information can be found in multiple Defense Contract Management Agency (DCMA) compliance instruction documents.

PARCA identified the following references to replace the contents and guidance found in the EVMIG:

EVM Concepts and Guidelines
EVM Concepts TBD EVM Analysis Guide
Defense Acquisition University (DAU) EVM Community of Practice
PARCA EVM Website
EVM System (EVMS) Concepts EVMSIG
DCMA Surveillance Guide

 

Procedures For Government Use of EVM
Organizational Roles and Responsibilities TBD EVM Application Guide
PARCA EVM Website
Defense Acquisition Guide (DAG)
WBS Development and Use MIL-STD-881C
TBD EVM Application Guide
EVM/EVMS Policy and Application TBD EVM Application Guide
PARCA EVM Website
Cost and Schedule Reporting Integrated Program Management Report (IPMR) Data Item Description (DID) and IPMR Guide
TBD EVM Application Guide
EVMS System Compliance EVMSIG
DCMA Surveillance Guide
Integrated Baseline Review (IBR) Program Manager’s Guide to the Integrated Baseline Review (IBR)
TBD EVM Application Guide
Reprogramming Formal Reprogramming Over Target Baseline (OTB)/Over Target Schedule (OTS) Guide
EVMSIG
Training Defense Acquisition University Website
PARCA EVM Website

Earned Value Management Implementation Guide (EVMIG) Rescinded Read Post »

Management Reserve; Comparing Earned Value Management (EVM) and Financial Management Views of “Reserves”

, , , , , , , , , ,
Management Reserve & Earned Value ManagementPerhaps you have witnessed the collision of earned value management’s views on “management reserve” with the Chief Financial Officer (CFO) and the finance department’s views on “balance sheet reserves.” Most companies tend to organize EVM, the function, reporting to either the programs’ organization or to the finance organization. Either will work but either can fail if the two organizations do not understand the interest of the other.

In this article we will outline three areas. The first will be EVM and Management Reserve (MR). The second will be finance and balance sheet “contingencies, loss provisions, or reserves.” The third will compare the two views and identify where they are similar and where they differ.

We will use two terms for both EVM and Financial Management; “in play” and “on the sideline.” “In play” for EVM means that it is in your Performance Measurement Baseline (PMB) and Budget at Completion (BAC). “On the sideline” for EVM means “not in scope” therefore in MR. “In play” for financial management means recorded on the balance sheet (e.g.: current liability; an accrued liability). “On the sideline” for financial management means not recorded on the balance sheet, because it is more likely than not that a liability has been incurred.   If material, however, it will likely be disclosed in the notes to the financial statements, even if it is not recorded on the balance sheet.

 

Earned Value Management and Management Reserve

A program manager and his or her team must deal with – mitigate – risk or be consumed by those risks as they become issues. There are two types of risks, known and unknown. The known risks are entered into a risk register, and their likelihood and consequence are determined. Mitigation for those known risks is done at the activity level in a program’s Integrated Master Schedule (IMS) (Planning and Scheduling Excellence Guide — PASEG page 141, ¶ 10.3.1). Mitigation of known risks is part of the PMB (in the BAC) and is therefore “in play.”

The second type of risk – unknown or unknowable risks – are covered by management reserve if within the Scope of Work (SOW) of the existing contract. If contractor and customer conclude that the realized risk is outside the existing contract, then an Engineering Change Proposal (ECP) would likely be created by the contractor; and a contract modification would be issued by the authorized customer contracting officer if they agreed.   The program manager should ask this question of his team: what work is “at risk” and what work is not “at risk?” Does labor or material present more risk? Management reserve “is an amount of the overall contract budget held for management control purposes and for unplanned events” (Integrated Program Management Report–IPMR DI-MGMT-81861 page 9, ¶ 3.2.4.6). Management reserve is “on the sidelines.” MR has no scope. MR is not earmarked. MR stands in waiting.

 

Earned Value Management Reserve (MR) Compared To Financial Management “Contingency”

Because the audience reading this blog is most likely from the EVM community, I’ll offer a Financial Management example of a company that faces many risks and must manage those risks or be consumed by them. Altria Group, Inc. and Subsidiaries (stock symbol: MO) are in the tobacco, e-Vapor and wine business. Altria’s history clearly shows that the company measures and successfully mitigates the risks they face. Altria faces a blizzard of litigation each year and must protect its shareholders from that risk. So how does Altria manage known risks (mostly from litigation) and how does Altria handle unknown risks?

Altria is a publicly traded company and its annual report (10K) is available on-line to the public. This data is from their 2014 annual report.

I am an MBA, not a CPA, so I’ll stick to Altria’s 2014 balance sheet. For those not familiar with financial statements, a balance sheet has on its left hand side all of a company’s assets – what the company owns and uses in its business (current assets = cash, accounts receivable, inventory; long term assets = property, plant and equipment). The right hand side of a company’s balance sheet shows current and non-current liabilities and shareholders’ equity. The top right hand side of the balance sheet includes current and non-current liabilities (accounts payable, customer advances, current and long-term debt, and accrued liabilities like income taxes, accrued payroll and employee benefits, accrued pension benefits and accrued litigation settlement costs) and the bottom of the right hand side of the balance sheet includes shareholders’ equity consisting of common and preferred stock, paid in capital and retained earnings.

Altria’s 2014 annual report shows under current liabilities; accrued liabilities; settlement charges (for pending litigation Contingency note # 18) a value of $3.5 billion dollars. The 2013 amount was $3.391 billion dollars.

So Altria has “in play” $3.5B for litigation for 2014. In financial terms, Altria has recorded $3.5 billion in expense related to the litigation, probably over several years as it became more likely than not that a liability had been incurred and was reasonably estimable. In EVM terms Altria has $3.5B in their baseline, or earmarked, or in scope for litigation (court cases).

What happens if Altria ultimately has more than $3.5B in litigation settlement costs? What does Altria have waiting on the “sidelines” to cover the unknown risks? Essentially Altria has on its balance sheet waiting “on the sidelines” $3.321 billion in cash and the ability to borrow additional funds or perhaps to sell additional shares of stock to fund the settlement costs. In EVM terms Altria has $3.5B in its baseline (on its balance sheet) to manage the risks associated with litigation. Altria’s market capitalization at the market close on May 17, 2015 was $52.82 billion and its 2014 net revenues were $24.522 billion. It is reasonable to understand that Altria has more than enough MR.

 

Differences Between EVM MR and Financial Management Balance Sheet Reserves

In EVM, MR is only released to cover unplanned or unknown events that are in scope to the contract but out-of-scope to any control account. A cost under-run is never reversed to MR, and a cost over-run is never erased with the release of MR into scope.

In industry in general, and Altria in particular, if the “in play” current liability for settlement charges of $3.5B are not needed (an under-run), then Altria will reverse a portion of the existing accrued liability into income, thereby improving profitability. If Altria’s balance sheet reserve of $3.5B is insufficient, then Altria’s future profits will be reduced as an additional provision will be expensed to increase the existing reserve (an over-run).

[Humphreys & Associates wishes to thank Robert “Too Tall” Kenney for authoring this article.]

Management Reserve; Comparing Earned Value Management (EVM) and Financial Management Views of “Reserves” Read Post »

Scroll to Top