Integrated Master Schedule (IMS)

EVM Consulting – Modeling & Simulation

, , , , , , , , ,

Fighter Jet Air Plain Flying in Front of Moon

Forewarned is Forearmed

Forewarned is forearmed. John Farmer, of New Hampshire, said that in a letter in 1685. But that advice is most likely biblical and very much older. No matter the source of the thought, we should take it as divine guidance if we are project managers. Maybe we should have it cut into a stone tablet, so we can share it with our team members.

Most of our work as project managers is spent in the “controlling” phase which is made up of the three steps “measure, analyze, act.” Our EVMS and IMS exist to be able to support this management function. The measuring part is done very well in our EVMS and our IMS; we know where we are and how we got there. The analyzing is equally well handled in the IMS and EVMS. Only the management task of acting is not well supported. Generally, we lack decision making support and tools.

EVM Consulting - Measure, Analyze, Act

Deterministic Path

No matter how well constructed and how healthy our IMS is, it has a deterministic path forward. The logic links between the activities are there because we expect them to be fulfilled. Indeed, if activity “B” is a finish-to-start successor to activity “A” we fully expect that at some point activity “A” will finish and will provide its output to activity “B”. That is a single path forward and it is a deterministic path. It is also a somewhat simplistic model.

EVM Consulting - Deterministic Relationships in EVMS

Multiple Outcomes

Our management system asks us to perform root cause analysis followed by corrective action. But what if there is more than one corrective action to be taken. And worse; what if the corrective actions can have multiple outcomes with each enjoying its own probability. That means multiple choices and multiple outcomes. How would we show that in our plan? How would we analyze the multiple possible futures that such a situation presents?

Happily, there are ways to model a future without a set path. And once we have the future model, there are also ways to simulate the outcomes to give the probabilities we need to decide which actions to take. We are talking about probabilistic branching, and we are saying that we can build a probabilistic map of the future to use in making decisions; especially making decisions on corrective actions.

Take a simple example of running a test on the project. The expectation is that eventually we will pass the test. We will keep trying until we do. In the IMS deterministic model the test portion of the IMS might look like this:

EVM Consulting - Run the Test then Use the Product

Simulation

We can simulate this situation with different expected durations for the test. That is helpful information, but it does not explain or even capture what is going on in those different durations. It looks like we are just taking longer to do the testing but is that really what is happening? What is going on here? We certainly don’t show that.

In the real world, this simple model might have three potential outcomes. There might be three paths we can take to get to the point where we use the product. Each path has a time and money cost. We might run the test and find that we passed. Or we might have to stop the test for issues on the item or the test setup. We might even fail the test and must correct something about the product to improve our chances of passing a rerun. Eventually we will get to a usable product. But what do we put in our estimate and our plan? What do we tell the resources we need? What do we tell the boss? The customer?

EVM Consulting - Real World Testing

Full Future Model

We now have a much better understanding of the future and can explain the situation. We also can simulate the situation to find out the most likely time and cost outcomes, so we can explain the future without any histrionics or arm waving.
If the issue is important enough we can build out the full future model and simulate it.

EVM Consulting - Full Future Model and Simulation

No matter how far we pursue the model of the future, having a valid model and being able to stand on solid ground are very valuable to us as project managers.

This is not to say that we should model out complex situations as a routine in the IMS. That would be impossible, or at least prohibitively costly. We are saying that when situations arise, we need to be able to use the IMS to help us make decisions.

This type of probabilistic modeling of the future is particularly useful in defining major decision points in our plan. When we reach a decision point the IMS may have multiple branches as successors but that implies we take every branch and that is not valid. Modeling each branch and its probabilities is valid. In the example below, where the milestone represents a decision point, we have shown three possible paths to take. If each were modeled out into the future with time and cost data, we should have the information we need to choose the path we wish to pursue. Without processes and tools like this, we would be flying blind.

Future Blog Posts

This discussion will be continued in future blogs to develop a better foundational understanding of the process and power of probabilistic modeling in our EVMS.

EVM Consulting - Decision Point

Good information sets the stage for good decisions. The IMS and the EVMS have sufficient information to help us model the pathways ahead of our critical decisions. We just need to learn to take advantage of what we have available to us.

Find out how an experienced Humphreys & Associates EVM Consultant can help you create a full future model and simulation of your most vital EVMS Systems. Contact Humphreys & Associates at (714) 685-1730 or email us.

EVM Consulting – Modeling & Simulation Read Post »

Project Management: Earned Value Consulting; Could You Use Some?

, , , , ,

Failed Projects

A recent article discussed the results of a survey on the reasons that projects failed. The definition of failure was that the project was abandoned. Abandonment does not occur frequently in the world of government projects; especially defense projects where there should be strong “must have” needs driving the project. These projects tend to persist until completed even though the outcomes are not satisfactory. But there is a lot to learn from the list of reasons for failure.

Of the sixteen reasons listed, the top four had to do with changes to the environment that had given rise to the project. For example, changes in the company priorities was the most often cited reason for abandonment. In that same vein were issues with changing objectives and inaccurate definition of requirements. These types of failures are not topics for this blog since they do not immediately involve execution of the project.

Execution Problems

Lower on the list of those environment related reasons for failure were the ones more related to execution problems. These are of significant interest to a project management using an earned value consulting company such as Humphreys & Associates (H&A). These reasons related more to issues of poor project management that could have been corrected. In this area were reasons like “poor change management,” “inaccurate cost estimates,” “inaccurate time estimates,” and “inexperienced project management.”

The answers given in a survey situation depend very much on the mindset of the person responding. Is the reason really “inaccurate cost estimates” or should it have been “failure to execute to the estimate”? How many times have you seen a problem in execution “swept under the carpet” as being an inaccurate estimate or plan? One of these two answers points to the estimating system and process while the other points to project management. The estimates were generated; and, at some point, they were deemed to be sufficiently detailed to launch the project. If a scrubbed and blessed estimate is “inaccurate” that would still be a failure of project management. If the problem were really a failure to execute, then how easy would it be to blame the problem on poor estimates? This blog will discuss the cited failures as if they were execution failures.

Earned Value Management (EVM) Consultant Specialists

There are situations in life where the need for specialized advice is common and well accepted by us all. When your doctor is unsure of the medical issues, the doctor will send you to a specialist. The reason is obvious. The specialist has learned so much more about a specific problem and has so much experience diagnosing and treating the problem that it would be foolish not to secure the services of that specialist. In fact, it might be malpractice. A project management consultant can be thought of much like a medical specialist.

There are similar situations in business where the need for specialized knowledge is critical. Large companies tend to have in-house legal departments to cover the day-to-day legal issues and tasks that are central to their businesses. However, the need to go to outside counsel for large or unusual issues is accepted. Companies do not hesitate to engage the services of outside law firms to help them through troubled times. Project management consultants are like outside counsel.

What if there were a project management or earned value management situation you have never encountered before? A good example would be the times that H&A has been called in to help clients navigate the unhappy circumstances of needing to go over-target. Going through the over-target-baseline (OTB) or over-target-schedule (OTS) process is not a common experience. It is a tense time when careers can be on the line and the company reputation might also be at risk. It takes specialized knowledge to get it right. In some cases, it even takes the objective view of an outsider to help make the right decisions.

Specialized Knowledge

Another example of specialized knowledge being crucial is when the customer has deemed some issue on the project to be deficient. In some situations, a customer’s Corrective Action Request (CAR) can result in cost penalties and damaged reputations; possibly even worse consequences could result. Engaging the services of an EVM consultant with experience in identifying problems, building Corrective Action Plans (CAP)s, and leading or helping implementing the corrective actions is often a valuable and necessary action. Ask yourself how smart it would be to assume that those who were involved in causing the issue would be capable of creating a satisfactory solution.

These scenarios are aligned with the idea of project management consulting being something you only need in a crisis. There are other non-crisis needs for specialized support. Often H&A is engaged simply to help a client prepare a proposal. A proposal situation puts heavy demands on the company staffing levels and can require areas of specialized knowledge not available in the company. What if the company has never created a fully compliant Integrated Master Schedule (IMS) and they could use help the first time? What if there are not enough trained and experienced schedulers to work on the proposal? What if the company does not have a documented project management system?

Make or Break Opportunities

Projects can be huge and risky. They can be make-or-break opportunities to a company. Where so much can depend on good project management, smart companies recognize the need for an outside opinion and outside talent. Just like the internal legal department, the internal project management group sometimes needs to call on outside subject matter experts. While it might be obvious, let’s look at some reasons why this is true.

There are more ordinary everyday reasons to engage a project management consultant. Perhaps an organization just managed to win a new project bigger than any they have won before. In this case, they may not be ready to handle the project in terms of experience, systems, and even just talented headcount. A project management consulting company such as H&A can bring solutions to your earned value woes. It can also provide temporary training staff to get things going until the client is ready to take over.

Poor Communication

Let’s get back to the survey of reasons that projects failed. Are there issues on the list where project management consulting could have made a difference? Imagine an improved project management process and staff after a period of consulting to support creating or improving systems and training personnel?

The fifth most frequent reason for failure is “poor communication.” A good project management system with trained personnel is all about communication. Communication of plans, communication of progress, communication of issues, and communication of corrective actions are all actions required in a project management system. Quite often the problem of “poor change management,” cited as the sixth most common reason for failure, is reduced or eliminated after using the consulting services of a specialist?

What about the twelfth cited problem of “inadequate resource forecasting”? Would a well built and maintained resource-loaded Integrated Master Schedule (IMS) go a long way in providing forecasts of resource needs and the impacts of not having the resources? In fact, a proper IMS would help with several of the cited reasons for failure, such as inaccurate duration estimates. In fact, the application of a process, such as Schedule Risk Analysis (SRA), with the help of an experienced consultant can identify such issues in advance while there is still time to take action.

Earned Value Training

Disregarding the threat of failure as a motivator, the need for constant improvement should be enough reason to consider a project management consultant. We can all laugh at the time-worn clichés of “not-invented-here” or “we’ve never done it that way;” however, these are clichés for a reason. There is resistance to outside help and there is resistance to change. But outside help can be a great logjam breaker. An experienced and knowledgeable consultant can be your voice when you need someone who has, to use another cliché, “been there and done that.”

In fact, our consultants can laugh when they say they have “been there” and they have more than a T-shirt to prove it.

Project Management: Earned Value Consulting; Could You Use Some? Read Post »

Along the IMS Time-Now Line

, , , , , , , , , , , ,

Arrows moving to the right.Recently one of our consultants was instructing a session on the Integrated Master Schedule (IMS) with a group of project personnel from one of our larger clients. The group was a mixture of beginners with no real experience in schedules and some much more experienced practitioners; some with more than 10 years of experience. The mixture made it somewhat difficult, but it also made for some interesting discussions that might have been missed in a more homogenous group. One of those things was the usefulness or importance of the “time-now” line.

When the group was asked about the importance of the time-now line and what information could be easily gained from a look at the line, there was silence. The beginners did not have a clue but also none of the experienced people had any response. What should have been a short discussion with just one “slide” as a visual, turned out to be a longer and more informative session on this topic.

The time-now line has different names in different software tools but it refers to the data date, or status date, of the schedule. That also would be the first day of the remainder of the schedule. When a scheduler sorts tasks by date, the time-now line runs down the screen and forms a highly useful visible reference.

In the small example below [see Figure 1], you can see the time-now line and visually assess the situation. Time-now is shown by a vertical line at the beginning of September, so all remaining effort has been scheduled to after that date. In other words, no work can be forecasted in the past. A walk down the line shows Task 1 has both started and completed. Task 2 started but has not completed. In fact, the remaining work in Task 2 has been pushed out by the time-now line. The start of Tasks 5 and 9 are also being pushed out by the time-now line. In most real project schedules, filters and other techniques may be needed to isolate information like this; but in our small example, we can simply “eyeball” the time-now line and see valuable information. Task 9 starts the critical path shown in red tasks.

 

The project start date was August 1. The status date is September 1. Tasks 2, 5, and 9 show gaps from the predecessor to their starts. in the case of Task 2 the cap is to the start of the remaining work. This gap is caused by the time-now being set to September 1 with all remaining work starting after that. The critical path is being pushed by time now.Figure 1

 

A slightly different setup for that same small example [see Figure 2] shows something interesting. The time-now line is still at the beginning of September. But now there is a gap between time-now and work on the critical path. This is an unusual situation and should be investigated for the root cause. It is possible this is an accurate portrayal of the situation, but regardless of the cause, it must be verified and explained.

 

Time now is still at September 1. There is a gap on the critical path at the start of Task 9 which, in this case, is caused by a Start-No-Earlier-Than constraint.Figure 2

 

In yet one more variation [see Figure 3], we see that a broken link results in Task 8 ending up on the time-now line. A task without a predecessor will be rescheduled to start at the earliest possible time (if the task is set to be “As Soon As Possible”). And the earliest possible time is the time-now line; the beginning of September. Just as broken things fall to the floor in real life, “broken things” fall to the time-now line in a schedule. Un-started work can land there. Un-finished work can land there. And un-linked work can land there.

It is further possible to see that Task 2 has had an increase in the remaining duration that has driven it onto the critical path. Task 2 at this moment is the most important task on the entire project. A slip to Task 2 will drive out the end date for the entire project. One question that needs answering is what is holding up Task 2?

If the display had been sorted by increasing total float/slack and the usual cascade by date, then the critical path would be starting at the upper left-hand corner; like the critical path in this example. The action on the project is almost always on the time-now line and the most important action, when sorted as described, will be at the upper left-hand corner.

 

Task 2 is now driving the critical path. Task 8 has fallen back to the time now line. The constraint on Task 9 has been removed.Figure 3

 

So, a walk down the time-now line can help us see the critical path action, find broken parts of the schedule, and locate unusual circumstances that need our attention. Our recommendation is to look at the time-now line any time there is data being changed in the IMS. This will help you catch issues early and keep the schedule cleaner.

Along the IMS Time-Now Line Read Post »

Management Reserve; Comparing Earned Value Management (EVM) and Financial Management Views of “Reserves”

, , , , , , , , , ,
Management Reserve & Earned Value ManagementPerhaps you have witnessed the collision of earned value management’s views on “management reserve” with the Chief Financial Officer (CFO) and the finance department’s views on “balance sheet reserves.” Most companies tend to organize EVM, the function, reporting to either the programs’ organization or to the finance organization. Either will work but either can fail if the two organizations do not understand the interest of the other.

In this article we will outline three areas. The first will be EVM and Management Reserve (MR). The second will be finance and balance sheet “contingencies, loss provisions, or reserves.” The third will compare the two views and identify where they are similar and where they differ.

We will use two terms for both EVM and Financial Management; “in play” and “on the sideline.” “In play” for EVM means that it is in your Performance Measurement Baseline (PMB) and Budget at Completion (BAC). “On the sideline” for EVM means “not in scope” therefore in MR. “In play” for financial management means recorded on the balance sheet (e.g.: current liability; an accrued liability). “On the sideline” for financial management means not recorded on the balance sheet, because it is more likely than not that a liability has been incurred.   If material, however, it will likely be disclosed in the notes to the financial statements, even if it is not recorded on the balance sheet.

 

Earned Value Management and Management Reserve

A program manager and his or her team must deal with – mitigate – risk or be consumed by those risks as they become issues. There are two types of risks, known and unknown. The known risks are entered into a risk register, and their likelihood and consequence are determined. Mitigation for those known risks is done at the activity level in a program’s Integrated Master Schedule (IMS) (Planning and Scheduling Excellence Guide — PASEG page 141, ¶ 10.3.1). Mitigation of known risks is part of the PMB (in the BAC) and is therefore “in play.”

The second type of risk – unknown or unknowable risks – are covered by management reserve if within the Scope of Work (SOW) of the existing contract. If contractor and customer conclude that the realized risk is outside the existing contract, then an Engineering Change Proposal (ECP) would likely be created by the contractor; and a contract modification would be issued by the authorized customer contracting officer if they agreed.   The program manager should ask this question of his team: what work is “at risk” and what work is not “at risk?” Does labor or material present more risk? Management reserve “is an amount of the overall contract budget held for management control purposes and for unplanned events” (Integrated Program Management Report–IPMR DI-MGMT-81861 page 9, ¶ 3.2.4.6). Management reserve is “on the sidelines.” MR has no scope. MR is not earmarked. MR stands in waiting.

 

Earned Value Management Reserve (MR) Compared To Financial Management “Contingency”

Because the audience reading this blog is most likely from the EVM community, I’ll offer a Financial Management example of a company that faces many risks and must manage those risks or be consumed by them. Altria Group, Inc. and Subsidiaries (stock symbol: MO) are in the tobacco, e-Vapor and wine business. Altria’s history clearly shows that the company measures and successfully mitigates the risks they face. Altria faces a blizzard of litigation each year and must protect its shareholders from that risk. So how does Altria manage known risks (mostly from litigation) and how does Altria handle unknown risks?

Altria is a publicly traded company and its annual report (10K) is available on-line to the public. This data is from their 2014 annual report.

I am an MBA, not a CPA, so I’ll stick to Altria’s 2014 balance sheet. For those not familiar with financial statements, a balance sheet has on its left hand side all of a company’s assets – what the company owns and uses in its business (current assets = cash, accounts receivable, inventory; long term assets = property, plant and equipment). The right hand side of a company’s balance sheet shows current and non-current liabilities and shareholders’ equity. The top right hand side of the balance sheet includes current and non-current liabilities (accounts payable, customer advances, current and long-term debt, and accrued liabilities like income taxes, accrued payroll and employee benefits, accrued pension benefits and accrued litigation settlement costs) and the bottom of the right hand side of the balance sheet includes shareholders’ equity consisting of common and preferred stock, paid in capital and retained earnings.

Altria’s 2014 annual report shows under current liabilities; accrued liabilities; settlement charges (for pending litigation Contingency note # 18) a value of $3.5 billion dollars. The 2013 amount was $3.391 billion dollars.

So Altria has “in play” $3.5B for litigation for 2014. In financial terms, Altria has recorded $3.5 billion in expense related to the litigation, probably over several years as it became more likely than not that a liability had been incurred and was reasonably estimable. In EVM terms Altria has $3.5B in their baseline, or earmarked, or in scope for litigation (court cases).

What happens if Altria ultimately has more than $3.5B in litigation settlement costs? What does Altria have waiting on the “sidelines” to cover the unknown risks? Essentially Altria has on its balance sheet waiting “on the sidelines” $3.321 billion in cash and the ability to borrow additional funds or perhaps to sell additional shares of stock to fund the settlement costs. In EVM terms Altria has $3.5B in its baseline (on its balance sheet) to manage the risks associated with litigation. Altria’s market capitalization at the market close on May 17, 2015 was $52.82 billion and its 2014 net revenues were $24.522 billion. It is reasonable to understand that Altria has more than enough MR.

 

Differences Between EVM MR and Financial Management Balance Sheet Reserves

In EVM, MR is only released to cover unplanned or unknown events that are in scope to the contract but out-of-scope to any control account. A cost under-run is never reversed to MR, and a cost over-run is never erased with the release of MR into scope.

In industry in general, and Altria in particular, if the “in play” current liability for settlement charges of $3.5B are not needed (an under-run), then Altria will reverse a portion of the existing accrued liability into income, thereby improving profitability. If Altria’s balance sheet reserve of $3.5B is insufficient, then Altria’s future profits will be reduced as an additional provision will be expensed to increase the existing reserve (an over-run).

[Humphreys & Associates wishes to thank Robert “Too Tall” Kenney for authoring this article.]

Management Reserve; Comparing Earned Value Management (EVM) and Financial Management Views of “Reserves” Read Post »

Variance Analysis, Corrective Action Plans, Root Cause Analysis

, , , , , , , , ,

Variance Analysis “provides EVMS contract management with early insight into the extent of problems and allows corrective actions to be implemented in time to affect the future course of the program.” [NDIA ANSI EIA 748 Intent Guide] Department of Defense Data Item Descriptions: DI-MGMT-81861, Integrated Program Management Report (IPMR) paragraphs 3.6.10xx; DI-MGMT-81466A, Contract Performance Report, paragraph 2.6.3; and DI-MGMT-81650, Integrated Master Schedule (IMS) — paragraph 2.5 — all require analysis for significant variances including cause, impact and corrective action plans.  By comparing the performance against the plan, it is possible to make mid-course corrections which assist completion of the project on time and within the approved budget. The Variance Analysis Report (VAR) is a “living, working document to communicate cause, impact and corrective action”. [See: Chapter 35 Variance Analysis and Corrective Action, Project Management Using Earned Value, Humphreys & Associates, page 707.] Well-written variance analyses should answer the basic questions of why, what and how.

Cause is also known as root cause, nature of the problem, problem statement, issue, or problem definition. Root cause is the fundamental reason for the problem. Root cause is required in order to take preventative corrective action. The explanation of the variance is broken down into each of its components: discuss schedule variances separately from cost variances; discuss labor separately from non-labor; discuss which portion of the variance was caused by efficiency (hours) and which portion was because of dollars (rates) or if the variance was driven by material discuss how much was because of price and how much was because of usage. For more information refer to Humphreys & Associates blog Variance Analysis-Getting Specific.

Once the root cause of the problem has been identified and described, the impact(s) on the project should be addressed. Identify impacts to customers, technical capability, cost, schedule (including when the schedule variance will become zero), other control accounts, program milestones, subcontractors, and the Estimate at Completion, including rationale.

A corrective action (CA) plan should be developed that describes the specific actions being taken, or to be taken, which includes the individual or organization responsible for the action(s). The corrective actions should be directly derived from root cause analysis and related to each identified root cause.   Results from previous corrective action plans should be included.  Occasionally, a successful plan will include interim modifications or fixes in the short term, with long term changes identified as well. When no corrective action for an overrun is possible, an explanation and EAC rationale should be included.  A corrective action log should be used that tracks the actions taken and the status of the corrective plan for each variance analysis cycle.  As was stated in the Humphreys & Associates article:  Corrective Action Response: Planning and Closure – Part 2 of 2  “It is critical that verification methods, objective measures, metrics, artifacts, and evidential products are identified that will verify that the corrective actions are effective.”  Corrective action plans based on clearly a defined root cause facilitates time management action and avoids the occurrence of repetitive problems.

Variance Analysis, Corrective Action Plans, Root Cause Analysis Read Post »

Scroll to Top