Integrated Master Schedule (IMS)

Including Level of Effort (LOE) in the Integrated Master Schedule (IMS)

, , ,

A recent H&A blog titled “Level of Effort (LOE) Best Practice Tips” discussed different approaches for handling LOE to avoid generating false variances. That discussion did not elaborate on including the LOE tasks in the integrated master schedule (IMS). This blog is a follow on to that earlier discussion with a focus on options for including LOE in the IMS along with notes on best practices, tips, and customer expectations.

In the general sense of an earned value management system (EVMS), the LOE scope of work is contained in summary level planning packages (SLPPs) or control accounts as subordinate planning packages or work packages. The budget values for those elements will most likely come from a resource loaded IMS or a resource loading mechanism aligned with the IMS. Not all organizations resource load the IMS activities but instead extract time buckets from the IMS for resource loading using other mechanisms. Resource loading the IMS activities is the recommended practice because it assures cost/schedule integration, but it can be difficult.

LOE work might not appear in the IMS since it is considered optional by some customers such as the Department of Defense (DoD). The Department of Energy (DOE) requires LOE tasks to be included so you can expect it to be in the IMS when DOE is the customer.

Before we talk about LOE in the IMS we must think about the type of work the LOE tasks represent. LOE might be a general task such as “Control Account Management” that is not directly related to other work except perhaps in the time frame in which they happen. But some LOE tasks such as support tasks are related to other discrete work. Modeling the LOE in the IMS starts by understanding what type of effort is involved and can help to determine the approach for linking activities. 

LOE Best Practice Tips Related to the IMS

The Level of Effort (LOE) Best Practice Tips blog included these points related to the IMS:

  • “When LOE activities are included in the schedule, they should not drive the date calculations of discrete activities in the integrated master schedule (IMS). They should also not appear on the critical path.”
  • “LOE must be segregated from discrete work effort. In practice, this means a work package can only be assigned a single earned value method.”
  • “Consider shorter durations for the LOE when that LOE is supporting discrete effort. Should the first occurrence of the LOE trigger a data anomaly test metric, it can be proactively handled along with any future replanning. The remaining LOE would already be in one or more separate work packages so there won’t be any criticism for changing open work packages.”

Government Agency and Industry Guidance on LOE on the IMS

Is there any guidance that can help clarify how best to handle LOE tasks in the IMS? Let’s take a look at three of the guidance documents that may be useful for your environment.

  1. The Integrated Program Management Data and Analysis Report (IPMDAR) Data Item Description (DID), DI-MGMT-81861C (August 2021). This DID is typically placed on contracts with the DoD or NASA that exceed the contract value threshold for EVM reporting or EVMS compliance. Relevant mentions of the data requirements for the IMS in the DID are as follows.

“2.4.1.1 Content. The Schedule consists of horizontally and vertically integrated discrete tasks/activities, consistent with all authorized work, and relationships necessary for successful contract completion.”

Note: This is where the option to exclude LOE from the IMS appears since this requires only discrete tasks/activities. The following sections provide additional guidance when LOE is included in the IMS.

“2.4.2.7 Level of Effort (LOE) Identification. If tasks/activities within an LOE work package are included in the Schedule, clearly identify them.”

“2.4.2.9 Earned Value Technique (EVT). Identify the EVT (e.g., apportioned effort, level of effort, milestone).”

  1. National Defense Industrial Association (NDIA) Integrated Program Management Division (IPMD) Planning and Scheduling Excellence Guide (PASEG) (Version 5.0). The PASEG is a widely recognized industry guide on scheduling best practices in government contracting environments. Section 5.8, Level of Effort (LOE) provides a discussion on the topic including things to promote and things to avoid. Excerpts from the PAGEG follow.

“There are pros and cons around including or excluding LOE tasks in the IMS. Including LOE tasks in the IMS allows for a more inclusive total program look at resource distribution, which aids in the maintenance and analysis of program resource distribution. However, if modeled incorrectly, including LOE tasking in the IMS can cause inaccurate total float and critical path calculations.”

“Tasks planned as LOE in the IMS should be easily and accurately identifiable. This includes populating the appropriate Earned Value Technique field (as applicable) and possibly even identifying the task as LOE in the task description.”

“Consider adding an LOE Completion Milestone to tie all LOE tasking to the end of the program.”

“LOE tasks should not be networked so that they impact discrete tasks. Incorrect logic application on LOE can lead to invalid impacts to the program critical path.”

“Level of Effort tasks should have no discrete successors and should therefore never appear on critical/driving paths.”

  1. DOE Guide 413.3-24 Planning and Scheduling (April 2022). This document provides guidance for acceptable practices in a DOE contractual environment. The discussion on LOE can be found in Section 7 Planning and Scheduling Special Topics, 7.2 Level of Effort, and 7.3 Inclusion of Level of Effort in the Integrated Master Schedule. Excerpts and image from the Guide follow. 

“Overview: Activity-based methods either cannot, or impracticably can measure the performance of LOE WPs and activities. Include all activities, both discrete and LOE, in the IMS.”

“LOE is planned in the IMS so that it does not impact discrete work. Figure 6 shows the recommended linkages in the IMS for planning level of effort.”

Interpreting this DOE Guide diagram for the recommended modeling of LOE in the IMS, notice the inclusion of a “LOE Complete” milestone following the Critical Decision (CD) 4 milestone with no constraint. CD4 in this diagram represents the end of contract effort. The purpose of this LOE-complete milestone, with no constraint, is to provide a successor for all LOE tasks where one is needed. That will prevent generating issues where tasks have no successors.

This recommended modeling is done so that the LOE tasks are not linked to the end of the contract work and thus will not push it. The LOE tasks will also not appear on the critical path since they are not in the path that established the end date.

Also note that the LOE tasks in green are linked as successors to discrete work which is a logic linking approach intended to keep the LOE work aligned with the discrete work but off the critical path. Study the logic and you see that a movement to the right of a discrete task will drag along its related LOE task.

DOE requires the use of Primavera schedule tools so the relationships shown here can be accomplished in that tool. That may not be true of all tools. Know how your tools work before you generate any guidance.

Additional Relevant Guidance Search

H&A earned value consultants recently conducted a survey of the various government and non-government documents regarding the IMS and collected relevant guidance related to LOE among other things. The table below lists the results from a search for “LOE” wording. Note: this is a representative sample of typical government agency and industry IMS references. You should verify current references before you generate your own internal IMS guidance.

Source DocumentGuidance for Capturing all Activities, LOE in IMS
DCMA EVMS Compliance Metrics (DECM) Checks (version 6.0)
  • 06A210a: Do LOE tasks/activities have discrete successors? (0% threshold)
  • 12A101a: Are the contractor’s Level of Effort (LOE) WPs supportive in nature and/or do not produce technical content leading to an end item or product? (≤ 15% threshold)
  • 12A301a: Does the time-phasing of LOE WP budgets properly reflect when the work will be accomplished? (≤ 10% threshold)
IPMDAR DID DI-MGMT 81816CIf tasks/activities within an LOE work package are included in the Schedule, clearly identify them.
DOE Guide 413.3-24 Planning and Scheduling, Appendix A Schedule Assessment PrinciplesPrinciple 20. No LOE on critical path.
GAO Schedule Assessment Guide: Best Practices for Project Schedules (December 2015)Selected excerpts:
  • LOE activities should be clearly marked in the schedule and should never appear on a critical path.
  • LOE activities … derive their durations from other discrete work.
  • Best Practices for confirming the critical path is valid: Does not include LOE activities, summary activities, or other unusually long activities, except for future planning packages.
NDIA IPMD PASEG (version 5.0) (as noted above)
  • Tasks planned as LOE in the IMS should be easily and accurately identifiable.
  • LOE tasks should not be networked so that they impact discrete tasks.
  • Level of effort tasks should have no discrete successors and should therefore never appear on critical/driving paths.
PMI Practice Standard for Scheduling (Second Edition)Since an LOE activity is not itself a work item directly associated with accomplishing the final project product, service, or results, but rather one that supports such work, its duration is based on the duration of the discrete work activities that it is supporting.

Conclusion

Based on the various sources of guidance, it is possible to structure the IMS to include LOE in a way that provides cost/schedule integration and keeps all work correctly aligned yet does not cause issues with the critical path and the driving paths. From this guidance, it should be a straightforward effort to generate your own internal scheduling procedure defining how to handle LOE in the IMS if you choose to include it or if you are required to include it.

Need help producing a clear and concise scheduling procedure or tool specific work instructions? H&A earned value consultants and scheduling subject matter experts have worked with numerous clients to create easy to follow guides that help to ensure schedulers are following your company’s best practices using the scheduling tools of choice. Call us today at (714) 685-1730 to get started. 

Including Level of Effort (LOE) in the Integrated Master Schedule (IMS) Read Post »

Improving Integrated Master Schedule (IMS) Task Duration Estimates

, , , ,
Improving Integrated Master Schedule (IMS) Task Duration Estimates

One of the top reasons projects fail is because of poor task duration estimating for an integrated master schedule (IMS). Without accurate and consistent estimates, project outcomes can become unpredictable, leading to missed deadlines, budget overruns, and overall project failure. A realistic schedule is required to place the necessary resources in the correct timeframe to adequately budget the work as well as to produce credible estimates to complete and to forecast completion dates. While missed deadlines and budget overruns are detrimental for any project, there can be additional business ramifications when producing schedules in an Earned Value Management System (EVMS) contractual environment.

While there are effective methods available to improve task duration estimates, they are often underutilized. A common reason for this oversight is the lack of time allocated to developing the project schedule and determining task durations.

During the proposal phase, initial durations are typically estimated at a more summary level than the detailed execution phase. The proposed work is often defined at a level one to two steps higher than where the actual tasks will be performed. After project initiation, the team’s initial effort is to break the work down into more manageable tasks. This decomposition is crucial for achieving more accurate estimates. It’s no surprise, then, that the initial breakdown efforts often result in duration estimates that don’t align with the proposed durations.

Parkinson’s Law tells us that work expands to fill the time available. If task durations are excessively long, costs will inevitably rise. To counter this, it’s important to require estimators to provide both the estimated effort and the duration needed to accomplish the task. This approach helps to gain a better understanding of the scope of the task and to avoid unrealistic estimates. If you see a task that requires 10,000 hours with a duration of 2 weeks, then you immediately would suspect something is wrong with the estimates.

Techniques for Developing More Accurate Task Duration Estimates

What are your options? H&A earned value consultants and senior master schedulers often employ the following techniques to help a client produce a more realistic IMS.

  1. Establish a Probability Goal. It is essential to set clear expectations for the estimating team. Without guidance, teams may default to estimates with a 50/50 probability of success, which is a recipe for failure. Instead, directing the team to aim for estimates within a 75% to 80% probability range can lead to better outcomes.
  2. Break Down Tasks. Decompose tasks into smaller, more manageable components. The further out the task’s horizon, the greater the variability in estimates. For example, asking someone to estimate the drive time from Washington, DC, to Boston without specifying the vehicle, route, limitations, or conditions introduces unnecessary uncertainty.
  3. Use Professional Judgment. Engage someone with experience in the specific type of work required for the task. A seasoned expert will provide more accurate duration estimates based on their knowledge and experience. Often, we ask the potential task manager to do the estimate, but that person may not be the one with the most related experience or knowledge about the work.
  4. Leverage Historical Data. If the task or a similar one has been done before, use that historical data to inform the estimate. This approach provides a realistic benchmark for future estimates.
  5. Use generative AI. If you have access to an AI capability along with access to historical data, that could be an option to leverage the source data using specific prompts to glean relevant information. As with all AI tools, always verify the generated results to ensure it is a useful basis to substantiate the estimate.
  6. Apply Parametric Estimating. When possible, use parametric analysis to estimate the durations. For example, if it took a specific number of days to clean up a certain amount of toxic waste under similar conditions, this data can be used to estimate the duration of a new but comparable task.
  7. Engage Multiple Estimators. Gathering estimates from more than one person helps to reduce individual biases and provides a more rounded estimate.
  8. Apply the Delphi Method. This technique involves three knowledgeable individuals providing estimates or three-point estimates. The initial estimates are analyzed, and the results are shared with the estimators without attributing specific values to any individual. After discussing the findings, the estimators revise their estimates based on the collective insights, leading to a more refined and accurate duration estimate.
  9. Use Three-Point Estimates. Ask estimators to provide best-case (BC), most likely (ML), and worst-case (WC) durations, along with their reasoning. Applying a formula like the Program Evaluation and Review Technique (PERT) duration formula (1BC+4ML+1WC)/6 can yield an adjusted and realistic estimate. You can vary the best and worst case estimate for risk if you have information on that.

    To see how this simple approach can work, walk through this exercise. Ask yourself how long it takes you to drive to work most of the time. Let’s say the answer is 45 minutes. Then ask yourself how long it would take on a Sunday morning in the summer when the roads were dry (the best case). Let’s say your answer is 25 minutes. Then ask yourself how long it would take on a Monday morning in the winter during a moderate snow event (the worst case). You tell yourself 90 minutes. Now you have enough information to calculate the PERT duration.

    Best Case = 25 minutes
    Most likely = 45 minutes
    Worst Case = 90 minutes
    PERT Duration = (25 + 180 + 90)/6 = 49 minutes

    Finally, let’s say you ask yourself how likely it is that you end up on the high side instead of the low side. If your answer is it is much more likely to encounter conditions that slow you down, you would modify the formula to use one and a half times the worst case (25 + 180 + 135)/6 = 57 minutes. That longer duration shows the impact of your impromptu risk analysis and provides a duration that has a much higher probability of being achievable.

    Now think about the same scenario but conducted by you interviewing three people who drive the same route to work. That would approximate the Delphi method.
  1. All or something less. It may not be necessary to analyze every task to the degree suggested. Even if you could do the analysis along the top several critical paths that would be an improvement. If you were to apply numerical factors to the tasks in related portions of the project that would be impactful. For example, all mechanical design tasks or all software development tasks.

What is the best approach?

You will need to analyze your project and determine which approach or approaches would yield useful information at a reasonable cost. If you apply your own thinking on how to improve your duration estimates, you will undoubtedly find a method most suitable for your situation. Depending on a project’s complexity and risk factors, you may also find it useful to take a more formal approach. Conducting a schedule risk assessment (SRA), a probabilistic assessment of a project’s outcome, can help you gain a better understanding of where the duration risk exists in the schedule.

H&A earned value consultants and scheduling subject matter experts often assist clients to establish basic guidance to help scheduling personnel to get into the habit of adequately defining tasks and using techniques to improve duration estimates. This is critical to be able to produce well-constructed and executable schedules to improve the likelihood of achieving project technical, schedule, and cost objectives.

H&A offers a range of project scheduling training workshops that can help schedulers to implement industry best practices. These workshops also cover how to take the next step to implement advanced scheduling techniques such as schedule risk assessments to ensure the schedule is realistic and achievable. H&A earned value consultants and master schedulers often provide one-on-one mentoring using the scheduling tool of choice to help scheduling personnel work through the learning curve of using advanced network scheduling techniques to produce executable schedules.  

Call us today at (714) 685-1730 to get started.

Improving Integrated Master Schedule (IMS) Task Duration Estimates Read Post »

EVM Consulting – Modeling & Simulation

, , , , , , , , ,

Fighter Jet Air Plain Flying in Front of Moon

Forewarned is Forearmed

Forewarned is forearmed. John Farmer, of New Hampshire, said that in a letter in 1685. But that advice is most likely biblical and very much older. No matter the source of the thought, we should take it as divine guidance if we are project managers. Maybe we should have it cut into a stone tablet, so we can share it with our team members.

Most of our work as project managers is spent in the “controlling” phase which is made up of the three steps “measure, analyze, act.” Our EVMS and IMS exist to be able to support this management function. The measuring part is done very well in our EVMS and our IMS; we know where we are and how we got there. The analyzing is equally well handled in the IMS and EVMS. Only the management task of acting is not well supported. Generally, we lack decision making support and tools.

EVM Consulting - Measure, Analyze, Act

Deterministic Path

No matter how well constructed and how healthy our IMS is, it has a deterministic path forward. The logic links between the activities are there because we expect them to be fulfilled. Indeed, if activity “B” is a finish-to-start successor to activity “A” we fully expect that at some point activity “A” will finish and will provide its output to activity “B”. That is a single path forward and it is a deterministic path. It is also a somewhat simplistic model.

EVM Consulting - Deterministic Relationships in EVMS

Multiple Outcomes

Our management system asks us to perform root cause analysis followed by corrective action. But what if there is more than one corrective action to be taken. And worse; what if the corrective actions can have multiple outcomes with each enjoying its own probability. That means multiple choices and multiple outcomes. How would we show that in our plan? How would we analyze the multiple possible futures that such a situation presents?

Happily, there are ways to model a future without a set path. And once we have the future model, there are also ways to simulate the outcomes to give the probabilities we need to decide which actions to take. We are talking about probabilistic branching, and we are saying that we can build a probabilistic map of the future to use in making decisions; especially making decisions on corrective actions.

Take a simple example of running a test on the project. The expectation is that eventually we will pass the test. We will keep trying until we do. In the IMS deterministic model the test portion of the IMS might look like this:

EVM Consulting - Run the Test then Use the Product

Simulation

We can simulate this situation with different expected durations for the test. That is helpful information, but it does not explain or even capture what is going on in those different durations. It looks like we are just taking longer to do the testing but is that really what is happening? What is going on here? We certainly don’t show that.

In the real world, this simple model might have three potential outcomes. There might be three paths we can take to get to the point where we use the product. Each path has a time and money cost. We might run the test and find that we passed. Or we might have to stop the test for issues on the item or the test setup. We might even fail the test and must correct something about the product to improve our chances of passing a rerun. Eventually we will get to a usable product. But what do we put in our estimate and our plan? What do we tell the resources we need? What do we tell the boss? The customer?

EVM Consulting - Real World Testing

Full Future Model

We now have a much better understanding of the future and can explain the situation. We also can simulate the situation to find out the most likely time and cost outcomes, so we can explain the future without any histrionics or arm waving.
If the issue is important enough we can build out the full future model and simulate it.

EVM Consulting - Full Future Model and Simulation

No matter how far we pursue the model of the future, having a valid model and being able to stand on solid ground are very valuable to us as project managers.

This is not to say that we should model out complex situations as a routine in the IMS. That would be impossible, or at least prohibitively costly. We are saying that when situations arise, we need to be able to use the IMS to help us make decisions.

This type of probabilistic modeling of the future is particularly useful in defining major decision points in our plan. When we reach a decision point the IMS may have multiple branches as successors but that implies we take every branch and that is not valid. Modeling each branch and its probabilities is valid. In the example below, where the milestone represents a decision point, we have shown three possible paths to take. If each were modeled out into the future with time and cost data, we should have the information we need to choose the path we wish to pursue. Without processes and tools like this, we would be flying blind.

Future Blog Posts

This discussion will be continued in future blogs to develop a better foundational understanding of the process and power of probabilistic modeling in our EVMS.

EVM Consulting - Decision Point

Good information sets the stage for good decisions. The IMS and the EVMS have sufficient information to help us model the pathways ahead of our critical decisions. We just need to learn to take advantage of what we have available to us.

Find out how an experienced Humphreys & Associates EVM Consultant can help you create a full future model and simulation of your most vital EVMS Systems. Contact Humphreys & Associates at (714) 685-1730 or email us.

EVM Consulting – Modeling & Simulation Read Post »

Project Management: Earned Value Consulting; Could You Use Some?

, , , , ,

Failed Projects

A recent article discussed the results of a survey on the reasons that projects failed. The definition of failure was that the project was abandoned. Abandonment does not occur frequently in the world of government projects; especially defense projects where there should be strong “must have” needs driving the project. These projects tend to persist until completed even though the outcomes are not satisfactory. But there is a lot to learn from the list of reasons for failure.

Of the sixteen reasons listed, the top four had to do with changes to the environment that had given rise to the project. For example, changes in the company priorities was the most often cited reason for abandonment. In that same vein were issues with changing objectives and inaccurate definition of requirements. These types of failures are not topics for this blog since they do not immediately involve execution of the project.

Execution Problems

Lower on the list of those environment related reasons for failure were the ones more related to execution problems. These are of significant interest to a project management using an earned value consulting company such as Humphreys & Associates (H&A). These reasons related more to issues of poor project management that could have been corrected. In this area were reasons like “poor change management,” “inaccurate cost estimates,” “inaccurate time estimates,” and “inexperienced project management.”

The answers given in a survey situation depend very much on the mindset of the person responding. Is the reason really “inaccurate cost estimates” or should it have been “failure to execute to the estimate”? How many times have you seen a problem in execution “swept under the carpet” as being an inaccurate estimate or plan? One of these two answers points to the estimating system and process while the other points to project management. The estimates were generated; and, at some point, they were deemed to be sufficiently detailed to launch the project. If a scrubbed and blessed estimate is “inaccurate” that would still be a failure of project management. If the problem were really a failure to execute, then how easy would it be to blame the problem on poor estimates? This blog will discuss the cited failures as if they were execution failures.

Earned Value Management (EVM) Consultant Specialists

There are situations in life where the need for specialized advice is common and well accepted by us all. When your doctor is unsure of the medical issues, the doctor will send you to a specialist. The reason is obvious. The specialist has learned so much more about a specific problem and has so much experience diagnosing and treating the problem that it would be foolish not to secure the services of that specialist. In fact, it might be malpractice. A project management consultant can be thought of much like a medical specialist.

There are similar situations in business where the need for specialized knowledge is critical. Large companies tend to have in-house legal departments to cover the day-to-day legal issues and tasks that are central to their businesses. However, the need to go to outside counsel for large or unusual issues is accepted. Companies do not hesitate to engage the services of outside law firms to help them through troubled times. Project management consultants are like outside counsel.

What if there were a project management or earned value management situation you have never encountered before? A good example would be the times that H&A has been called in to help clients navigate the unhappy circumstances of needing to go over-target. Going through the over-target-baseline (OTB) or over-target-schedule (OTS) process is not a common experience. It is a tense time when careers can be on the line and the company reputation might also be at risk. It takes specialized knowledge to get it right. In some cases, it even takes the objective view of an outsider to help make the right decisions.

Specialized Knowledge

Another example of specialized knowledge being crucial is when the customer has deemed some issue on the project to be deficient. In some situations, a customer’s Corrective Action Request (CAR) can result in cost penalties and damaged reputations; possibly even worse consequences could result. Engaging the services of an EVM consultant with experience in identifying problems, building Corrective Action Plans (CAP)s, and leading or helping implementing the corrective actions is often a valuable and necessary action. Ask yourself how smart it would be to assume that those who were involved in causing the issue would be capable of creating a satisfactory solution.

These scenarios are aligned with the idea of project management consulting being something you only need in a crisis. There are other non-crisis needs for specialized support. Often H&A is engaged simply to help a client prepare a proposal. A proposal situation puts heavy demands on the company staffing levels and can require areas of specialized knowledge not available in the company. What if the company has never created a fully compliant Integrated Master Schedule (IMS) and they could use help the first time? What if there are not enough trained and experienced schedulers to work on the proposal? What if the company does not have a documented project management system?

Make or Break Opportunities

Projects can be huge and risky. They can be make-or-break opportunities to a company. Where so much can depend on good project management, smart companies recognize the need for an outside opinion and outside talent. Just like the internal legal department, the internal project management group sometimes needs to call on outside subject matter experts. While it might be obvious, let’s look at some reasons why this is true.

There are more ordinary everyday reasons to engage a project management consultant. Perhaps an organization just managed to win a new project bigger than any they have won before. In this case, they may not be ready to handle the project in terms of experience, systems, and even just talented headcount. A project management consulting company such as H&A can bring solutions to your earned value woes. It can also provide temporary training staff to get things going until the client is ready to take over.

Poor Communication

Let’s get back to the survey of reasons that projects failed. Are there issues on the list where project management consulting could have made a difference? Imagine an improved project management process and staff after a period of consulting to support creating or improving systems and training personnel?

The fifth most frequent reason for failure is “poor communication.” A good project management system with trained personnel is all about communication. Communication of plans, communication of progress, communication of issues, and communication of corrective actions are all actions required in a project management system. Quite often the problem of “poor change management,” cited as the sixth most common reason for failure, is reduced or eliminated after using the consulting services of a specialist?

What about the twelfth cited problem of “inadequate resource forecasting”? Would a well built and maintained resource-loaded Integrated Master Schedule (IMS) go a long way in providing forecasts of resource needs and the impacts of not having the resources? In fact, a proper IMS would help with several of the cited reasons for failure, such as inaccurate duration estimates. In fact, the application of a process, such as Schedule Risk Analysis (SRA), with the help of an experienced consultant can identify such issues in advance while there is still time to take action.

Earned Value Training

Disregarding the threat of failure as a motivator, the need for constant improvement should be enough reason to consider a project management consultant. We can all laugh at the time-worn clichés of “not-invented-here” or “we’ve never done it that way;” however, these are clichés for a reason. There is resistance to outside help and there is resistance to change. But outside help can be a great logjam breaker. An experienced and knowledgeable consultant can be your voice when you need someone who has, to use another cliché, “been there and done that.”

In fact, our consultants can laugh when they say they have “been there” and they have more than a T-shirt to prove it.

Project Management: Earned Value Consulting; Could You Use Some? Read Post »

Along the IMS Time-Now Line

, , , , , , , , , , , ,

Arrows moving to the right.Recently one of our consultants was instructing a session on the Integrated Master Schedule (IMS) with a group of project personnel from one of our larger clients. The group was a mixture of beginners with no real experience in schedules and some much more experienced practitioners; some with more than 10 years of experience. The mixture made it somewhat difficult, but it also made for some interesting discussions that might have been missed in a more homogenous group. One of those things was the usefulness or importance of the “time-now” line.

When the group was asked about the importance of the time-now line and what information could be easily gained from a look at the line, there was silence. The beginners did not have a clue but also none of the experienced people had any response. What should have been a short discussion with just one “slide” as a visual, turned out to be a longer and more informative session on this topic.

The time-now line has different names in different software tools but it refers to the data date, or status date, of the schedule. That also would be the first day of the remainder of the schedule. When a scheduler sorts tasks by date, the time-now line runs down the screen and forms a highly useful visible reference.

In the small example below [see Figure 1], you can see the time-now line and visually assess the situation. Time-now is shown by a vertical line at the beginning of September, so all remaining effort has been scheduled to after that date. In other words, no work can be forecasted in the past. A walk down the line shows Task 1 has both started and completed. Task 2 started but has not completed. In fact, the remaining work in Task 2 has been pushed out by the time-now line. The start of Tasks 5 and 9 are also being pushed out by the time-now line. In most real project schedules, filters and other techniques may be needed to isolate information like this; but in our small example, we can simply “eyeball” the time-now line and see valuable information. Task 9 starts the critical path shown in red tasks.

 

The project start date was August 1. The status date is September 1. Tasks 2, 5, and 9 show gaps from the predecessor to their starts. in the case of Task 2 the cap is to the start of the remaining work. This gap is caused by the time-now being set to September 1 with all remaining work starting after that. The critical path is being pushed by time now.Figure 1

 

A slightly different setup for that same small example [see Figure 2] shows something interesting. The time-now line is still at the beginning of September. But now there is a gap between time-now and work on the critical path. This is an unusual situation and should be investigated for the root cause. It is possible this is an accurate portrayal of the situation, but regardless of the cause, it must be verified and explained.

 

Time now is still at September 1. There is a gap on the critical path at the start of Task 9 which, in this case, is caused by a Start-No-Earlier-Than constraint.Figure 2

 

In yet one more variation [see Figure 3], we see that a broken link results in Task 8 ending up on the time-now line. A task without a predecessor will be rescheduled to start at the earliest possible time (if the task is set to be “As Soon As Possible”). And the earliest possible time is the time-now line; the beginning of September. Just as broken things fall to the floor in real life, “broken things” fall to the time-now line in a schedule. Un-started work can land there. Un-finished work can land there. And un-linked work can land there.

It is further possible to see that Task 2 has had an increase in the remaining duration that has driven it onto the critical path. Task 2 at this moment is the most important task on the entire project. A slip to Task 2 will drive out the end date for the entire project. One question that needs answering is what is holding up Task 2?

If the display had been sorted by increasing total float/slack and the usual cascade by date, then the critical path would be starting at the upper left-hand corner; like the critical path in this example. The action on the project is almost always on the time-now line and the most important action, when sorted as described, will be at the upper left-hand corner.

 

Task 2 is now driving the critical path. Task 8 has fallen back to the time now line. The constraint on Task 9 has been removed.Figure 3

 

So, a walk down the time-now line can help us see the critical path action, find broken parts of the schedule, and locate unusual circumstances that need our attention. Our recommendation is to look at the time-now line any time there is data being changed in the IMS. This will help you catch issues early and keep the schedule cleaner.

Along the IMS Time-Now Line Read Post »

Scroll to Top