Earned Value Management System (EVMS)

Project Management: Earned Value Consulting; Could You Use Some?

, , , , ,

Failed Projects

A recent article discussed the results of a survey on the reasons that projects failed. The definition of failure was that the project was abandoned. Abandonment does not occur frequently in the world of government projects; especially defense projects where there should be strong “must have” needs driving the project. These projects tend to persist until completed even though the outcomes are not satisfactory. But there is a lot to learn from the list of reasons for failure.

Of the sixteen reasons listed, the top four had to do with changes to the environment that had given rise to the project. For example, changes in the company priorities was the most often cited reason for abandonment. In that same vein were issues with changing objectives and inaccurate definition of requirements. These types of failures are not topics for this blog since they do not immediately involve execution of the project.

Execution Problems

Lower on the list of those environment related reasons for failure were the ones more related to execution problems. These are of significant interest to a project management using an earned value consulting company such as Humphreys & Associates (H&A). These reasons related more to issues of poor project management that could have been corrected. In this area were reasons like “poor change management,” “inaccurate cost estimates,” “inaccurate time estimates,” and “inexperienced project management.”

The answers given in a survey situation depend very much on the mindset of the person responding. Is the reason really “inaccurate cost estimates” or should it have been “failure to execute to the estimate”? How many times have you seen a problem in execution “swept under the carpet” as being an inaccurate estimate or plan? One of these two answers points to the estimating system and process while the other points to project management. The estimates were generated; and, at some point, they were deemed to be sufficiently detailed to launch the project. If a scrubbed and blessed estimate is “inaccurate” that would still be a failure of project management. If the problem were really a failure to execute, then how easy would it be to blame the problem on poor estimates? This blog will discuss the cited failures as if they were execution failures.

Earned Value Management (EVM) Consultant Specialists

There are situations in life where the need for specialized advice is common and well accepted by us all. When your doctor is unsure of the medical issues, the doctor will send you to a specialist. The reason is obvious. The specialist has learned so much more about a specific problem and has so much experience diagnosing and treating the problem that it would be foolish not to secure the services of that specialist. In fact, it might be malpractice. A project management consultant can be thought of much like a medical specialist.

There are similar situations in business where the need for specialized knowledge is critical. Large companies tend to have in-house legal departments to cover the day-to-day legal issues and tasks that are central to their businesses. However, the need to go to outside counsel for large or unusual issues is accepted. Companies do not hesitate to engage the services of outside law firms to help them through troubled times. Project management consultants are like outside counsel.

What if there were a project management or earned value management situation you have never encountered before? A good example would be the times that H&A has been called in to help clients navigate the unhappy circumstances of needing to go over-target. Going through the over-target-baseline (OTB) or over-target-schedule (OTS) process is not a common experience. It is a tense time when careers can be on the line and the company reputation might also be at risk. It takes specialized knowledge to get it right. In some cases, it even takes the objective view of an outsider to help make the right decisions.

Specialized Knowledge

Another example of specialized knowledge being crucial is when the customer has deemed some issue on the project to be deficient. In some situations, a customer’s Corrective Action Request (CAR) can result in cost penalties and damaged reputations; possibly even worse consequences could result. Engaging the services of an EVM consultant with experience in identifying problems, building Corrective Action Plans (CAP)s, and leading or helping implementing the corrective actions is often a valuable and necessary action. Ask yourself how smart it would be to assume that those who were involved in causing the issue would be capable of creating a satisfactory solution.

These scenarios are aligned with the idea of project management consulting being something you only need in a crisis. There are other non-crisis needs for specialized support. Often H&A is engaged simply to help a client prepare a proposal. A proposal situation puts heavy demands on the company staffing levels and can require areas of specialized knowledge not available in the company. What if the company has never created a fully compliant Integrated Master Schedule (IMS) and they could use help the first time? What if there are not enough trained and experienced schedulers to work on the proposal? What if the company does not have a documented project management system?

Make or Break Opportunities

Projects can be huge and risky. They can be make-or-break opportunities to a company. Where so much can depend on good project management, smart companies recognize the need for an outside opinion and outside talent. Just like the internal legal department, the internal project management group sometimes needs to call on outside subject matter experts. While it might be obvious, let’s look at some reasons why this is true.

There are more ordinary everyday reasons to engage a project management consultant. Perhaps an organization just managed to win a new project bigger than any they have won before. In this case, they may not be ready to handle the project in terms of experience, systems, and even just talented headcount. A project management consulting company such as H&A can bring solutions to your earned value woes. It can also provide temporary training staff to get things going until the client is ready to take over.

Poor Communication

Let’s get back to the survey of reasons that projects failed. Are there issues on the list where project management consulting could have made a difference? Imagine an improved project management process and staff after a period of consulting to support creating or improving systems and training personnel?

The fifth most frequent reason for failure is “poor communication.” A good project management system with trained personnel is all about communication. Communication of plans, communication of progress, communication of issues, and communication of corrective actions are all actions required in a project management system. Quite often the problem of “poor change management,” cited as the sixth most common reason for failure, is reduced or eliminated after using the consulting services of a specialist?

What about the twelfth cited problem of “inadequate resource forecasting”? Would a well built and maintained resource-loaded Integrated Master Schedule (IMS) go a long way in providing forecasts of resource needs and the impacts of not having the resources? In fact, a proper IMS would help with several of the cited reasons for failure, such as inaccurate duration estimates. In fact, the application of a process, such as Schedule Risk Analysis (SRA), with the help of an experienced consultant can identify such issues in advance while there is still time to take action.

Earned Value Training

Disregarding the threat of failure as a motivator, the need for constant improvement should be enough reason to consider a project management consultant. We can all laugh at the time-worn clichés of “not-invented-here” or “we’ve never done it that way;” however, these are clichés for a reason. There is resistance to outside help and there is resistance to change. But outside help can be a great logjam breaker. An experienced and knowledgeable consultant can be your voice when you need someone who has, to use another cliché, “been there and done that.”

In fact, our consultants can laugh when they say they have “been there” and they have more than a T-shirt to prove it.

Project Management: Earned Value Consulting; Could You Use Some? Read Post »

Humphreys and Assoc Reviews 7 Principles of Earned Value Management Tier 2 System Implementation Intent Guide

, , , , , , ,

In this video we review the 7 Principles of Earned Value Management Tier 2 System Implementation Intent Guide published by the Assistant Secretary for Preparedness and Response, or ASPR.

This Guide is primarily used by the Biomedical Advanced Research and Development Authority, or BARDA, on countermeasure R&D contracts that have a total acquisition cost greater than $25 million and a Technical Readiness Level of less than 7.

7 Principles of Earned Value Management Tier 2 System Implementation Intent Guide -- EVM Cross Reference Guide

Humphreys and Assoc Reviews 7 Principles of Earned Value Management Tier 2 System Implementation Intent Guide Read Post »

Agile/Scrum Ceremonies and Metrics Useful in EVMS Variance Analysis and Corrective Action

, , , , , , , , , , , , , , , , , , , , , , , , , ,
Agile Scrum EVMS

P. Bolinger, CSM October 2016
Humphreys & Associates

How can Agile/ Scrum be used to support EVMS Variance Analysis and Forecasting in a way that provides program managers with cost and schedule integrated information for no extra effort?

The discipline of EVMS and the Agile/Scrum practices have several touch-points that are covered in two major documents: NDIA IPMD Agile Guide March 2016, and PARCA Agile and EVM PM Desk Guide. Neither of these documents, as yet, drives to the level of specifics when it comes to best practices for use of Agile to support EVM Variance Analysis and EVM Forecasting.

Looking at the literature for Agile/Scrum, we know that there are recommended ceremonies that are conducted at various levels of the product structure and at different times during the project life cycle. These ceremonies are supported by many discussions of the metrics that can be collected at each ceremony and their potential use in managing the technical work of development within the Agile/Scrum framework. But where do these ceremonies potentially support EVMS Variance Analysis and Forecasting?

Now suppose we are presented with a control account that has exceeded the EVMS thresholds for cumulative cost and schedule variances. Wouldn’t it be great to have at our fingertips the underlying data from the process? In this case we might find, for example, that the Velocity is less than that needed to meet the end goal, the story cycle time is longer than desired, the pass/fail ratio is not favorable, too many team members have been absent in the last Sprint, the number of disruptions has been excessive, and the work to accomplish the stories is higher than estimated. It is not difficult to surmise the outcome would likely be a behind schedule and overrun condition in the EVMS. These data measures would provide the fodder for deep diving to the root cause and impact statements.

Where would we get that information?

Let’s start with the Agile/Scrum ceremonies. The particular Agile/Scrum ceremonies that we find conducted during the project are:

Backlog Refinement. This ceremony can be nearly continuous. It involves redefining the backlog of development work (scope), the prioritization or re-prioritization of that work, and potentially the assignment of responsibilities for the backlog.

Release Planning. This is a recurring ceremony aligned with the release cadence for the project. It involves establishing the capabilities and features of the product and when they will be released.

Sprint. This is a short time-defined effort to accomplish the design, code, and test of some subset of the product. The Sprints are controlled by the self-managing teams.

Daily Scrum or Standup. This is a daily (recommended) team meeting to discuss what has happened, what roadblocks exist, what is planned for the day, and other necessary items.

Sprint Review. The session in which the team products are demonstrated to the owner and self-off is accomplished.

Sprint Retrospective. A meeting of the stakeholders to discuss what went right (or wrong) during the Sprint and to define improvement actions that are needed.

The relationship of these Agile ceremonies with EVMS might look like this:

Agile/Scrum Ceremony

Agile Purpose

Relationship to EVM Variance Analysis, Root Cause Analysis, Corrective Action Planning & Follow-up and Forecasting

 

 

 

Backlog Refinement Manage, estimate, prioritize, and organize the product backlog in an on-going routine. Estimating – impacts the EVMS ETC and EAC as well as durations of efforts.
    Prioritizing – in response to issues is corrective action management.
    Organizing the backlog could be a form of corrective action effort.
     
Release Planning Establishing the contents and timing for releases of product. Updates could be part of corrective action planning in response to issues. Creation of new work packages. Changes to planning packages and SLPPs would also.
     
Sprint Short time-box performance unit. Work is done in Sprints. Below the work package. Short span measurement period is possible.
     
Daily Scrum and Stand-up Make short term plan, adjust to issues, discuss problems, clear roadblocks. Much of the daily action would relate to root cause analysis and corrective action planning although the time-frame is very short and the issues may be too small to individually impact feature work package or the Epic control account.
     
Sprint Review Demonstrate the product, update released work, make changes to product. This would relate to corrective action planning and follow-up. Issues would be found here that would impact risks, ETCs, corrective actions, performance metrics.
     
Sprint Retrospective Reflect on the project, progress, people processes, what was good, what was bad, and take actions to improve. This should be the richest source of supporting information for EVMS root cause & corrective action within the VAR realm. Very timely for variance analysis as it happens potentially many times during work package (feature) duration.
Feature Retrospective (not one of the basic ceremonies) Review situation regarding technical scope deficit. Reflect on the project, progress, people processes, what was good, what was bad, and take actions to improve. Because this only happens at the end of the feature it is limited in value for variance analysis timeliness. Any lessons learned can only be applied to future feature work.

But where is the meat? Where do we get actionable data or at least data we can analyze to decide what management efforts are required?

There are numerous potential metrics that can be collected during these ceremonies. These metrics can form the basic data set that could be analyzed to define the root cause of cost and schedule variances. In addition to isolating the cause of issues, within some of these ceremonies the impact of the issue on the Sprint, or Feature, or team may be made. Certainly, these metrics can be used as the basis for projecting future workload and performance.

The total number of potential metrics is not known. In this paper, we looked at 17 metrics and considered what the data might mean. The results of this review are contained in this matrix:

Metric

Type of Measure

Discussion

Sprint Burn up/Burn Down Backlog Value of backlog remaining for Sprint. Decrease is expected when work is done. Increase means work increased. Burn up can include total completed plus remaining; a great metric.
Feature Burn Up/Burn Down Backlog Value of backlog remaining for Feature. Decrease is expected when work is done. Increase means work increased or shifted.
Customer support requests received. Disruption Number of instances. Unplanned interruptions by customer can lower the output of the team if excessive.
Disruption measures Disruption How many and what type (except customer support requests). Higher disruptions impact team efficiency.
Estimate Accuracy (Sprint or Feature) Estimating Measure of budgeted value (estimated value) for the Stories in the Sprint or Feature versus the actual cost (calculated cost) of the Stories when done. Related to team size.
Discovered work Estimating Emerging work discovered during the Sprint. Will translate to extra effort in future if adopted into backlog.
Exceeds WIP Limits Management If WIP limits are set on team or individuals then exceeding set limits will impact efficiency and output.
Retrospective Action Log Management Count of improvement actions listed in Retrospective. Increasing count means issues are not being resolved.
Attendance Management Comparison of actual hours worked by team compared to baseline expectations in plan.
WIP Productivity Measure of the number of stories or points in WIP at any time. WIP growth can indicate bottlenecks and inefficiencies.
Velocity Productivity Measure of the amount of work (Stories or Points) accomplished during a time period. Higher velocity means greater throughput per person/team.
Stability measures Productivity Comparing Sprint by Sprint basic measures from this list. If there is high variability between Sprints in measures, then future is unpredictable.
% Tests Automated Productivity Higher automated testing should increase efficiency & decrease cycle time.
Defects found by team Quality Number of bugs reported during team effort. Measures quality of work. Higher bug incidence translates to lower output and higher costs.
Defects found by customer Quality Number of bugs reported by user/customer. Measures quality of work delivered. Higher bug incidence translates to lower customer satisfaction and higher rework costs.
Pass/Fail (Re-do) measures Quality How does the rate of success in testing compare to the number of attempts? High success rate should mean greater output and efficiency.
Cycle Time Schedule Time from start of a story to complete. Short cycle time is desired.

Let us continue the theme of the behind schedule and overrun control account and look at what information would be available for support to developing the estimate-to-complete. An updated and refined backlog would have the scope of work remaining for the control account. The updated release plan would have the timing for the deliveries to be made in the control account. The metrics collected about the effort expended per accomplished story or story point would provide a factor for projecting future real-work hours. Planned corrective actions and improvements would tell us how we might expect improvement to the quality and improvement in the speed or cost of work. The insights available from a full set of metrics are impressive.

Does a project have to collect all of these metrics? If not all then which ones would be the right ones? Questions like that would be answered by the project management team analyzing their prior experience and the particular challenges of the project. The team would establish a data collection plan, likely described in their Software Development Plan or Program Management Plan that would explain the metrics, meaning, and frequency along with their purpose. With a clear understanding of the technical data to be collected and analyzed, the Control Account Managers would not have a difficult task to define how they would use that data in developing Variance Analyses and generating well-considered Forecasts. In fact, these tasks should be much simpler with the data in hand.

Agile/Scrum Ceremonies and Metrics Useful in EVMS Variance Analysis and Corrective Action Read Post »

Who Owns EVM? Programs or Finance?

, , , , , , , ,
earned value management: finance department or programsI have read several Earned Value Management (EVM) reports, papers, and articles that debate what company organization should “own” EVM and the company’s Earned Value Management System (EVMS). These debates most often mention the programs’ organization and the finance department as common EVM “owners.” The majority opinion seems to be that because EVM is a program management best practice it belongs in programs. A minority opinion is that because EVM is denominated in dollars, schedule included, and because EVM reports are financial in nature, EVM belongs in the finance department. Before we dive into this debate, a summary of the responsibilities of a Chief Financial Officer (CFO) and of the head of programs is useful. In our company A and company B examples to follow, both the CFO and the head of programs report to the company president.

WHAT ARE THE DUTIES OF A CHIEF FINANCIAL OFFICER ( CFO)?

A CFO has three duties, each measured in the time domain. The first duty of the CFO is as the company’s controller and is responsible to accurately and honestly report past company financial performance. The CFO is also responsible for the current financial health of the company – to insure that today’s decisions create rather than destroy value. And lastly, the CFO must protect the company’s future financial health and that all expenditures of capital maximize future financial health. Every business decision, especially those of the CFO, are either good decisions (are accretive – increase shareowner value) or are bad decisions (are dilutive – destroys shareowner value).

WHAT ARE THE DUTIES OF THE HEAD OF PROGRAMS?

The head of programs is typically a Vice President or higher and all program and project managers report to him or her. The head of all programs has profit and loss responsibility for his or her portfolio of programs and projects. In addition, each program is responsible for achieving the technical, cost and schedule requirements of the contracts it is executing on behalf of its customers.

A TALE OF TWO COMPANIES:

I will now describe first-hand experiences with two companies and how each company decided who should “own” EVM.

Company “A” had EVM assigned to the finance department. All EVM employees were overhead, even those assigned to a program. A new CFO arrived and quickly decided to reduce indirect costs, declaring that he was “coin-operated.” The new CFO terminated the employment of all EVM employees. Each program attempted to create an EVM branch office but failed. A level 3 CAR enumerating EVM deficiencies was issued and the CFO was fired. A second “new” CFO arrived and agreed to transfer EVM to the head of programs. The head of programs was instrumental in changing the disclosure statement making EVM personnel assigned to a program a direct charge to that program / contract. The head of programs created a Program Planning and Control (PP&C) organization and demanded all PMs and their program members to quickly learn, use and master EVM. A program control room was built with five screens. Daily 2:00 pm EVM data-driven reviews were held on short notice. These daily reviews became known as “CAM Bakes.” The EVM and program management culture changed quickly and dramatically at Company “A.”

Company “B” had EVM assigned to the CFO who was as “coin-operated” and unaware of EVM as the first “new” CFO of Company “A.” The culture of company “B” was very hostile to EVM, so it probably did not matter who “owned” EVM. The company failed 16 of 32 guidelines and was decertified. Significant withholdings were imposed and the company’s reputation was damaged. Several top managers hostile to EVM “sought employment elsewhere.” A new CFO arrived who was also “coin-operated” but expert in EVM. The new CFO formed a partnership with the head of programs. The new CFO was as much a PM as he was a CFO. The new CFO told his direct reports assigned to each program to “make the program managers successful.” And they did exactly that.

The new CFO understood that the company was the sum of all its contracts and that every dollar flowed from its customers. The EVM and program management culture at Company “B” changed rapidly.

Who Should “Own” EVM? Programs or Finance?

Returning to our original question of who should “own” EVM, the majority theory is that the Programs’ organization should “own” EVM. All else equal, I tend to agree with this theory.

However, while theory is suggestive, experience is conclusive. My experience at Company “A” proved that a strong programs’ leader could change the EVM and program management culture of a company rapidly. My experience at Company “B” proved that a CFO could “own” EVM and be successful at changing the company’s EVM and program management culture. The CFO and the head of programs must form an EVM partnership no matter who “owns” EVM.

Who “owns” EVM at your company?

Robert “Too Tall” Kenney
H&A Associate

Who Owns EVM? Programs or Finance? Read Post »

EVM (Earned Value Management) vs. Agile Project Management

, , , , , , , , , , , , ,

This article provides an introduction to the differences between an Earned Value Management System (EVMS) and Agile approaches on projects, and isolates the challenges of implementing an EVMS on a project where the project management has chosen to follow an Agile approach to the development work. The article explores the principles of EVMS and of Agile, and contrasts them to show where there are inherent conflicts. The article then discusses how the conflicts can be mitigated so that the benefits of both the EVMS and Agile can be obtained from a joint implementation.

Controlled Planning with EVMS

Controlled Planning with EVMS

Earned Value Management (EVM) Background

Earned Value Management is a 50 +/- year old methodology based on widely accepted principles that applies documented, systematized practices to support the processes of organizing, planning, directing, and controlling large complex projects, of any nature, which contain a high degree of uncertainty.

An EVMS is structured compliant to 32 guidelines that define what a project management information system should be capable of doing to support the program management team. Within the 32 guidelines there is a subset of generally recognized core principles. The core principles are:

  1. Organize the entire scope of the project using a Work Breakdown Structure (WBS).
  2. Organize the project team using an Organization Breakdown Structure (OBS).
  3. Integrate the project work with the project team to create management control points (Control Accounts).
  4. Schedule the project work in the Control Accounts across the entire project duration at the appropriate level of detail.
  5. Establish time-phased budgets for the scheduled work in the Control Accounts.
  6. Establish the scope/schedule/budget baseline as the Performance Measurement Baseline (PMB).
  7. Authorize the scope/schedule/budget and control the start/stop of work.
  8. Periodically measure the schedule and the value of completed work and determine the Earned Value.
  9. Record direct costs (actual costs) and summarize into the Control Accounts.
  10. Compare planned, accomplished, and spent to analyze the performance and associated variances.
  11. Develop realistic time and cost estimates for the remaining effort in the Control Accounts.
  12. Rigorously control changes to the Performance Measurement Baseline.

The EVM concept presented in these guidelines is a sound management approach, that once incorporated on any type of program, whether research and development, construction, production, etc. provides all levels of management with early visibility into cost and schedule problems.  Earned Value Management now appears as a contractual requirement on programs world-wide.  Primary EVM users include the United States, Europe, England, Canada, Australia, China, and Japan. It is a requirement of many U.S. Government agencies, including the Department of Defense (DoD), the National Aeronautics and Space Administration (NASA), the Department of Energy (DOE), the Intelligence Community, the Department of Homeland Security (DHS), the Federal Aviation Administration (FAA), the Department of Transportation (DOT), Health and Human Services (HHS), and others.

EVMS has been adopted by companies in situations where it is not a contractual requirement so that they can gain the discipline and benefits of the structural management approach discussed in the guidelines.

 

evms 2

Flexible Planning with Agile

Agile Background

Agile is a 20 +/- year old approach to applying a mindset that values the use of small, empowered, self-organizing, multi-functional teams, mainly in software development, to establish a test driven product development effort. This uses a series of short, rapid incremental builds within projects with a high degree of uncertainty to achieve shorter development times, lower costs, and products more closely aligned with customer requirements.

Agile does not usually appear as a contractual requirement. The concept is adopted by companies and organizations with the belief that a better product will be produced faster, and with less expense, using this approach than if traditional approaches were followed.

There are a core set of principles for Agile that were initially established in the copyrighted Agile Manifesto. These delineated core principles are:

  1. Early and continuous product delivery.
  2. Deliver working software (product) frequently.
  3. Expect change and respond positively to change.
  4. Developers and project business organization (PMO) work together.
  5. Product-focused build teams are at the core.
  6. Support self-organizing teams – trust among peers.
  7. Encourage face-to-face discussions (involve the user/customer).
  8. Working software is the measure of progress.
  9. Maintain a constant sustainable pace of development.
  10. Simplify the process and the product.
  11. Put the highest value on technical excellence.
  12. Improve team effectivity.

So How Does Agile Work?

The Agile mindset or approach is implemented through a process of defining the product backlog into smaller and smaller subsets of work that are structured in a top down fashion. At the lowest level of product backlog, the work elements or requirements can be prioritized and assigned to teams. The self-organizing teams pull work from the backlog and work the tasks to completion in a series of short, time-fixed Sprints or iterations. Sprints are often from 2 to 4 weeks long.

Because the teams are self-organizing, there is no team manager or team lead. The teams work as a group and only pull from the backlog at the last possible minute, and do minimal planning for each Sprint. If the product backlog is properly deconstructed and defined into user stories, then the planning meeting for an entire 4 week Sprint can be accomplished in a few hours.

The teams design, code, test, integrate, and deliver functionality in every Sprint. Since tested product is output every few weeks, all on the project can see the product being created and can contribute along the timeline, as needed, to provide a complete finished product.

The product owner embodies the customer’s perspective and either accepts or rejects the team’s work.  At the latter point of each Sprint, the tested product is demonstrated to the product owner.

High Level Side-by-Side

The two approaches are contrasted in the chart shown below. The EVMS is a methodology that is highly documented and highly systematized, while Agile is just the opposite. It is more of a mindset than a methodology with the preference not to have significant process documentation.

The EVMS is applied to entire projects and contracts, while generally Agile is applied to software portions of projects.  However, it could also be used on other development work.

The EVMS is usually a contractual requirement with significant implementation and operation constraints while Agile has none of these. As a contractual requirement, the EVMS carries with it the option for customer reviews and the threat of non-compliance, which entails penalties.

EVM Agile
Methodology Mindset
Documented Self-defined
Systematized Self-defined
Any type of project Software development (mainly)
High degree of uncertainty High degree of uncertainty
Applied to the entire project Applied to portions of the project
Often a contractual requirement Adopted not required

Lower Level Side-by-Side

In addition to the high level side-by-side, there are significant differences within the details of the two approaches. These are shown in the side-by-side table below.

Agile EVMS
Minimal documentation More documentation
Plan at last moment Plan ahead to end of project
Scope is flexible Scope is baselined and controlled
Expect and embrace change Avoid and/or control change
Schedule (Sprint) is fixed.  Timebox ends the Sprint. End the package when the work is done.
Budget is secondary Budget is baselined and controlled
Cost collection is not mentioned. Cost collection at the right level is critical

Accommodate and Capitalize on Differences

It is possible to implement Agile along with an EVMS if the EVMS application is set up to accommodate the differences and capitalize on them.

For example, the main reason that Agile’s embrace of change is a potential problem within an EVMS is because often the EVMS is used to plan too far in advance, and then reacting to change is difficult and expensive. If short term planning in the EVMS can be coordinated with the Agile planning, then the two can coexist.

The Agile free acceptance of scope changes within the backlog runs counter to the EVMS imposition of baseline change control. But if the EVMS baseline can be carefully set at a work level above the busy lowest level ups and downs, the impact to baseline change control is manageable.

A surprising chance to capitalize on Agile, within the EVMS, is found in the Scrum team approach in Agile where the team breaks work down into tasks far below what would normally be done in an EVMS, and then meets daily to update progress and provide corrective action. This low level constant attention means that the EVMS benefits from a better look at real progress as assessed by the real performers.

Not all the compromise needs be on the EVMS side of the equation. The Scrum team operations will often be defined to have the least possible recording of what happens during the Sprint. Since the product is king, then only the product really matters. But that misses the opportunities to capture the actions of the team for analysis, and use in upgrading their skills later. Necessary compromises would include some additional recording of the daily actions of the team and capturing the progress and problems. These would then be used in the EVMS functions of performance measurement, variance analysis, and corrective action planning.

One other compromise in the Agile realm that would be needed is the adoption of some minimum documentation of processes so that team operations can be repeatable and stable. Even a self-organizing team cannot change the way they work every time it wishes. That would raise the risk of a chaotic work environment.

These topics are recapped in the table below.

Agile EVMS Accommodation
Scope is flexible Select a higher level package for the baseline
Change is expected and embraced Have the shortest possible planning horizon
Plan at the last possible minute Have the shortest possible planning horizon
Daily Scrum Stand-up Meeting Collect the data and use it for performance measurement
Sprint Review Meeting Use for periodic measurement and analysis
Sprint Retrospective Meeting Use in Corrective Action Plans
Lack of documentation Add minimum documentation to stabilize team operations

Bottom Line

Implementing an EVMS is a challenge itself. Implementing Agile is a challenge too; perhaps a more difficult challenge. Implementing the two approaches side-by-side can seem impossible. But it is possible and even beneficial if done in a way the makes needed accommodations in both arenas for the project’s benefit.

EVM (Earned Value Management) vs. Agile Project Management Read Post »

Scroll to Top